Pune/Project record

MahaRERA · the public record

YUVAN PARK

PIMPALE, PURANDAR · AMBRISH NAGESH SWAMI

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

15 Mar 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

15 Mar 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100026401

Delivery and registration

When is the project declared for completion?

YUVAN PARK is registered with MahaRERA as P52100026401 and the promoter has declared completion for 15 Mar 2024.

15 Mar 2024

declared completion

30months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100026401
Registered on17 Sep 2020
Promoter-declared completion15 Mar 2024
Current statusCertificate Signed
Against todayabout 30 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for YUVAN PARK record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Ambrish Nagesh Swami is the promoter of record on 3 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In YUVAN PARK, 0 of 31 plots filed with MahaRERA are recorded as sold or booked, about 0%, and 31 remain available.

0%sold

0 of 31 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for YUVAN PARK in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at PIMPALE, PURANDAR, PIMPALE, PURANDAR, Haveli, Pune, 412301. Per the filed land record, the plot is bounded to the north by GAT NO 433 435 436 P, to the south by ROAD, to the east by GAT NO 5 6 7 AND ROAD and to the west by SUBHADRA BABURAO BHALERAO AND PIMPALE GAOTHAN. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Saswad

Bliss Fields-Phase-I
possession by Oct 2026 · SAI Shraddha Venture
Karha Vastu
possession by Nov 2026 · S J Developers
Venkatesh Pushpakala
Not filing quarterly progress reports · possession by Dec 2026 · Sanjay Dnynoba Jagtap
Anand Baug C Wing
possession by Dec 2026 · Sankalp Developers
Kanishka Grand Plaza
possession by Dec 2026 · Platinum Lifespace Developers
Kanishka Grand Plaza Max
Not filing quarterly progress reports · possession by Dec 2026 · Platinum Lifespace Developers

Major developers building in Saswad

Other RERA-registered projects in Pune

Yuvraj Residency
possession by Dec 2027 · B V M Properties
Zambare Icon
possession by Jun 2027 · Shreeshivtej Buildcon Pvt. Ltd.
ZEN-Dale
possession by Mar 2027 · Elite Promoters And Builders
ZEN Elite
possession by Dec 2026 · Rion Buildtech Private Limited
ZEN Estate
declared completion Sep 2025 · Destination Kharadi Developers LLP
Zen Kode
possession by Dec 2027 · Rion Buildtech Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026