PHOENIX RESIDENCY

Porwal Park · PHOENIX INFRASPACE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100034724

Delivery and registration

When is the project declared for completion?

PHOENIX RESIDENCY is registered with MahaRERA as P52100034724 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100034724
Registered on20 Apr 2022
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PHOENIX RESIDENCY record 11 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Deregistered — MahaRERA has deregistered this project — it is off the register.
  • Filing progress reports — 11 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Phoenix Infraspace is the promoter of record on 31 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

31projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PHOENIX RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
PHOENIX RESIDENCY1G+631 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2024We have received First Building Sanction Plan on 28/09/2021. After getting said Sanction our architect noticed that there are some technicalities arose in the previous sanctioned b

Location, Land & Connectivity

Located at Porwal Park, Alandi Road, Haveli, Pune, 411006. Per the filed land record, the plot is bounded to the north by 30 Ft Road, to the south by S no 106 Hissa No 2, to the east by Plot No 35 and to the west by PlotNo 33. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre4 km
Pune Int'l Airport (Lohegaon)5 km
Kharadi / EON IT Park7 km
Magarpatta / Hadapsar IT8 km
Baner–Balewadi belt10 km
Hinjewadi Rajiv Gandhi IT Park15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Yerawada

Bluegrass Residences Tower III
possession by Dec 2026 · Sagitarius Ecospaces LLP
Belmont Lunar
possession by Mar 2027 · Prasad Balasaheb Shinde
Vaishnavi Ouranos
possession by Dec 2027 · Vaishnavi & OM Construction
Power Terrace
possession by Mar 2028 · Sapra Builders
River Vista
possession by Mar 2028 · Rahul Shubham LLP
Sheetal Park CO-Operative Housing Society LTD
possession by Mar 2028 · Belvalkar Housing LLP

Major developers building in Yerawada

Other RERA-registered projects in Pune

Phule Mansion CO-Operative Housing Society Limited
possession by Dec 2030 · Shreesha Landmark LLP
Piccadilly
declared completion Dec 2018 · Kumar Construction And Properties Pvt Lt
Pietra Lake Castle
declared completion Dec 2022 · Navranglal Shankarlal Kumawat
Pinewood Phase II
possession by Dec 2027 · Sainath Buildcon
Pinewoods
possession by Dec 2028 · Shree Samrajya Developers
Pinnacle
declared completion Dec 2023 · Jawaleshwar Construction

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026