MahaRERA Property Intelligence · Pune

ZEN ESTATE

P52100022495 · KHARADI · promoter Destination Kharadi Developers

Certificate SignedDue 30 Sep 2025

Delivery & Registration

MahaRERA registrationP52100022495
Registered on25 Sep 2019
Promoter-declared completion30 Sep 2025
Current statusCertificate Signed
Against todayabout 10 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Destination Kharadi Developers is the promoter of record on 2 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~1.0% of the estimated project cost incurred as of the last certificate (₹9.35 Cr spent against a ₹931.63 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. The declared completion date has already passed while the cost-incurred filing sits at ~1.0% — a wide gap between the promise and the money actually spent on site.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 473 homes filed with MahaRERA, 473 are sold/booked and 0 remain available (~100% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹268.13 Cr in agreement value so far. Of that, ₹268.13 Cr (~100%) is already collected, ₹0 receivable — a read on how far along these sales really are. Note: the project registers 541 homes in total, but this sold/unsold inventory filing covers only 473 of them — the other 68 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 473 registered agreements, the effective carpet rate is ₹7,654/sqft (typical range ₹3,100–₹8,189) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

⚠ The inventory filing also declares: 68 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17 and 541 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
A1G+175530 Sep 2024
B1G+165630 Sep 2024
C1G+164330 Sep 2024
D1G+166830 Sep 2024
E1G+168430 Sep 2024
F1G+156030 Sep 2024
G1G+156030 Sep 2024
H1G+156030 Sep 2024
I -MHADA1G+155530 Sep 2024

Unit mix on the filing: 529 residential and 12 non-residential (shops/offices).

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000031052005/06/2024Rishabh Gupta vs Manoj Guptaorder passed

Location, Land & Connectivity

Located at KHARADI, PLOT NO. 5 AND 6 S NO. 18 KHARADI TAL HAVELI PUNE, Pune City, Pune, 411014. Per the filed land record, the plot is bounded to the north by PLOT NO P7 AS PER SANCTIONED LAYPOUT, to the south by 24 MTR ROAD, to the east by 24 MTR ROAD and to the west by PLOT NO P5 AS PER SANCTIONED LAYOUT. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kharadi

Satyam Shivam Phase 2
Not filing quarterly progress reports · possession by Sep 2026 · Vijayalaxmi Associates
The Collection - W2 And W7
possession by Sep 2026 · Bramhacorp Limited
Unique Youtopia Phase III
possession by Sep 2026 · Unique Associates
Spandan
possession by Oct 2026 · Evolve Infra
Ganga Platinum A
possession by Oct 2026 · Shree Balaji Associates Pune LLP
Percept Bounty 3
possession by Dec 2026 · Prime Estate

Major developers building in Kharadi

Other RERA-registered projects in Pune

Zen Kode
possession by Dec 2027 · Rion Buildtech Private Limited
ZEN Square
possession by Dec 2028 · Rion Buildtech Private Limited
Zenistry- B
possession by Dec 2028 · Ellanza Corp
Zenith
possession by Dec 2026 · Ambar Icon LLP
Zenith Spaces
possession by Jun 2027 · Rudra Realtors
Zenone B Building
possession by Sep 2027 · K & T Infrastructure

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026