Pune/Project record

MahaRERA · the public record

SAI ICON

SANDVIK COLONY · M/S. K. K. Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

26 Jan 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

26 Jan 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100017404

Delivery and registration

When is the project declared for completion?

SAI ICON is registered with MahaRERA as P52100017404 and the promoter has declared completion for 26 Jan 2022.

26 Jan 2022

declared completion

56months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100017404
Registered on09 Aug 2018
Promoter-declared completion26 Jan 2022
Current statusCertificate Signed
Against todayabout 56 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAI ICON record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAI ICON in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
SAI ICON1G+826 Jan 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at SANDVIK COLONY, DIGHI ROAD, Haveli, Pune, 411039. Per the filed land record, the plot is bounded to the north by 9 MTR WIDE ROAD, to the south by PCMC LAYOUT NO 2, to the east by 9 MTR WIDE ROAD and to the west by PART OF SURVEY NO 230. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

M/s. K. K. Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by M/s. K. K. Developers

M/s. K. K. Developers
FlaggedPune

Other RERA-registered projects in Bhosari

Vision Exotica
possession by Oct 2026 · Vision Avis Groups
Ramnagar Housing Complex Phase L
possession by Dec 2026 · Vaastu Udyog
Diamond Hills
possession by Dec 2026 · A Square Properties
Evernest Shivshrushti
possession by Dec 2026 · Evernest Perfectinfra LLP
Riya Casa
possession by Dec 2026 · Sarode Developers
Vision Exotica Phase-II
possession by Dec 2026 · Vision Avis Groups

Other RERA-registered projects in Pune

SAI Icon Wing B
possession by Dec 2026 · M/s. K. K. Developers
Sai Imperial
possession by Mar 2027 · Veena Constructions
Sai Kalash
declared completion Dec 2024 · Sai Anand Properties
Sai Kirti Meadows
declared completion Mar 2026 · M/s Sai Kirti Meadows LLP
Sai Kirti Riverview
declared completion Jun 2025 · M/s Sai Kirti Riverview Llp
Sai Kirti Serenity
possession by Dec 2026 · M/s Sai Kirti Serenity LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026