MahaRERA Property Intelligence · Pune

Xrbia Abode

P52100001412 · Jambhul · promoter Xrbia Abode Developers

Certificate SignedDue 29 Mar 2023

Delivery & Registration

MahaRERA registrationP52100001412
Registered on28 Jul 2017
Promoter-declared completion29 Mar 2023
Current statusCertificate Signed
Against todayabout 40 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Xrbia Abode Developers is the promoter of record on 27 projects, of which 16 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
A11G+831 Mar 2021
B11G+831 Mar 2021
B21G+731 Mar 2021
B31G+831 Mar 2021
C11G+831 Mar 2021
D11G+831 Mar 2021
D21G+831 Mar 2021
E11G+731 Mar 2021
F11G+831 Mar 2021
G11G+831 Mar 2021
G21G+831 Mar 2021

Complaints & Orders

19 complaints are on the MahaRERA record for this project, with orders passed in 19. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000002291517/06/2019POOJA NAGESH MUSALE & MR MAGESH RAMESH MUSALE vs XERBIA ABODE DEVELOPERS PVT LTD & MIRACLE SHELTERS PVT LTDorder passed
CC00500000002201411/09/2018FIROZ AZIZ SHAIKH vs XRBIA DEVELOPERS LIMITEDorder passed
CC00500000002238624/03/2019Seeta Bajrang Kachi vs Xrbia Abode Dev.Pvt.Ltd.order passed
CC00500000002266415/02/2019Satbir Singh vs Xrbia Abode Developers Pvt.Ltdorder passed
CC00500000002304120/05/2019Ritesh Suresh Doiphode vs XRBIA DEVELOPERS LTD.order passed
CC00500000004369323/11/2019Vaishali Sanjay Jadhav vs XRBIA ABODE DEVELOPERS PVT LTDorder passed
CC00500000007520010/02/2021VIJAY DATTATRAY CHAVAN vs Xrbia Developers Limitedorder passed
CC00500000005415114/03/2020sATYABHAMA VIJAY BHADORIA vs XRBIA ABODE DEVELOPERS PVt. Ltd.order passed
CC00500000006454224/08/2020Shaheen Amirali Batliwala vs Xrbia Abode Developers Private Limitedorder passed
CC00500000008550126/04/2021Afsana Kayyum Shaikh vs Kishor Hindgaonkarorder passed
CC00500000009588213/08/2021Arun Ranchhoddas Ashar vs Xbria Abode Developers Private Limited through its authorised signatory Karan Rajivkumar Karnawatorder passed
CC00500000009611311/10/2021Yogesh hulle vs XRBIA DEVELOPERorder passed
CC00500000014718201/06/2022Anju Sopchand Barewar vs Xrbia Abode Developers Pvt Ltdorder passed
CC00500000031042623/02/2024Kavita Harichandra Surywanshi vs Xrbia Abode Developers Pvt. Ltd. Through its Authorized Signatory Mr. Gajanan Sadashiv Dongareorder passed
CC00500000034079217/04/2024Harsha Dalvi vs Xrbia Abode Developers Pvt. Ltd.order passed
CC1240082620/11/2024Soma Chabu Gawari vs Xrbia Abode Developers Private Limitedorder passed
CC1250243017/07/2025Satish Salian vs Xrbia Abode Developers Private Limitedorder passed
CC1250273605/08/2025ATUL ASHOK MORE vs Xrbia Abode Developers Private Limitedorder passed
CC1260136512/03/2026SUNITA RAMSINGH SAHANI vs Xrbia Abode Developers Private Limitedorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
29 Mar 202329 Mar 20236 Buildings Out of 11 Buildings have recived Completion / Occupancy Certificate. Work Got Delayed Due to Heavy Rains and Covid19 Related Lockdown , migration of labourers.

Location, Land & Connectivity

Located at Jambhul, Jambhul, Pune City, Pune, 410507. Per the filed land record, the plot is bounded to the north by Gat No 240 and Gat No 178, to the south by Gat No 240 Part, to the east by Gat No 240 Part and Gat No 192 and to the west by Gat No 175 and Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~22 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park22 km
Baner–Balewadi belt28 km
Pune Junction / city centre37 km
Pune Int'l Airport (Lohegaon)37 km
Kharadi / EON IT Park41 km
Magarpatta / Hadapsar IT42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Talegaon Dabhade

Real Dream Homes Wing C AND D
possession by Jul 2026 · Real Buildcon Builders AND Developers
ECO City
possession by Aug 2026 · Namrata Promoters AND Builders
Luxuria
possession by Aug 2026 · Prammukh Associates
Arunoday Classic A Wing
possession by Sep 2026 · Kedar Harishchandra Khandge
Hillcrest
possession by Oct 2026 · Swapnashilp Buildcon
Greendale ENA
possession by Dec 2026 · M/s. Karpe Construction Company

Major developers building in Talegaon Dabhade

Other RERA-registered projects in Pune

Xrbia Ambi - Ph - 1
declared completion Mar 2022 · Xrbia Ambience Realty LLP
Xrbia Ambi - Ph - 2
declared completion Mar 2023 · Xrbia Ambience Realty LLP
Xrbia Eiffel City Chakan PH1
declared completion Mar 2022 · Xrbia Chakan Developers Private Limited
Xrbia Eiffel City Chakan PH2
declared completion Mar 2022 · Xrbia Chakan Developers Private Limited
Xrbia Hinjewadi Road/riverfront-PH-1
declared completion Jun 2019 · Xrbia North Hinjewadi Developers Private
Xrbia Hinjewadi Road / Riverfront - Ph - 2
declared completion Dec 2019 · Xrbia North Hinjewadi Developers Private

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026