Pune/Project record

MahaRERA · the public record

Sai Empire H

Wadmukhwadi · M/s Sai Angan Empire LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100048924

Delivery and registration

When is the project declared for completion?

Sai Empire H is registered with MahaRERA as P52100048924 and the promoter has declared completion for 31 Dec 2023.

31 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100048924
Registered on24 Jan 2023
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Sai Empire H record 4 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Filing progress reports — 4 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sai Angan Empire is the promoter of record on 89 projects registered with MahaRERA, 11 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

89projects

registered with MahaRERA

11flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In Sai Empire H, 2 of 24 plots filed with MahaRERA are recorded as sold or booked, about 8%, and 22 remain available.

8%sold

2 of 24 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Sai Empire H in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Wadmukhwadi, Wadmukhwadi, Haveli, Pune, 412105. Per the filed land record, the plot is bounded to the north by By Remaining land out of Sr No 178, to the south by By Remaining land out of Sr no 178, to the east by By Remaining land out of Sr No 178 and to the west by By Remaining land out of Sr no 178. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Moshi

Ideal Avenue
possession by Sep 2026 · Ideal Builders
Fortune Vedas Phase II
Not filing quarterly progress reports · possession by Sep 2026 · Fortune Vastusilpa Developers LLP
Gulmohar 24
possession by Sep 2026 · Royal Gulmohar Reality
Krishnai Residency
possession by Sep 2026 · Vastu Buildcon
Omkar Residency
possession by Sep 2026 · Prerna Group
Town Square
possession by Sep 2026 · Krupasindhu Developers

Major developers building in Moshi

Other RERA-registered projects in Pune

Sai Empire I
declared completion Dec 2023 · Sai Angan Properties LLP
Sai Empire J
declared completion Dec 2023 · M/s Sai Angan Projects LLP
Sai Empire - Plot A
possession by Dec 2026 · Sai Angan Empire LLP
Sai Empire - Plot C
declared completion Jun 2025 · Sai Angan Empire LLP
Sai Enclave
declared completion Aug 2023 · Chandrakant Sarjerao Shinde
Sai Enclave
possession by Dec 2028 · Shreyash Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026