MahaRERA Property Intelligence · Pune

The Peak

P52100017885 · Mohammed Wadi · promoter Kundan Buildcon

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP52100017885
Registered on24 Sep 2018
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Kundan Buildcon is the promoter of record on 18 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
The Peak Sanctioned upto 13th floor1G+1630 Jun 2023
The Peak from 14TH floor1G+630 Jun 2023

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1240045919/10/2024Kundan Buildcon vs Shilpa Parag Deshpandeorder passed
CC1260327831/05/2026Aftab Mahuvawala vs Kundan Buildconpending / no order on file

Location, Land & Connectivity

Located at Mohammed Wadi, NIBM Undri Road, Haveli, Pune, 411038. Per the filed land record, the plot is bounded to the north by 9 mtr Road, to the south by Adjc HSS No 102 D, to the east by 24 mtr DP Road and to the west by Adjc CTS No 830 P. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Kundan Buildcon is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Kundan Buildcon

Other RERA-registered projects in Kothrud

Umed
possession by Jul 2026 · Runwal Realtors Pvt Ltd
Chandra Apartment
possession by Aug 2026 · Deshpande Landmark Private Limited
Keshar
possession by Aug 2026 · Badhekar Properties
Tungabhadra CO OP HSG SOC
possession by Aug 2026 · Not Available
Arunali
possession by Sep 2026 · Badhekar Properties
Guruvaibhav CO-Op.housing Society Limited
possession by Sep 2026 · Shreepad Associates

Major developers building in Kothrud

Other RERA-registered projects in Pune

THE Pearl
declared completion Jul 2025 · Limra Properties
THE Pearl
possession by Dec 2026 · Bhosale Gavhane Associates
THE Platinum Towers
declared completion Aug 2025 · Avishkar Arista Developers LLP
THE Pleasant CO OP Housing Society LTD
possession by Sep 2026 · Shree Venkatesh Landmarks
THE Porwal Suites
declared completion Mar 2026 · Kishor Sheshmal Porwal
THE Premia
possession by Dec 2028 · Chanddrakant Shivajirao Ghuley

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026