Nitesh Melbourne Park

Bengaluru East · NITESH HOUSING DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2022declared completionK-RERA registration · read 20 Sep 2026
490registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3Bed - 27
2

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

10.7registered acres

45.9registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/170916/000224

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 March 2022
Land area43,199 sq m (10.7 acres)
Homes registered490
Tower/wing entries12
Unit mix2 × 3Bed - 27

In context

Density45.9 homes per acre
Density in context17th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units490Total inventory registered with K-RERA.
Official carpet area117 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area43,199 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.75Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries12Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)490Separate filed counts; these categories may overlap and are not added together.
Open-parking field53Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date17-10-2016

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3Bed - 272100%117 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Block A44040-
Block B44040-
Block C44040-
Block D45050-
Block E45050-
Block F45050-
Block G44040-
Block H44545-

Showing first 8 of 12 tower/wing rows.

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 490 official flat/unit rows, matching the 490 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK33195.9-128.7 sqm61.8-103.0 sqm331
2.5BHK8492.0-95.9 sqm57.6-81.7 sqm84
1BHK3510.0-11.3 sqm6.6-7.3 sqm35
4BHK30150.8-150.9 sqm95.7-120.1 sqm30
1B1T1010.0 sqm6.6 sqm10

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Block D5011.3-150.8 sqm7.3-120.0 sqm50
Block E5011.3-150.9 sqm7.3-120.1 sqm50
Block F5011.3-150.9 sqm7.3-120.1 sqm50
Block H4510.0-118.0 sqm6.6-93.2 sqm45
Block K4510.0-126.6 sqm6.6-96.3 sqm45
Block A40117.9-128.7 sqm74.8-102.7 sqm40
Block B40117.9-128.1 sqm74.8-95.5 sqm40
Block C40118.0-128.1 sqm74.8-101.9 sqm40
Block G4095.9-127.5 sqm61.8-98.8 sqm40
Block I4095.1-128.1 sqm61.3-102.9 sqm40
Block J4095.1-128.1 sqm61.3-103.0 sqm40
Block L10117.9 sqm74.8-90.2 sqm10
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
NIMP-A-0001Block A03BHK128.7 sqm100.5 sqm1
NIMP-A-0002Block A03BHK128.7 sqm102.7 sqm1
NIMP-A-0003Block A03BHK117.9 sqm94.8 sqm1
NIMP-A-0004Block A03BHK117.9 sqm95.0 sqm1
NIMP-A-0005Block A03BHK117.9 sqm82.2 sqm1
NIMP-A-0006Block A03BHK117.9 sqm83.3 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 14 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Mar 2022, extended (Covid Extension) to 31 Dec 2022 — both dates have passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

