MahaRERA Property Intelligence · Pune

SWARNA VATIKA

P52100020905 · PUNE · promoter Raichandani Constructions And

Certificate SignedDue 01 Jul 2024

Delivery & Registration

MahaRERA registrationP52100020905
Registered on16 May 2019
Promoter-declared completion01 Jul 2024
Current statusCertificate Signed
Against todayabout 24 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Raichandani Constructions And is the promoter of record on 14 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
SWARNA VATIKA BUILDING B1G+13-
SWARNA VATIKA BUILDING B61G+13-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 4 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Mar 202330 Sep 2023Due to covid pandemic
30 Mar 202331 Mar 2024Due to Covid-19 e faced several challenges such as lack of availability of labour as many of them migrated back to their native places, disruption of supply chain of essential cons
30 Mar 202331 Dec 2023we have completed the construction of project and have handed over the units but we are ought to receive the completion certificate.
30 Mar 202301 Jul 2024Project completion is delayed due to minor finishing work .We have obtained concent of 44 allotees . Please grant us extension till 1/07/2024.

Location, Land & Connectivity

Located at PUNE, NA, Pune City, Pune, 411048. Per the filed land record, the plot is bounded to the north by Survey No 16 Part Village Kondhwa Khurd, to the south by Survey No 16 Part Village Kondhwa Khurd, to the east by By Road and to the west by By Nala. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Raichandani Constructions AND Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Raichandani Constructions AND Developers

Raichandani Constructions AND Developers
FlaggedPune

Other RERA-registered projects in Kondhwa Bk

Alcon Signare
possession by Jul 2026 · Alcon Builders
Vrundavan Residency
possession by Sep 2026 · Gangai Developers
Krushna Chayya
possession by Sep 2026 · Shree Mahalaxmi Builder AND Developars
Majestic Pride
possession by Oct 2026 · Anwar Mahmoo Shaikh
Krishna Kunj
possession by Nov 2026 · Bace India Developers
THE Latitude - D
possession by Dec 2026 · Ahura Builders

Major developers building in Kondhwa Bk

Other RERA-registered projects in Pune

Swarnavilas Phase 1
declared completion Dec 2017 · Sachin Vitthal Nimhan
Swarnavilas Phase 2
declared completion Mar 2024 · Sachin Vitthal Nimhan
Swarneem
declared completion Apr 2024 · Aditya Jagannath Harne
Swaroop Darshan
declared completion Sep 2023 · Swaroop Developers
Swaroop Enclave
declared completion Mar 2023 · AMS Landmarks CO.
Swaroop Homes
possession by Nov 2026 · Swaroop Homes LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026