Pune/Project record

MahaRERA · the public record

SAMARTH AANGAN C

Pune · SHREE REALITY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

01 Aug 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 Aug 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100003323

Delivery and registration

When is the project declared for completion?

SAMARTH AANGAN C is registered with MahaRERA as P52100003323 and the promoter has declared completion for 01 Aug 2023.

01 Aug 2023

declared completion

37months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100003323
Registered on05 Aug 2017
Promoter-declared completion01 Aug 2023
Current statusCertificate Signed
Against todayabout 37 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAMARTH AANGAN C record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAMARTH AANGAN C in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SAMARTH AANGAN C1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Jan 2022Sir, Our Project is completed and file for completion certificate was given to T.P (PMRD). but now this area is merged in PMC Pune. Therefore there is delay in obtaining Completio
31 Jan 202201 Aug 2023Sir, Our Project is completed and file for completion certificate was given to T.P (PMRD). but now this area is merged in PMC Pune. Therefore there is delay in obtaining Completio

Location, Land & Connectivity

Located at Pune City, Pune, 411041. Per the filed land record, the plot is bounded to the north by 18-26-34-69N TO 73-47-18-01E, to the south by 18-26-33-96N TO 73-47-18-08E, to the east by 18-26-34-37N TO 73-47-19-14E and to the west by 18-26-34-08N TO 73-47-16-75E. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Pune Junction / city centre9 km
Magarpatta / Hadapsar IT11 km
Baner–Balewadi belt14 km
Kharadi / EON IT Park15 km
Pune Int'l Airport (Lohegaon)16 km
Hinjewadi Rajiv Gandhi IT Park19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dhayari

Aqura Pride
possession by Sep 2026 · Aqura Builder And Developer Private Limi
Majestique Swapnangan Wing A And Wing B
possession by Sep 2026 · Majestique Horizon LLP
Tridal Samruddhi
possession by Sep 2026 · M/s. Tridal Associates
Vasant Vihar A Wing
possession by Sep 2026 · A R Developers
Homedale
possession by Dec 2026 · M/s. Om Shiv Sai Promoters & Develop
Navjyot Abha Phase II B And D
Not filing quarterly progress reports · possession by Dec 2026 · Sumeru Buildcon Private Limited

Major developers building in Dhayari

Other RERA-registered projects in Pune

Samarth Balaji Plaza
declared completion Feb 2025 · Balaji Construction
Samarth Business HUB
possession by Mar 2028 · D.a.borade & Sons
Samarth Classic
possession by Dec 2026 · M/s Saste Patil Developers
Samarth County
possession by Oct 2026 · D A Borade AND Sons
Samarth Elite
possession by Feb 2028 · Sarika Vishal Randive
Samarth Florencia Building B
declared completion Mar 2024 · Samarth Landmarks

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026