MahaRERA Property Intelligence · Pune

PRAMMUKH RESIDENCY

P52100035103 · KADOLKAR COLONY · promoter Prammukh Builders

Certificate SignedDue 31 Dec 2023

Delivery & Registration

MahaRERA registrationP52100035103
Registered on10 May 2022
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Prammukh Builders is the promoter of record on 3 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Sales & Inventory

Of 21 homes filed with MahaRERA, 21 are sold/booked and 0 remain available (~100% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹6.62 Cr in agreement value so far. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 21 registered agreements, the effective carpet rate is ₹5,314/sqft (typical range ₹4,782–₹5,761) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 21 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
PRAMMUKH RESIDENCY1G+72131 Dec 2023

Unit mix on the filing: 21 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at KADOLKAR COLONY, KADOLKAR COLONY, Pune City, Pune, 410506. Per the filed land record, the plot is bounded to the north by 9 MTR COLONY ROAD, to the south by CTS NO 5084, to the east by CTS NO 5075 and to the west by 9 MTR COLONY ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park16 km
Baner–Balewadi belt21 km
Pune Junction / city centre30 km
Pune Int'l Airport (Lohegaon)30 km
Kharadi / EON IT Park33 km
Magarpatta / Hadapsar IT35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Prammukh Builders is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Prammukh Builders

Other RERA-registered projects in Talegaon Dabhade

One Lonvala
possession by Aug 2026 · Holy Valley Lifescapes Private Limited
Vaarivana Phase D - 2A
possession by Oct 2026 · Sanjivani Integrated Township LLP
Rohan Anand Phase II
possession by Dec 2026 · Rohan Builders & Developers Private
Abhimaan Homes Phase 3
possession by Dec 2026 · Rising Propcon LLP
Aditya Vardhan Heights
possession by Dec 2026 · Shree Ganesh Developers
City Plaza
Past its declared completion date · possession by Dec 2026 · Shreenathji Construction LLP

Major developers building in Talegaon Dabhade

Other RERA-registered projects in Pune

Pramukh Vivanta
declared completion Sep 2025 · Pramukh Developers
Pranali
possession by Dec 2028 · Gangotree Homes
Pranam
declared completion Jun 2025 · Primary Housing Corporation LLP
Pranam Towers
declared completion Mar 2024 · Amis Constructions LLP
Pranav
possession by Dec 2028 · Sonigara Ventures
Pranjal
declared completion Dec 2025 · Gajendra Dattatraya Pawar

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026