30 Nov 2020declared completionK-RERA registration · read 20 Sep 2026
73registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Nov 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

4 BHK
61

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

14.8registered acres

4.9registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/309/PR/170915/000418

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 November 2020
Land area59,969 sq m (14.8 acres)
Homes registered73
Tower/wing entries73
Unit mix61 × 4 BHK

In context

Density4.9 homes per acre
Density in context3rd percentile of 525 Bengaluru North projects (median 75.4)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units73Total inventory registered with K-RERA.
Official carpet area289 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area59,969 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI0.47Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries73Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)146Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date30-06-2016

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
4 BHK61100%289 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
287112-
288112-
290112-
292112-
293112-
294112-
295112-
297112-

Showing first 8 of 73 tower/wing rows.

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 73 official flat/unit rows, matching the 73 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
4BHK73233.4-326.6 sqm0.0 sqm146

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
2871290.6 sqm0.0 sqm2
2881255.8 sqm0.0 sqm2
2901255.6 sqm0.0 sqm2
2921255.6 sqm0.0 sqm2
2931255.6 sqm0.0 sqm2
2941290.6 sqm0.0 sqm2
2951285.6 sqm0.0 sqm2
2971233.4 sqm0.0 sqm2
2991256.2 sqm0.0 sqm2
3011256.2 sqm0.0 sqm2
3021292.3 sqm0.0 sqm2
3031291.6 sqm0.0 sqm2

Showing first 12 of 73 tower/wing groups.

Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
28728704BHK290.6 sqm0.0 sqm2
28828804BHK255.8 sqm0.0 sqm2
29029004BHK255.6 sqm0.0 sqm2
29229204BHK255.6 sqm0.0 sqm2
29329304BHK255.6 sqm0.0 sqm2
29429404BHK290.6 sqm0.0 sqm2

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

⚠ 2 of 15 compliance document slots are filed as under process / not yet usable: Proforma For Sale Deed, Brochure of Current Project.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Nov 2020, extended (Extension) to 03 Nov 2023 — both dates have passed with no OC on file. An extension application filed on 27 Jul 2022 is pending with K-RERA — until it is approved, the registration stands lapsed.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

2 K-RERA orders on this project (PROJECT EXTENSION) — read the order copies on the K-RERA portal.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Anil Kumar Kurra vs Adarsh Nivaas Private LimitedDirect the respondent to pay interest on delay period, to complete and handover of possession and to register the sale deed in favor of complainant.AUTHORITY01/07/2026

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (1 complaint listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/221011/0010086
11-10-2022
Delay in Refunding theToken amount after canceling the booking due to insufficient legal docsAdarsh Palm Acres - Phase 1-Part A (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectRajani PM-2004No10, Vittal Malya Road
ContractorAdarsh Developers-1990no 10, vittal mallya road
Structural engineerRADHA B P---

Builder track record

RERA filing

Adarsh has 18 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Adarsh Nivaas”) (average reported construction progress 61%). 12 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹162.3 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC richmond (IFSC HDFC0000523, a/c …1389). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bellandur–Marathahalli belt1 km
Whitefield IT hub8 km
Electronic City9 km
MG Road / city centre11 km
Outer Ring Road / Manyata15 km
Kempegowda Int'l Airport31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Adarsh Nivaas. View Adarsh Nivaas's full track record →
Adarsh Nivaas has 5 projects registered in Bangalore.

Other projects by this builder in Bangalore

Adarsh Palm Acres Phase 3
On track · 2% built · 19% sold
Adarsh Palm Acres - Phase 1-Part A
No filings
Adarsh Palm Acres - Phase 1-Part B
No filings
Adarsh Palm Acres - Phase 2-Part A
No filings

Other RERA-registered projects in Bellandur

Major developers building in Bellandur

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Adarsh Palm Acres - Phase 2-Part B?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026