Pune/Project record

MahaRERA · the public record

Sumit Homes

Dhayari · Sumit Homes

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

46units filed as unsoldInventory · 19 September 2026
12 Oct 2028declared completionMahaRERA registration · read 12 Jul 2026
54registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

12 Oct 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100048874

Delivery and registration

When is the project declared for completion?

Sumit Homes is registered with MahaRERA as P52100048874 and the promoter has declared completion for 12 Oct 2028.

12 Oct 2028

declared completion

25months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100048874
Registered on24 Jan 2023
Promoter-declared completion12 Oct 2028
Current statusCertificate Signed
Against today25 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Sumit Homes record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sumit Homes is the promoter of record on 44 projects registered with MahaRERA, 7 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

44projects

registered with MahaRERA

7flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In Sumit Homes, ₹2.42 Cr of a declared ₹10.51 Cr estimated project cost is reported as incurred, about 23.1%, as at the last certified filing with MahaRERA.

23.1%

₹2.42 Cr

of ₹10.51 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Sumit Homes, 0 of 46 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 46 remain available.

0%sold

0 of 46 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 54 homes in total, while this sold/unsold inventory filing covers 46 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The inventory filing also declares: 8 not for sale.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Sumit Homes in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 September 2026

What the filings record, home by home

Read from MahaRERA on 19 September 2026

No home in Sumit Homes carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 46 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 5,051 a sq ft typical, over Rs 4,677 to Rs 5,055.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 46 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 46 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 54 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Wing A1G+72812 Oct 2028
Wing B1G+72612 Oct 2028

Unit mix on the filing: 54 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Dhayari, Dhayari, Haveli, Pune, 411041. Per the filed land record, the plot is bounded to the north by 18 m wide proposed DP road, to the south by Adjacent S No 7 Part, to the east by Adjacent S No 7 Part and to the west by 6 Meter wide road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Pune Junction / city centre11 km
Baner–Balewadi belt13 km
Magarpatta / Hadapsar IT14 km
Hinjewadi Rajiv Gandhi IT Park18 km
Kharadi / EON IT Park18 km
Pune Int'l Airport (Lohegaon)19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dhayari

Aqura Pride
possession by Sep 2026 · Aqura Builder And Developer Private Limi
Majestique Swapnangan Wing A And Wing B
possession by Sep 2026 · Majestique Horizon LLP
Tridal Samruddhi
possession by Sep 2026 · M/s. Tridal Associates
Vasant Vihar A Wing
possession by Sep 2026 · A R Developers
Homedale
possession by Dec 2026 · M/s. Om Shiv Sai Promoters & Develop
Navjyot Abha Phase II B And D
Not filing quarterly progress reports · possession by Dec 2026 · Sumeru Buildcon Private Limited

Major developers building in Dhayari

Other RERA-registered projects in Pune

Sumukh
possession by Dec 2028 · Amol Ajit Ravetkar
Sumukh Residency
declared completion Mar 2024 · Samartha Buildcons
SUN Apex
possession by Dec 2030 · Jindal Mittal Graha Nirman Pvt. Ltd.
Sun Aura
declared completion Dec 2018 · Mittal Vastushilp LLP
Sun City - Ambegaon Phase - III
declared completion Mar 2026 · Mittal Projects
Sun Emerald
possession by Dec 2029 · Jindal Mittal Graha Nirman Pvt. Ltd.

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026