Shree Ganesha Apartment

P52100015007 · Baburao Nagar, Shirur · promoter Saisamruddhi Construction

Certificate SignedDue 31 Dec 2019

Delivery & Registration

MahaRERA registrationP52100015007
Registered on22 Jan 2018
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 79 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Saisamruddhi Construction is the promoter of record on 2 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Shree Ganesha Apartment1G+531 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Baburao Nagar, Shirur, Pune Nagar Road, Shirur, Pune, 412210. Per the filed land record, the plot is bounded to the north by Plot No 75 Paiki, to the south by Plot No 72, to the east by Aminity Plot and to the west by 9 M Wide Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~54 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kharadi / EON IT Park54 km
Pune Int'l Airport (Lohegaon)55 km
Magarpatta / Hadapsar IT58 km
Pune Junction / city centre62 km
Baner–Balewadi belt69 km
Hinjewadi Rajiv Gandhi IT Park71 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Saisamruddhi Construction is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Saisamruddhi Construction

Saisamruddhi Construction
FlaggedPune

Other RERA-registered projects in Shirur

Advik Paradise
possession by Aug 2026 · NG Developers
1 Sadabaug Phase-I
possession by Sep 2026 · Lalita Dharamchand Phulfagar
1 Sadabaug Phase-II
possession by Sep 2026 · Lalita Dharamchand Phulfagar
1 Sadabaug Phase-III
possession by Sep 2026 · Lalita Dharamchand Phulfagar
Babji Market
possession by Sep 2026 · Pyramid Constructions
Rayat Residency
possession by Sep 2026 · Soham Constructions AND Developers

Other RERA-registered projects in Pune

Shree Ganesha Heights
declared completion Mar 2026 · Siddhivinayak Enterprises
Shree Ganesha Icon
possession by Dec 2027 · Potent Associates
Shree Ganesha Residency
declared completion Jan 2021 · Tirupati Developers
Shree Ganesha Residency
declared completion Dec 2024 · Shruti Promoters & Developers
Shree Ganesham
declared completion Feb 2021 · S P Developers
Shree Ganraj Complex
declared completion Sep 2024 · Shree Builtcon

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026