MahaRERA Property Intelligence · Pune

Sadguru Residence

P52100010778 · Yerawada · promoter Manoj Mandhare Associates

Certificate SignedDue 30 Sep 2023

Delivery & Registration

MahaRERA registrationP52100010778
Registered on31 Aug 2017
Promoter-declared completion30 Sep 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Manoj Mandhare Associates is the promoter of record on 8 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Sadguru Residence1G+5-

Complaints & Orders

5 complaints are on the MahaRERA record for this project, with orders passed in 5. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000008527526/02/2021Mr. Surendra Dnyaneshwar Kamble vs M/s. Manoj Mandhare and AssociatesThrough its Proprietor Mr. Manoj P. Mandhareorder passed
CC00500000008530306/03/2021Mr. Sunil Tukaram Kamble vs M/s. Manoj Mandhare and AssociatesThrough its Proprietor Mr. Manoj P. Mandhareorder passed
CC00500000008532517/03/2021Mr. Rajendra Tukaram Kamble vs M/s. Manoj Mandhare and Associates Through its Proprietor Mr. Manoj P. Mandhareorder passed
CC00500000008543008/04/2021Mr. Fayyaz Gayasuddin Shaikh vs M/S. MANOJ MANDHARE AND ASSOCIATES Through its Proprietor Mr. Manoj P. Mandhareorder passed
CC00500000008560931/05/2021Mr. Ravindra Namdeo Kamble vs M/s. Manoj Mandhare and Associates Through its Proprietor Mr. Manoj P. Mandhareorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202331 Mar 2023The project is 90% completed and Flats are allotted to land owners but there is no amount received from booking due to market issues. Major finances are invested by us in the proj

Location, Land & Connectivity

Located at Yerawada, Yerawada, Haveli, Pune, 411006. Per the filed land record, the plot is bounded to the north by CTS no 538, to the south by CTS no 639 and 643, to the east by CTS 772 665 657 and to the west by CTS no 574 to 580. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~112 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park112 km
Baner–Balewadi belt118 km
Pune Junction / city centre128 km
Pune Int'l Airport (Lohegaon)129 km
Kharadi / EON IT Park133 km
Magarpatta / Hadapsar IT134 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Manoj Mandhare & Associates is the promoter on 3 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Manoj Mandhare & Associates

Manoj Mandhare & Associates
FlaggedPune
Manoj Mandhare & Associates
Not filing quarterly progress reportsPune

Other RERA-registered projects in Yerwada

Bluegrass Residences Tower III
possession by Dec 2026 · Sagitarius Ecospaces LLP
Belmont Lunar
possession by Mar 2027 · Prasad Balasaheb Shinde
Vaishnavi Ouranos
possession by Dec 2027 · Vaishnavi & OM Construction
Power Terrace
possession by Mar 2028 · Sapra Builders
River Vista
possession by Mar 2028 · Rahul Shubham LLP
Sheetal Park CO-Operative Housing Society LTD
possession by Mar 2028 · Belvalkar Housing LLP

Major developers building in Yerwada

Other RERA-registered projects in Pune

Sadguru Residency
possession by Dec 2026 · MAA Pranaam Buildcon Private Limited
Sadhguru Homes
possession by Sep 2026 · Ashok Motiram Taras
Saee Arjun
declared completion Mar 2022 · Vishal Hariram Tapkir
Safal Onerio
declared completion Mar 2021 · Sanjay Dattatray Dapodikar
Safalya
declared completion Jun 2023 · Mohan Vijaykumar Damle
Saffron
declared completion Dec 2020 · Soba Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026