1 K-RERA order on this project (PROJECT WITHDRAWL) — read the order copies on the K-RERA portal.

K-RERA complaint orders (31 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
DEEPAK MARTIN S vs NITESH HOUSING DEVELOPERS PRIVATE LIMITEDfull refund of our principal and interest as per the agreementAUTHORITY30/03/2023
vijaykumar S Nayanegali vs NITESH MELBOURNE PARKRefund of booking amount of Rs 4 laks and Interest till dateAUTHORITY27/04/2022
KUMAR ABHISHEK vs NITESH HOUSING DEVELOPERS PRIVATE LIMITEDFull Refund amount plus penaltyAUTHORITY25/06/2022
AJEET KUMAR MALL vs NITESH HOUSING DEVELOPERS PRIVATE LIMITEDPrincipal payment with interest as per RERA rulesAUTHORITY25/06/2022
MAHANTESH R GUNDALI vs NITESH HOUSING DEVELOPERS PRIVATE LIMITEDFull REfund amount with penaltyAUTHORITY25/06/2022
SHRIKANT SARDA & (2) NAMRATA SARDA vs NITESH HOUSING DEVELOPERS PRIVATE LIMITED Now called as NHDPL PROPERTIES PRIVATE LIMITEDRefund of the amount including interest and penaltyAUTHORITY23/05/2023
CHETAN ANAND & MRS. NARINDER KAUR ANAND vs NITESH HOUSING DEVELOPERS PVT LTDRefund along with interest on monies paidAUTHORITY23/05/2023
SURESH BABU M vs NITESH HOUSING DEVELOPERS PRIVATE LIMITED NOW CALLED AS NHDPL PROPERTIES PRIVATE LIMITEDRefund of Rs.64,87,376 with compensation (interest)AUTHORITY22/02/2023
BHUSHAN SHRAVAN BARI vs NITESH HOUSING DEVELOPERS PRIVATE LIMITED Now called as NHDPL PROPERTIES PRIVATE LIMITEDRefund paid amount with applicable interestAUTHORITY22/02/2023
ANIL REBELLO vs NITESH HOUSING DEVELOPERS PRIVATE LIMITED Now called as NHDPL PROPERTIES PRIVATE LIMITEDrefund of amount, interest and compensationAUTHORITY21/06/2023
LAKSHMANAN BALAKRISHNAN vs NITESH HOUSING DEVELOPERS PRIVATE LIMITED now as called NHDPL SOUTH PRIVATE LIMITEDTo get back my investment of Rs.50,00,000 plus interestAUTHORITY20/05/2023
Vijay Kumar M vs VIJAY KUMAR M & MRS. CHANDANA CHANDRASHEKARRefund of Principal paid with interest and compensationAUTHORITY20/05/2023
SHEKHAR SHARAN BHATIYA & (2) RADHA BHATIYA vs NITESH HOUSING DEVELOPERS PRIVATE LIMITED Now called as NHDPL PROPERTIES PRIVATE LIMITEDSince project is stalled kindly order builder to refund the money paid with interest.AUTHORITY16/02/2023
NAVNEETH BHEEMAN & (2) LEENA POOVANNA NAVNEETH vs NITESH HOUSING DEVELOPERS PRIVATE LIMITED Now called as NHDPL PROPERTIES PRIVATE LIMRefund of full amount paid along with interest at prevailing rates of 9.5%AUTHORITY15/03/2023
R SREERAM ANVESH vs NITESH HOUSING DEVELOPERS PRIVATE LIMITEDRefund, Interest, Compensation for mental agony and Legal CostAUTHORITY11/02/2023
ASHWINI MADAPPA M vs NITESH HOUSING DEVELOPERS PRIVATE LIMITEDRefund of INR 30.23 lakhs (fully paid amount) + applicable interest for delaysAUTHORITY11/02/2023
MERILIN STANLEY & STANLEY FRANCIS vs NITESH HOUSING DEVELOPERS PRIVATE LIMITEDRs 40,00,000/-AUTHORITY11/02/2023
RASHMI KOTHARI vs NITESH HOUSING DEVELOPERS PRIVATE LIMITEDRefund of Total amount paid of Rs. 4399730/ + Interest @ 18% pa.AUTHORITY11/02/2023
JITENDRA HARICHANDAN vs NITESH HOUSING DEVELOPERS PRIVATE LIMITEDRefund with Compensation for Paid InstallmentsAUTHORITY11/02/2023
RANJIT NAMBIAR vs NITESH HOUSING DEVELOPERS PRIVATE LIMITEDHelp in refund.AUTHORITY11/02/2023
MUKUND MADHAV AGARWAL vs NITESH HOUSING DEVELOPERS PRIVATE LIMITEDRefund of Money with InterestAUTHORITY11/02/2023
Dsouza Prakash vs Nitesh Housing Developers Pvt Ltd.Refunds of advance payment paid to Nitesh Housing Developers with interestAUTHORITY11/02/2023
Anand Kumar Verma vs NITESH HOUSING DEVELOPERS PRIVATE LIMITEDPlease help me to get my principal and interest amount from NiteshAUTHORITY11/02/2023
Karthic Raj S vs NITESH MELBOURSE PARKI would request that Nitesh estates refunds my amount in full with Interest and penalty fee for the delay of more than 7 years .AUTHORITY11/02/2023
SUDEEP KABI vs NITESH HOUSING DEVELOPERS PRIVATE LIMITEDCancellation of Unit No. D-0307 along with refund of Rs. 20,75,869/- with 18% interest p.a and compensation of Rs. 5,00,000/- for delayAUTHORITY11/02/2023
NACHIKETA TRIVEDI vs NITESH HOUSING DEVELOPERS PRIVATE LIMITED Now called as NHDPL PROPERTIES PRIVATE LIMITEDHelp in refund with the applicable interestAUTHORITY09/06/2023
AMREETA MAZUMDAR & (2) ARUNAVA SEAL vs NITESH HOUSING DEVELOPERS PRIVATE LIMITED Now called as NHDPL PROPERTIES PRIVATE LIMITEDRefund of the money we gave to NHDPL with interestAUTHORITY05/05/2023
Chintu Varkey vs NITESH HOUSING DEVELOPERS PRIVATE LIMITEDCancellation of Unit No. D-0001 along with refund of Rs. 31,00,089/- with 18% interest p.a and compensation of Rs. 5,00,000/- for delayAUTHORITY05/04/2023
Chintu Varkey vs NITESH HOUSING DEVELOPERS PRIVATE LIMITEDCancellation of Unit No. D-0091 along with refund of Rs. 10,05,302/- with 18% interest p.a and compensation of Rs. 5,00,000/- for delayAUTHORITY05/04/2023
MANISHA BAJAJ vs NITESH HOUSING DEVELOPERS PRIVATE LIMITEDFor refund of the entire amount paid by the complainant along with interest and compensationAUTHORITY03/05/2023
Sunil Banthiya vs NITESH HOUSING DEVELOPERS PRIVATE LIMITEDCompensationAUTHORITY01/03/2023

