MahaRERA Property Intelligence · Pune

VAISHNAV CLASSIC

P52100009025 · promoter Shree Datta Developers

Certificate SignedDue 31 Dec 2017

Delivery & Registration

MahaRERA registrationP52100009025
Registered on19 Aug 2017
Promoter-declared completion31 Dec 2017
Current statusCertificate Signed
Against todayabout 103 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+40.

BuildingWingsFloorsDeclared completion
VAISHNAV CLASSIC1G+40-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Haveli, Pune, 411027. Per the filed land record, the plot is bounded to the north by 17, to the south by 17, to the east by 38 and to the west by 38. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Baner–Balewadi belt2 km
Hinjewadi Rajiv Gandhi IT Park6 km
Pune Junction / city centre10 km
Pune Int'l Airport (Lohegaon)13 km
Magarpatta / Hadapsar IT15 km
Kharadi / EON IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Datta Developers is the promoter on 9 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Shree Datta Developers project & its RERA track record →

Other flagged projects by Shree Datta Developers

Shree Datta Developers
FlaggedPune

Other RERA-registered projects in Pimple Nilakh

S3 Lifestyle
possession by Jul 2026 · Siddhivinayak Kohinoor Ventures
Audumber Residency
possession by Aug 2026 · Shama Construction Through Properiter Vi
Sai Neel
possession by Sep 2026 · Vishal Anil Khairnar
Marigold Calendula
possession by Sep 2026 · Audumbar Homes LLP
Sai Aura
possession by Sep 2026 · WJV Landmarks LLP
Sky 2 Cosmos
possession by Oct 2026 · Emperos Properties

Major developers building in Pimple Nilakh

Other RERA-registered projects in Pune

Vaishnav Construction
declared completion Dec 2017 · Vaishnav Construction
Vaishnav Gaatha
possession by Dec 2026 · Kalbhor Realtors And Services LLP
Vaishnav Residency
declared completion Dec 2018 · Vaishnav Residency
Vaishnave Classic
declared completion Jun 2023 · Mangaldeep Associates & Developers
Vaishnavi
declared completion Jul 2023 · Vaishnavi Developers
Vaishnavi - 2
declared completion Jun 2018 · Varad Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026