SAMARTH COUNTY

Ravet · D A BORADE AND SONS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

41units filed as unsoldInventory · 17 September 2026
31 Oct 2026declared completionMahaRERA registration · read 12 Jul 2026
176registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Oct 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100029698

Delivery and registration

When is the project declared for completion?

SAMARTH COUNTY is registered with MahaRERA as P52100029698 and the promoter has declared completion for 31 Oct 2026.

31 Oct 2026

declared completion

1months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100029698
Registered on26 Jun 2021
Promoter-declared completion31 Oct 2026
Current statusCertificate Signed
Against today1 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAMARTH COUNTY record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Borade And Sons is the promoter of record on 18 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

18projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In SAMARTH COUNTY, ₹97.60 Cr of a declared ₹97.68 Cr estimated project cost is reported as incurred, about 99.9%, as at the last certified filing with MahaRERA.

99.9%

₹97.60 Cr

of ₹97.68 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In SAMARTH COUNTY, 135 of 176 homes filed with MahaRERA are recorded as sold or booked, about 77%, and 41 remain available.

77%sold

135 of 176 homes

₹70.34 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹61.57 Cr (about 88%) is recorded as collected and ₹8.78 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 135 registered agreements, the effective carpet rate is ₹8,952/sqft, with eight in ten falling between ₹6,002 and ₹10,041 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 17 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 135 homes carry one, and 41 of the 176 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
OFFICE- 103636 sqftRs 49.11 lakh typical, over Rs 31.50 lakh to Rs 71.61 lakh69 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In SAMARTH COUNTY, 31 of the 41 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 40 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24 and 176 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
A WING1G+2483-
B WING1G+2483-
C WING1G+310-

Unit mix on the filing: 166 residential and 10 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2026Respected Sir/Madam, We, the promoters of Samarth County (Reg. No. P52100029698), humbly request an extension of the project registration, currently valid till 31/12/2025, up to 30
30 Jun 202631 Oct 2026Respected Sir/Madam, We, the promoters of SAMARTH COUNTY, registered with the Authority under Registration No. P52100029698, humbly submit this application seeking extension of pro

Location, Land & Connectivity

Located at Ravet, Sr No 61/1,61/2/1, Haveli, Pune, 412101. Per the filed land record, the plot is bounded to the north by By remainig property of Sr No 61, to the south by By 24 mtr road, to the east by By 6 mtr colony road and to the west by By property of Sr No 65. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park4 km
Baner–Balewadi belt9 km
Pune Junction / city centre18 km
Pune Int'l Airport (Lohegaon)19 km
Kharadi / EON IT Park23 km
Magarpatta / Hadapsar IT23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ravet

City ONE Skyve
possession by Sep 2026 · Shree SAI Capital
Godrej Carnival
possession by Sep 2026 · Godrej Skyline Developers Limited
Godrej Nurture
possession by Sep 2026 · Godrej Skyline Developers Limited
Madhuban
possession by Sep 2026 · Godrej Skyline Developers Limited
OM Mangalam Chaitanya
possession by Sep 2026 · Shri Associates
OM Mangalam Disha
possession by Sep 2026 · Shri Associates

Major developers building in Ravet

Other RERA-registered projects in Pune

Samarth Elite
possession by Feb 2028 · Sarika Vishal Randive
Samarth Florencia Building B
declared completion Mar 2024 · Samarth Landmarks
Samarth Fortune
declared completion Sep 2020 · Fortune Vastusilpa Developers LLP
Samarth Heights
declared completion Mar 2023 · Horizon Infrastructure
Samarth Heights
possession by Dec 2026 · Swamisamarth Developers
Samarth Heights
possession by Jun 2029 · M/s Samarth Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026