Pune/Project record

MahaRERA · the public record

SILVER KARISHMA

Pune · SAWANT JADHAV ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

15 May 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

15 May 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100010954

Delivery and registration

When is the project declared for completion?

SILVER KARISHMA is registered with MahaRERA as P52100010954 and the promoter has declared completion for 15 May 2022.

15 May 2022

declared completion

52months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100010954
Registered on31 Aug 2017
Promoter-declared completion15 May 2022
Current statusCertificate Signed
Against todayabout 52 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SILVER KARISHMA record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sawant Jadhav Associates is the promoter of record on 65 projects registered with MahaRERA, 9 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

65projects

registered with MahaRERA

9flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SILVER KARISHMA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
SILVER KARISHMA1G+1215 May 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered15 Nov 2021Delay due to COVID pandemic.

Location, Land & Connectivity

Located at Haveli, Pune, 412105. Per the filed land record, the plot is bounded to the north by NAMDEV PANDURANG SASTE, to the south by 24 MTR WIDE ROAD, to the east by GAT 56 and to the west by GAT 51. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~122 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park122 km
Baner–Balewadi belt127 km
Pune Junction / city centre138 km
Pune Int'l Airport (Lohegaon)138 km
Kharadi / EON IT Park142 km
Magarpatta / Hadapsar IT143 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Moshi

Ideal Avenue
possession by Sep 2026 · Ideal Builders
Fortune Vedas Phase II
Not filing quarterly progress reports · possession by Sep 2026 · Fortune Vastusilpa Developers LLP
Gulmohar 24
possession by Sep 2026 · Royal Gulmohar Reality
Krishnai Residency
possession by Sep 2026 · Vastu Buildcon
Omkar Residency
possession by Sep 2026 · Prerna Group
Town Square
possession by Sep 2026 · Krupasindhu Developers

Major developers building in Moshi

Other RERA-registered projects in Pune

Silver Lavish
declared completion Mar 2026 · OM Infra AND Prapti Icon
Silver Leaf
declared completion May 2022 · Shrijibuildcorp Through Proprietor Rajni
Silver Meteor
possession by Dec 2028 · Roshan Builders LLP
Silver Mist C, D Building
declared completion Jun 2018 · Nirman Buildcon
Silver Nest
possession by Dec 2026 · Silver Nest
Silver OAK
declared completion Mar 2021 · Shree Siddhivinayak Construction

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026