MahaRERA Property Intelligence · Pune

Pansare Paradise Phase 1

P52100015622 · NEAR ANAND NAGAR · promoter Hari Om Builders

Certificate SignedDue 30 Sep 2020

Delivery & Registration

MahaRERA registrationP52100015622
Registered on15 Mar 2018
Promoter-declared completion30 Sep 2020
Current statusCertificate Signed
Against todayabout 70 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Pansare Paradise B Wing1G+731 Mar 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at NEAR ANAND NAGAR, PABAL ROAD, Shirur, Pune, 412210. Per the filed land record, the plot is bounded to the north by SN 45B and road, to the south by SN 46 A and certified school, to the east by SN 45A H7 2 and to the west by SN 45A H1A 3. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~55 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)55 km
Kharadi / EON IT Park55 km
Magarpatta / Hadapsar IT59 km
Pune Junction / city centre62 km
Baner–Balewadi belt70 km
Hinjewadi Rajiv Gandhi IT Park72 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shirur

Advik Paradise
possession by Aug 2026 · NG Developers
1 Sadabaug Phase-I
possession by Sep 2026 · Lalita Dharamchand Phulfagar
1 Sadabaug Phase-II
possession by Sep 2026 · Lalita Dharamchand Phulfagar
1 Sadabaug Phase-III
possession by Sep 2026 · Lalita Dharamchand Phulfagar
Babji Market
possession by Sep 2026 · Pyramid Constructions
Rayat Residency
possession by Sep 2026 · Soham Constructions AND Developers

Other RERA-registered projects in Pune

Pant Sarathi Builders LLP
possession by Dec 2028 · Pantsarathi Builders LLP
Papa Imperio
declared completion Dec 2019 · Anup Indrapal Bashani
Papa Mamta Residency
declared completion Jun 2019 · Anup Indrapal Bashani
Paradigam Vandan
possession by Feb 2028 · Paradigm Developers Private Limited
Paradise
declared completion Jun 2024 · Amarnath Buildcon
Paradise - B2 And B3
declared completion Jun 2026 · Kevin Properties

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026