30 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100004404

Delivery and registration

When is the project declared for completion?

RAJESH GOLDEN HOMES is registered with MahaRERA as P52100004404 and the promoter has declared completion for 30 Dec 2026.

30 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100004404
Registered on09 Aug 2017
Promoter-declared completion30 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RAJESH GOLDEN HOMES record 36 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Rajesh Builders is the promoter of record on 187 projects registered with MahaRERA, 34 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

187projects

registered with MahaRERA

34flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RAJESH GOLDEN HOMES in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
C WING1G+1031 Dec 2025
A WING1G+331 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at KAREGAON, BABULSAR ROAD, Shirur, Pune, 412220. Per the filed land record, the plot is bounded to the north by GAT NO 239 AND 240, to the south by GAT NO 259 AND 260, to the east by BABULSAR ROAD and to the west by GAT NO 254 AND 261. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~45 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kharadi / EON IT Park45 km
Pune Int'l Airport (Lohegaon)45 km
Magarpatta / Hadapsar IT49 km
Pune Junction / city centre53 km
Baner–Balewadi belt60 km
Hinjewadi Rajiv Gandhi IT Park62 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Rajesh Builders is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Karegaon

Nisarg Ansh
possession by Dec 2026 · Ganesh Vasant Walke
Shreeyog
possession by Dec 2026 · S K Developers
Playtor Ranjangaon Midc Phase 4
Not filing quarterly progress reports · possession by Apr 2033 · Sujit Santosh Bhansali
Playtor Ranjangaon- Phase 3
Past its declared completion date · declared completion Dec 2023 · Playtor Lifespaces Private Limited
Playtor Ranjangaon- Phase 2
Past its declared completion date · declared completion Jun 2022 · Playtor Lifespaces Private Limited
Indraprastha
declared completion Feb 2021 · Omkar Developers

Other RERA-registered projects in Pune

Rajeshwari Enclave
declared completion Feb 2022 · Rajratna Developers
Rajgad Heights
declared completion Dec 2024 · Unique Developers AND Builders
Rajgruhi Residency Tower C
declared completion Dec 2025 · Wellbuild Merchants Private Limited
Rajgruhi Residency Tower C1
declared completion Dec 2025 · Atria Constructions
Rajhans
possession by May 2027 · Joshi Buildcon Landmarks
Rajkala Dreams
declared completion Dec 2021 · Kavita Rajkumar Patel

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.