MahaRERA Property Intelligence · Pune

Royal Palm

P52100004008 · promoter Vaishali Developers Builders

Certificate SignedDue 30 Dec 2021

Delivery & Registration

MahaRERA registrationP52100004008
Registered on07 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vaishali Developers Builders is the promoter of record on 11 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
A1G+6-
B1G+6-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Haveli, Pune, 411035. Per the filed land record, the plot is bounded to the north by Property of Namdeo bhau Borate, to the south by Property of Ganpat bhiku Borate, to the east by Property of Borate and to the west by Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park14 km
Pune Int'l Airport (Lohegaon)14 km
Baner–Balewadi belt14 km
Pune Junction / city centre17 km
Kharadi / EON IT Park18 km
Magarpatta / Hadapsar IT20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Akurdi

Pentagon Business HUB
possession by Sep 2026 · Cosmic Infrastructure
Mantra Meraki Phase 5
possession by Dec 2026 · Mantra Residential Akurdi Private Limite
Mantra Meraki Phase 6
possession by Dec 2026 · Mantra Residential Akurdi Private Limite
ONE Platinum
possession by Dec 2026 · Matrix Developers
Orchard Residences
possession by Dec 2026 · A & A Realtors
Vasant Estella
possession by Dec 2026 · Shrikrishna Wonder Properties

Major developers building in Akurdi

Other RERA-registered projects in Pune

Royal Palm
possession by Dec 2029 · Udayan Pravin Dhame
Royal Palms
declared completion Aug 2024 · G T Buildcon
Royal Pancham
declared completion Dec 2024 · Royal Developers
Royal Panchwati
possession by Jun 2027 · Royal Developers
Royal Paradise
declared completion Dec 2023 · Vineet Builders AND Developers
Royal Paradise
possession by Jun 2027 · Royal Properties

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026