MahaRERA Property Intelligence · Pune

SAIRAJ RESIDENCY

P52100004377 · promoter Sairaj Developers

Certificate SignedDue 31 Dec 2019

Delivery & Registration

MahaRERA registrationP52100004377
Registered on09 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 79 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sairaj Developers is the promoter of record on 43 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SAIRAJ RESIDENCY1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Pune City, Pune, 411048. Per the filed land record, the plot is bounded to the north by S NO 58, to the south by S NO 58-5-2-25, to the east by S NO 58 and to the west by ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre9 km
Magarpatta / Hadapsar IT9 km
Kharadi / EON IT Park13 km
Pune Int'l Airport (Lohegaon)15 km
Baner–Balewadi belt16 km
Hinjewadi Rajiv Gandhi IT Park21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sairaj Developers is the promoter on 7 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Sairaj Developers

Sairaj Developers
Past its declared completion datePune

Other RERA-registered projects in Kondhwa Bk

Alcon Signare
possession by Jul 2026 · Alcon Builders
Vrundavan Residency
possession by Sep 2026 · Gangai Developers
Krushna Chayya
possession by Sep 2026 · Shree Mahalaxmi Builder AND Developars
Majestic Pride
possession by Oct 2026 · Anwar Mahmoo Shaikh
Krishna Kunj
possession by Nov 2026 · Bace India Developers
THE Latitude - D
possession by Dec 2026 · Ahura Builders

Major developers building in Kondhwa Bk

Other RERA-registered projects in Pune

Sairam Residency
declared completion Dec 2025 · Manoj Harishchandra Kale
Sairang Residency
possession by May 2028 · A B Sai Groups
Sairang Residency Phase II
declared completion Mar 2018 · Priyanka Santosh Dhobale
Sairatna Heights
declared completion Dec 2020 · Malhar Builders AND Developers
Sais Leela
declared completion Dec 2019 · Saibaba Sales Private Limited
Saisha
declared completion Dec 2025 · SAI Samarttha Properties

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026