SKY GALAXIA

P52100017750 · FURSUNGI · promoter Signifia Properties

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP52100017750
Registered on11 Sep 2018
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
SKY GALAXIA1G+731 Jan 2021

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000008555915/05/2021MAHESH BHOITE vs Significa Propertiesorder passed
CC00500000022832615/02/2023Mahesh Bhoite vs Signifia Propertiesorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jan 202215 Jan 2023Project got delayed due to Pandemic. Material was not available. Labour had gone to their home town. It took time to start again.
30 Jan 202231 Dec 2024The project got delayed due to Pandemic.

Location, Land & Connectivity

Located at FURSUNGI, FURSUNGI, Haveli, Pune, 412308. Per the filed land record, the plot is bounded to the north by 6M WIDE ROAD, to the south by 12 M WIDE ROAD, to the east by REMAINING PART OF GAT NO 178 and to the west by REMAINING PART OF GAT NO 178. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Fursungi

Simplicity Phase 4 - A Wing
possession by Jul 2026 · J K P Developers Unit NO 2
Tranquility Annexe C Wing
possession by Jul 2026 · K AND B Associates
Casalino Towers Phase 3
possession by Oct 2026 · Sai Siddhi Promoters & Builders
Silver Park - B Wing
possession by Dec 2026 · Hakke AND KAD Developers
Green Hive Plus Wing A4
possession by Dec 2026 · Ram India Shelters
Sahara Platinum
possession by Dec 2026 · Sahara Buildtek

Major developers building in Fursungi

Other RERA-registered projects in Pune

SKY Gardens
declared completion Jun 2026 · APK Landmarks LLP
SKY Gate
possession by Oct 2028 · SGD Realtors
Sky Heights Phase 2
declared completion Dec 2022 · Homeland Constructions Pvt. Ltd.
SKY Homes
possession by May 2028 · Mahalaxmi Enterprise
Sky Lavish
possession by May 2028 · Sujit Group
SKY Line
declared completion Dec 2022 · Swara Properties LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026