RAHUL CASTLE

MOSHI, BORHADEWADI, PIMPRI CHINCHWAD, PUNE · LAXMI CONSTRUCTIONS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100026870

Delivery and registration

When is the project declared for completion?

RAHUL CASTLE is registered with MahaRERA as P52100026870 and the promoter has declared completion for 30 Sep 2022.

30 Sep 2022

declared completion

48months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100026870
Registered on31 Oct 2020
Promoter-declared completion30 Sep 2022
Current statusCertificate Signed
Against todayabout 48 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RAHUL CASTLE record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RAHUL CASTLE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
5 TH FLOOR1G+631 Mar 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at MOSHI, BORHADEWADI, PIMPRI CHINCHWAD, PUNE, NEAR TO PUNE NASHIK HIGHWAY MOSHI TOLL PLAZZ., Haveli, Pune, 412105. Per the filed land record, the plot is bounded to the north by REMAINING PART OF GAT NUMBER 272-1-7, to the south by REMAINING PART OF GAT NUMBER 272-1-7, to the east by PUNE NASHIK HIGHWAY and to the west by REMAINING PART OF GAT NUMBER 272-1-7 AND ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Laxmi Constructions is the promoter on 3 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Laxmi Constructions

Laxmi Constructions
Past its declared completion datePune

Other RERA-registered projects in Moshi

Ideal Avenue
possession by Sep 2026 · Ideal Builders
Fortune Vedas Phase II
Not filing quarterly progress reports · possession by Sep 2026 · Fortune Vastusilpa Developers LLP
Gulmohar 24
possession by Sep 2026 · Royal Gulmohar Reality
Krishnai Residency
possession by Sep 2026 · Vastu Buildcon
Omkar Residency
possession by Sep 2026 · Prerna Group
Town Square
possession by Sep 2026 · Krupasindhu Developers

Major developers building in Moshi

Other RERA-registered projects in Pune

Rahul Downtown - Phase I
declared completion Jul 2025 · Paras Multispace LLP
Rahul Downtown - Phase II
possession by Apr 2027 · Paras Multispace LLP
Rahul Eastview II
declared completion Oct 2020 · Rahul Constructions
Rahul Park
declared completion Mar 2024 · Revive Homes LLP
Raichandani Aura
possession by Aug 2028 · Raichandani Constructions Private Limite
Raichandani One
possession by May 2029 · Raichandani Constructions & Develope

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026