Bangalore/Project record

K-RERA · the public record

ADARSH PINECOURT

Bengaluru East · Nusrath Unisa

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

28 Feb 2022declared completionK-RERA registration · read 20 Sep 2026
59registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

28 Feb 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

4.1registered acres

14.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/191025/002975

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion28 February 2022
Land area16,693 sq m (4.1 acres)
Homes registered59
Tower/wing entries8

In context

Density14.3 homes per acre
Density in context5th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units59Total inventory registered with K-RERA.
Registered land area16,693 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.738Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries8Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)59Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date01-06-2018

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
BLOCK B41010-
BLOCK C41010-
BLOCK E41010-
BLOCK F455-
BLOCK G41010-
BLOCK H444-
BLOCK K455-
BLOCK J455-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 59 official flat/unit rows, matching the 59 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK371,135.0-1,187.0 sqft0.0 sqft37
2BHK12804.0-936.0 sqft0.0 sqft12
2.5BHK101,060.0-1,089.0 sqft0.0 sqft10

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
BLOCK B10861.0-1,168.0 sqft0.0 sqft10
BLOCK C10936.0-1,155.0 sqft0.0 sqft10
BLOCK E101,135.0-1,187.0 sqft0.0 sqft10
BLOCK G10874.0-1,183.0 sqft0.0 sqft10
BLOCK F51,060.0-1,082.0 sqft0.0 sqft5
BLOCK J5814.0-822.0 sqft0.0 sqft5
BLOCK K51,160.0-1,168.0 sqft0.0 sqft5
BLOCK H4804.0-834.0 sqft0.0 sqft4
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
B-001BLOCK B02BHK861.0 sqft0.0 sqft1
B-004BLOCK B03BHK1,150.0 sqft0.0 sqft1
B-101BLOCK B13BHK1,168.0 sqft0.0 sqft1
B-104BLOCK B13BHK1,155.0 sqft0.0 sqft1
B-201BLOCK B23BHK1,168.0 sqft0.0 sqft1
B-204BLOCK B23BHK1,155.0 sqft0.0 sqft1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

⚠ 1 of 18 compliance document slots are filed as under process / not yet usable: Brochure of Current Project.

1 additional compliance slots are filed as Not Applicable.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 28 Feb 2022, extended (Section 6 Extension) to 28 Nov 2023 — both dates have passed with no OC on file. The extension on file was granted on 09 Feb 2024 (K-RERA extension no. EX/PRM/KA/RERA/1251/446/PR/240209/002975) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

1 K-RERA order on this project (OTHERS) — read the order copies on the K-RERA portal.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectC B Vivek Uthaiah-2000Unit 010 South Block Raheja Chambers, 12 Museum Road
ContractorK K Civil Contractors-2000No 1234 A 1ST Phase, 1st Stage Chandra layout
Structural engineerDesigntree Service Consultants Pvt Ltd---

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

RERA 70% project account is on file: HDFC Vasanth Nagar (IFSC HDFC0003881, a/c …4615). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata6 km
MG Road / city centre13 km
Kempegowda Int'l Airport14 km
Whitefield IT hub16 km
Bellandur–Marathahalli belt17 km
Electronic City27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Nusrath Unisa.

Other RERA-registered projects in Kothanur

Major developers building in Kothanur

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Adarsh Pinecourt?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026