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (71 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190302/0002335
02-03-2019
Cancellation and refund of money with interestNitesh Columbus Square Phase II (another project by this promoter)DISPOSED AO
CMP/190325/0002497
25-03-2019
Huge delay in completion of Nitesh Columbus Square projectNitesh Columbus Square Phase II (another project by this promoter)DISPOSED AO
CMP/190327/0002527
27-03-2019
Not handed over as per commitment and incomplete constructionNitesh Columbus Square Phase II (another project by this promoter)DISPOSED AO
CMP/190417/0002295
17-04-2019
Grievance against Nitesh Housing Developers PVT Ltd/Nitesh Columbus Square/C 701Nitesh Columbus Square Phase II (another project by this promoter)DISPOSED AO
CMP/190513/0002972
13-05-2019
Inordinate delay in completion of project and handing over possession - Refund RequestNitesh Napa Valley (another project by this promoter)DISPOSED AO
CMP/190528/0003188
28-05-2019
Nitesh not refunding amount around 35 Lacs that I paid during sale agreement and there afterNitesh Melbourne ParkDISPOSED AUTHORITY
CMP/190624/0002421
24-06-2019
Requesting refund with interest and penalty due to non completion of project by promoterNitesh Columbus Square Phase II (another project by this promoter)DISPOSED AO
CMP/190626/0003405
26-06-2019
Return of amount and compensationNitesh Hyde Park Phase II (another project by this promoter)DISPOSED AUTHORITY

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectSandeep Shikre & Associates-1989Prabhadevi Industrial Estate, Veer Sawarkar Marg
ContractorAL Fara'A Infraprojects Pvt Ltd.,-2011Andheri-Kurla Road, Andheri( East)
Structural engineerNovel Engineering Consultants---

Builder track record

RERA filing

Nitesh has 10 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Nitesh Housing”). 10 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a higher delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹31.4 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: YES BANK Kasturba Road (IFSC YESB0000022, a/c …0671). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 2 project-photo uploads.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata5 km
MG Road / city centre12 km
Kempegowda Int'l Airport15 km
Whitefield IT hub16 km
Bellandur–Marathahalli belt16 km
Electronic City26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Nitesh Housing. View Nitesh Housing's full track record →
Nitesh Housing has 4 projects registered in Bangalore.

Other projects by this builder in Bangalore

Nitesh Columbus Square Phase II
No filings
Nitesh Hyde Park Phase II
No filings

Other RERA-registered projects in Kothanur

Major developers building in Kothanur

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.