Pune/Project record

MahaRERA · the public record

SADGURU HERITAGE

Ambegoan Bk · SB REALTY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

16units filed as unsoldInventory · 17 September 2026
31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
84registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100023640

Delivery and registration

When is the project declared for completion?

SADGURU HERITAGE is registered with MahaRERA as P52100023640 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100023640
Registered on24 Dec 2019
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SADGURU HERITAGE record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In SADGURU HERITAGE, ₹8.40 Cr of a declared ₹24.54 Cr estimated project cost is reported as incurred, about 34.2%, as at the last certified filing with MahaRERA.

34.2%

₹8.40 Cr

of ₹24.54 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In SADGURU HERITAGE, 30 of 50 homes filed with MahaRERA are recorded as sold or booked (24 with registered agreements and 6 booked), about 60%, and 20 remain available.

60%sold

30 of 50 homes

₹14.76 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹7.12 Cr (about 48%) is recorded as collected and ₹7.64 Cr as receivable. The project registers 84 homes in total, while this sold/unsold inventory filing covers 50 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 30 registered agreements, the effective carpet rate is ₹7,140/sqft, with eight in ten falling between ₹6,912 and ₹7,235 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1101660 sqft (61.36 sqm)₹38.15 Lakh
Floor 101001660 sqft (61.36 sqm)₹39.69 Lakh
Floor 111101660 sqft (61.36 sqm)₹39.69 Lakh
Floor 111102627 sqft (58.28 sqm)₹37.70 Lakh
Floor 111104912 sqft (84.75 sqm)₹54.82 Lakh
Floor 111107650 sqft (60.35 sqm)₹39.03 Lakh
Floor 2201660 sqft (61.36 sqm)₹39.69 Lakh
Floor 2202627 sqft (58.28 sqm)₹37.70 Lakh
Floor 2203629 sqft (58.42 sqm)₹37.79 Lakh
Floor 2204912 sqft (84.75 sqm)₹54.82 Lakh
Floor 3301660 sqft (61.36 sqm)₹39.69 Lakh
Floor 3302627 sqft (58.28 sqm)₹37.70 Lakh
Floor 3303629 sqft (58.42 sqm)₹37.79 Lakh
Floor 4404912 sqft (84.75 sqm)₹54.82 Lakh
Floor 5504912 sqft (84.75 sqm)₹54.82 Lakh
Floor 6601660 sqft (61.36 sqm)₹39.69 Lakh
Floor 6603629 sqft (58.42 sqm)₹37.79 Lakh
Floor 7701660 sqft (61.36 sqm)₹39.69 Lakh
Floor 7704912 sqft (84.75 sqm)₹54.82 Lakh
Floor 8804912 sqft (84.75 sqm)₹54.82 Lakh

The inventory filing also declares: 33 owner/investor-held and 1 not for sale.

What the filings record, home by home

Read from MahaRERA on 17 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 35 homes carry one, and 16 of the 84 are recorded unsold. Since we started watching this ledger, 6 homes have moved out of the unsold list, most recently on 08 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
1107650 sqftRs 44.90 lakh typical, over Rs 44.90 lakh to Rs 51.00 lakh6 filed on this stack, floors 1–9

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In SADGURU HERITAGE, 9 of the 16 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 15 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11 and 84 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Building A1G+118431 Dec 2022

Unit mix on the filing: 75 residential and 9 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2027Our project, registered in 2019, faced delays due to insufficient funds, challenging market conditions, and the impact of COVID-19. With the required funding now secured, we kindly

Location, Land & Connectivity

Located at Ambegoan Bk, Ambegaon Bk, Haveli, Pune, 411046. Per the filed land record, the plot is bounded to the north by Common land of S No 39 24, to the south by Common land of S No 39 24, to the east by Land Mr Oswal and to the west by Common road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~159 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)158 km
Kharadi / EON IT Park159 km
Magarpatta / Hadapsar IT162 km
Pune Junction / city centre166 km
Baner–Balewadi belt172 km
Hinjewadi Rajiv Gandhi IT Park174 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

SB Realty is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Ambegaon Bk

Amits Bloomfield Phase III - J AND K Building
possession by Sep 2026 · Amit Enterprises Housing Limited
Ankur Residency
possession by Oct 2026 · Ankur Developers
Astonia Royale Phase III - P Building
possession by Oct 2026 · Amit Enterprises Housing Limited
Airavat B Wing
possession by Nov 2026 · Ashtavinayak Developers
Rajyog C Wing
possession by Dec 2026 · Santosh Shankar Tathe
Deveshwar Tekadi- Phase I- Building: A,b,c,d,e
Not filing quarterly progress reports · possession by Dec 2026 · Mahadrishti Spaces LLP

Major developers building in Ambegaon Bk

Other RERA-registered projects in Pune

Sadguru Krupa B2
possession by Mar 2027 · Janai Developers
Sadguru Prasad
declared completion Dec 2024 · Sadguru Guru Krupa Developers
Sadguru Residence
declared completion Sep 2023 · Manoj Mandhare & Associates
Sadguru Residency
possession by Dec 2026 · MAA Pranaam Buildcon Private Limited
Sadhguru Homes
possession by Sep 2026 · Ashok Motiram Taras
Saffron Residency
declared completion Aug 2025 · Steadfast Landmark Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026