Pune/Project record

MahaRERA · the public record

PARIJAAT RESIDENCY

TALEGAON DABHADE · JAGDAMBA REALTORS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100003107

Delivery and registration

When is the project declared for completion?

PARIJAAT RESIDENCY is registered with MahaRERA as P52100003107 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

39months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100003107
Registered on04 Aug 2017
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PARIJAAT RESIDENCY record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Jagdamba Realtors is the promoter of record on 12 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

12projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PARIJAAT RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
A11G+930 Jun 2022
A21G+930 Jun 2022
A31G+930 Jun 2022
A41G+930 Jun 2022
A51G+930 Jun 2022
B1G+3-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at TALEGAON DABHADE, TALEGAON CHAKAN ROAD, Mawal, Pune, 410507. Per the filed land record, the plot is bounded to the north by S NO 23, to the south by S NO 14, to the east by S NO 24-2 and to the west by S NO 20. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~17 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park17 km
Baner–Balewadi belt22 km
Pune Int'l Airport (Lohegaon)30 km
Pune Junction / city centre30 km
Kharadi / EON IT Park34 km
Magarpatta / Hadapsar IT35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Talegaon Dabhade

Hillcrest
possession by Oct 2026 · Swapnashilp Buildcon
Greendale ENA
possession by Dec 2026 · M/s. Karpe Construction Company
Indraprasth
possession by Dec 2026 · J V Buildcon
Krishna Mahel
Deregistered by MahaRERA · possession by Dec 2026 · Mahesh Developers Ltd
Panoramaa
possession by Dec 2026 · Kakade Properties
SAI Ganesh
possession by Dec 2026 · Aditya Developers

Major developers building in Talegaon Dabhade

Other RERA-registered projects in Pune

Parijat
declared completion Jul 2021 · Arunodaya Developers
Parijat
possession by Mar 2028 · M/S SRS Constructions
Parikshit
possession by Oct 2028 · Belvalkar Housing LLP
Parin Empire
declared completion Feb 2022 · Gote Bhilare Associates
Parishreya
declared completion Dec 2021 · NEW Front Prabhavee Ventures
Park Abhilasha- A,b,c Building
possession by Dec 2027 · Aaryan Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026