MahaRERA Property Intelligence · Pune

RAJESHWARI ENCLAVE

P52100013589 · promoter Rajratna Developers

Certificate SignedDue 28 Feb 2022

Delivery & Registration

MahaRERA registrationP52100013589
Registered on16 Oct 2017
Promoter-declared completion28 Feb 2022
Current statusCertificate Signed
Against todayabout 53 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Rajratna Developers is the promoter of record on 2 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
RAJESHWARI ENCLAVE1G+8-
CLUB HOUSE1G+1-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
28 Feb 202231 Aug 2021As per Pune Municipal Corporation revised project plan, Road and Amenity handover due to the Process our Project has been revised. Befored seven floor are 100% completed. P
28 Feb 202230 Jun 2019revised plan of pune corporation

Location, Land & Connectivity

Located at Haveli, Pune, 412308. Per the filed land record, the plot is bounded to the north by OLD FURSUNGI ROAD, to the south by HARPALE PLOT, to the east by HARPALE PLOT and to the west by WIDE ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~117 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park117 km
Baner–Balewadi belt123 km
Pune Junction / city centre133 km
Pune Int'l Airport (Lohegaon)134 km
Kharadi / EON IT Park137 km
Magarpatta / Hadapsar IT138 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Fursungi

Simplicity Phase 4 - A Wing
possession by Jul 2026 · J K P Developers Unit NO 2
Tranquility Annexe C Wing
possession by Jul 2026 · K AND B Associates
Casalino Towers Phase 3
possession by Oct 2026 · Sai Siddhi Promoters & Builders
Silver Park - B Wing
possession by Dec 2026 · Hakke AND KAD Developers
Green Hive Plus Wing A4
possession by Dec 2026 · Ram India Shelters
Sahara Platinum
possession by Dec 2026 · Sahara Buildtek

Major developers building in Fursungi

Other RERA-registered projects in Pune

Rajeshwari Heights
declared completion Dec 2019 · Sandeep Govind Newale
Rajgad
declared completion Dec 2024 · S R K Prime
Rajgad
declared completion Jan 2024 · Global Developers
Rajgad 3
declared completion Dec 2023 · S R K Realty
Rajgad 5
declared completion Mar 2024 · S R K Realty
Rajgruhi Business Hub
declared completion Dec 2020 · Rajgruhi Business Hub

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026