Pune/Project record

MahaRERA · the public record

SIMANTINI

BHAMBURDA · N N JOSHI CONSTRUCTIONS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100017187

Delivery and registration

When is the project declared for completion?

SIMANTINI is registered with MahaRERA as P52100017187 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100017187
Registered on17 Jul 2018
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SIMANTINI record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Joshi Constructions is the promoter of record on 98 projects registered with MahaRERA, 16 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

98projects

registered with MahaRERA

16flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SIMANTINI in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
SIMANTINI1G+631 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at BHAMBURDA, PANKUWAR FIRODIA ROAD, Pune City, Pune, 411005. Per the filed land record, the plot is bounded to the north by ROAD, to the south by CTS NO 1076 PLOT NO 11 AND 12, to the east by CTS NO 1076 PLOT NO 4 and to the west by CTS NO 1076 PLOT NO 2. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shivajinagar

Centropolis
Past its declared completion date · possession by Oct 2026 · Skywards Ashtika Lifestyle
One Place - F C Road
possession by Dec 2026 · Palash Realtors LLP
Buttepatil Capital
possession by Dec 2026 · Buttepatil Properties
Nirmiti Adisha
possession by Dec 2026 · Nirmiti Lifestyle
SAI Chambers
possession by Dec 2026 · Milind Ramkrishna Upasani
Vijay Business Square
possession by Feb 2027 · NS Developers

Other RERA-registered projects in Pune

Sindhu Apartments
possession by Sep 2028 · Ranade Realtors LLP
Sindhu Park
possession by Jun 2027 · Shubharambh Promoters AND Builders
Sindhu Shantai
declared completion Dec 2022 · Santosh Nathuram Navale
Sindhu Skies
possession by Oct 2030 · G K Wonders
Singapune Ph 1
possession by Dec 2028 · Xrbia Mirth Properties LLP
Singapune Ph 2
possession by Dec 2028 · Xrbia Mirth Properties LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026