Prestige Green Gables

Bengaluru East · PRESTIGE ESTATES PROJECTS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

100%construction reportedQ3 2025 filing
0units not bookedof 406 · Q3 2025 filing
30 Jun 2025declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q3 2025

declared completion

30 Jun 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3 BHK (2T)
104
2 BHK (2T)
104
1 BED
50
3BHK + M
44
3 BHK (3T)
104

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

5.5registered acres

73.6registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/140222/004706

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 June 2025
Land area22,334 sq m (5.5 acres)
Homes registered406
Tower/wing entries4
Unit mix104 × 3 BHK (2T), 104 × 2 BHK (2T), 50 × 1 BED, 44 × 3BHK + M, 104 × 3 BHK (3T)

In context

Density73.6 homes per acre
Density in context47th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units406Total inventory registered with K-RERA.
Official carpet area34,322 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area66,702 sqmUseful scale context when comparing density and project cost.
Registered land area22,334 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.246Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries4Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)444Separate filed counts; these categories may overlap and are not added together.
Covered-parking field381Separate filed counts; these categories may overlap and are not added together.
Open-parking field38Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberLPUse this to match the sanctioned drawing set shown by the builder.
Plan approval date30-06-2021
Project start date01-03-2022

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK (2T)10426%9,152 sqm
2 BHK (2T)10426%7,384 sqm
1 BED5012%2,000 sqm
3BHK + M4411%5,324 sqm
3 BHK (3T)10426%10,462 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower 11210010540 m
Tower 21210311440 m
Tower 31210311540 m
Tower 41210011040 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 406 official flat/unit rows, matching the 406 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
D-3BR-2T10488.0 sqm57.4 sqm137
B-2BR5270.7 sqm45.0 sqm52
C-2BR5270.7 sqm45.4 sqm52
E-3BR5299.1 sqm65.3 sqm52
A-1BR5039.9 sqm27.0 sqm50
F-3BR48101.9 sqm66.9 sqm48
J-3BR+M44120.9 sqm78.1 sqm44
G-3BR2102.7 sqm67.4 sqm2
H-3BR2105.7 sqm69.0 sqm2

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower 210339.9-99.1 sqm27.0-65.3 sqm114
Tower 310339.9-99.1 sqm27.0-65.3 sqm115
Tower 110070.7-120.9 sqm45.4-78.1 sqm100
Tower 410070.7-120.9 sqm45.4-78.1 sqm110
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1001Tower 10D-3BR-2T88.0 sqm57.4 sqm1
1002Tower 10F-3BR101.9 sqm66.9 sqm1
1003Tower 10G-3BR102.7 sqm67.4 sqm1
1004Tower 10C-2BR70.7 sqm45.4 sqm1
1005Tower 10C-2BR70.7 sqm45.4 sqm1
1007Tower 10F-3BR101.9 sqm66.9 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

10 of 38 compliance document slots are filed as Not Applicable; the remaining 28 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Jun 2025, extended (Section 6 Extension) to 31 Dec 2025 — both dates have passed with no OC on file. The extension on file was granted on 27 Jun 2025 (K-RERA extension no. EX/PRM/KA/RERA/1251/446/PR/250627/004706) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Complaints on this project's K-RERA page (61 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190225/0002242
25-02-2019
Builder not paying compensation as per agreement and no handover of apartment after deadlinePRESTIGE WESTWOODS (another project by this promoter)DISPOSED AO
CMP/190325/0002508
25-03-2019
Delayed Interest for delayed handoverPrestige Royale Gardens Phase-I (another project by this promoter)DISPOSED AO
CMP/190330/0002539
30-03-2019
Delay in delivery of ProjectPrestige Royale Gardens Phase-I (another project by this promoter)DISPOSED AO
CMP/190419/0002630
19-04-2019
This is to request to adjust against balance or reimburse the amount as per delay clause @ 9% till date on the amount paid. Also to adhere to agreement for handover of flat no 14011 in tower 14Prestige Royale Gardens Phase-I (another project by this promoter)DISPOSED AO
CMP/190519/0003075
19-05-2019
Prestiege Royale Gardens T2147 Apartmen Dealy in possession, compensation not being pais as per agreementPrestige Royale Gardens Phase-I (another project by this promoter)DISPOSED AO
CMP/190519/0003091
19-05-2019
Undue delay of project completion and Monetary compensation towards that per Construction agreementPrestige Royale Gardens Phase-I (another project by this promoter)DISPOSED AO
CMP/190520/0003069
20-05-2019
There is no OC 2 yrs after promised data of delivery. There is misrepresentation of the tower number scheduled apartment comparing brochure and sanctioned plan.PRESTIGE ROYALE GARDENS PHASE 2 (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/190614/0003288
14-06-2019
Delay in delivery and compensation not paidPRESTIGE ROYALE GARDENS PHASE 2 (another project by this promoter)DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved04-10-2022BWSSB NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved23-02-2021MOEF NOC.pdf
KPTCL- BESCOMApproved12-04-2021Bescom NOC.pdf
Fire and SafetyApproved13-10-2020FIRE NOC.pdf
Airport Authority of IndiaApproved19-11-2019AIRPORT NOC.pdf
BSNL/Telecommunication DepartmentApproved30-09-2019BSNL NOC.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantM Padmanabha Bhat0253051986Bengaluru Urban, Karnataka - 560093
EngineerDesign Ventures Engineering Consultants (I) Pvt LtdBCCL/BL-3.6/SE- 0218/21-222009Bengaluru Urban, Karnataka - 560080
ArchitectZachariah ConsultantsCA/2010/470152016Bengaluru Urban, Karnataka - 560025
ContractorJMC Projects (India) Ltd.-1994Bengaluru Urban, Karnataka - 560025

Builder track record

RERA filing

Prestige has 81 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Prestige Estates”) (average reported construction progress 62%). 53 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q3): ₹14.65 Cr collected from buyers, ₹14.43 Cr withdrawn from the project's escrow account.

Construction progress100% → 100% (+0 pts)
Units sold/booked as registered406/406 (100%)
Buyer collections in available QPRs₹14.65 Cr
Escrow withdrawals in available QPRs₹14.43 Cr (0.98x collections)
  • 100% of registered units are shown as sold/booked, but no completion certificate is on file yet.
  • The filed unit sales count did not move across the available QPR window because the project was already effectively sold out.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹32.4 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: KOTAK MAHINDRA BANK Lavelle Road Bangalore IFSC Code : KKBK0000422 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bellandur–Marathahalli belt1 km
Whitefield IT hub6 km
MG Road / city centre11 km
Electronic City11 km
Outer Ring Road / Manyata14 km
Kempegowda Int'l Airport29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Prestige Estates. View Prestige Estates's full track record →
Prestige Estates has 46 projects registered in Bangalore, 2 completed, 1 past RERA deadline.

Other projects by this builder in Bangalore

Prestige Elm Park
Past deadline · 88% built · 72% sold
Prestige Gardenia Estate
Filing overdue · 59% built
Evergreen @ Prestige Raintree Park
On track · 24% built · 59% sold
Prestige Bagamane Temple Bells
No filings

Other RERA-registered projects in Bellandur

Major developers building in Bellandur

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.