Bangalore/Project record

K-RERA · the public record

Sobha Neopolis Phase 3 - W 1, 2, 10 & 11

Bengaluru East · SOBHA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

27%construction reportedQ1 2026 filing
66units not bookedof 374 · Q1 2026 filing
31 Dec 2029declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Dec 2029

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

ELECTRICAL ROOM
2
4 BHK
152
3 BHK
222

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

9.0registered acres

41.7registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/220923/006282

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2029
Land area36,283 sq m (9.0 acres)
Homes registered374
Tower/wing entries4
Unit mix2 × ELECTRICAL ROOM, 152 × 4 BHK, 222 × 3 BHK

In context

Density41.7 homes per acre
Density in context15th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units374Total inventory registered with K-RERA.
Official carpet area47,824 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area95,420 sqmUseful scale context when comparing density and project cost.
Registered land area36,283 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.99Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries4Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)374Separate filed counts; these categories may overlap and are not added together.
Covered-parking field596Separate filed counts; these categories may overlap and are not added together.
Open-parking field38Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBBMP/Addl.Dir/JDNORTH/0003/23-24Use this to match the sanctioned drawing set shown by the builder.
Plan approval date05-09-2023
Project start date01-10-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
ELECTRICAL ROOM21%0 sqm
4 BHK15240%22,805 sqm
3 BHK22259%25,018 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Wing 118767657.6 m
Wing 21811111157.6 m
Wing 1018767657.6 m
Wing 111811111157.6 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 374 official flat/unit rows, matching the 374 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK222105.1-135.0 sqm39.1-52.9 sqm222
4 BHK152145.3-150.3 sqm56.7-60.3 sqm152

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Wing 11111105.1-135.0 sqm39.1-52.9 sqm111
Wing 2111105.1-135.0 sqm39.1-52.9 sqm111
Wing 176145.3-150.3 sqm56.7-60.3 sqm76
Wing 1076145.3-150.3 sqm56.7-60.3 sqm76
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1001Wing 104 BHK145.3 sqm57.7 sqm1
1002Wing 104 BHK150.3 sqm59.3 sqm1
1003Wing 104 BHK150.3 sqm59.3 sqm1
1004Wing 104 BHK145.3 sqm57.7 sqm1
1011Wing 114 BHK145.3 sqm56.7 sqm1
1012Wing 114 BHK150.3 sqm58.3 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

9 of 83 compliance document slots are filed as Not Applicable; the remaining 74 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
EPari Sanat Kumar Patro vs SOBHA LIMITEDBuilder is supposed to refund 12 lacs that I have deposited and it is due since 40 days past as per the 45 days norm to return the money from cancellation and I expect interest at 3% from builderAUTHORITY25/03/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (127 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190217/0002175
17-02-2019
Compensation for Delay of projectsSobha City - Casa Paradiso Block 4 (another project by this promoter)DISPOSED AO
CMP/190218/0002166
18-02-2019
Refund of booking amountSobha Dream Acres - Palm Springs Phase 17 Wing 54 (another project by this promoter)DISPOSED AO
CMP/190225/0002263
25-02-2019
Refund of Advance amount-Sobha Arena - The Park ( Block 2 ) (another project by this promoter)DISPOSED AO
CMP/190308/0002388
08-03-2019
Non-allotment of agreed units & RefundSobha Indraprastha (another project by this promoter)DISPOSED AO
CMP/190308/0002322
08-03-2019
Promoter SL Demanding 38% payment of unit cost before entering the ATSSobha Arena - Pebble Court (Block 1) (another project by this promoter)DISPOSED AO
CMP/190315/0002219
15-03-2019
About refund of booking amountSobha Dream Acres - Tropical Greens Phase 8 Wing 43 and 44 (another project by this promoter)DISPOSED AO
CMP/190324/0002505
24-03-2019
Compensation against late deliverySobha City - Casa Paradiso Block 4 (another project by this promoter)DISPOSED AO
CMP/190401/0002556
01-04-2019
Please refund booking amountSobha Dream Acres - Rain Forest Phase 2 Wing 3 and 4 (another project by this promoter)DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

3 of 4 applicable approvals are on file; still outstanding: KPTCL- BESCOM. Confirm each has been granted, not merely applied for, before booking.

6 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved05-05-2023BWSSB NOC SNP 05052023.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved23-11-2022KSPCB CFE SNP 23112022.pdf
KPTCL- BESCOMApplied11-08-2025View NOC
Fire and SafetyApproved06-10-2022Fire NOC SNP 06102022.pdf

Project team & certifications

RERA filing

K-RERA names 5 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantBalaji D2173902016Bengaluru Urban, Karnataka - 560084
EngineerMr.HAREESH GOWDABCC/BL-3.6 SE-153/2013-141995Bengaluru Urban, Karnataka - 560095
EngineerBalakrishnan GF-124976-92019Bengaluru Urban, Karnataka - 560103
ArchitectGeetha K NairCA/93/156411993Bengaluru Urban, Karnataka - 560103
ContractorSobha Limited-1995Bengaluru Urban, Karnataka - 560103

Builder track record

RERA filing

Sobha has 121 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Sobha”) (average reported construction progress 62%). 60 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹36.74 Cr collected from buyers, ₹12.02 Cr withdrawn from the project's escrow account.

Construction progress15% → 27% (+12 pts)
Units sold/booked as registered308/374 (82%)
Buyer collections in available QPRs₹102.78 Cr
Escrow withdrawals in available QPRs₹99.47 Cr (0.97x collections)
  • Construction progress moved from 15% to 27% across the filed QPR window.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹92.7 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: KOTAK MAHINDRA BANK MG road IFSC Code : KKBK0008066 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bellandur–Marathahalli belt3 km
Whitefield IT hub6 km
Electronic City11 km
MG Road / city centre13 km
Outer Ring Road / Manyata16 km
Kempegowda Int'l Airport30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sobha. View Sobha's full track record →
Sobha has 120 projects registered in Bangalore, 25 completed.
274 complaints on the K-RERA register against Sobha in Bangalore.

Buyer reviews · MouthShut

★★☆☆☆ 1.6/5

337 reviews for Sobha in Bangalore
Read 337 reviews on MouthShut →

Other projects by this builder in Bangalore

Sobha Crystal Meadows Phase 1 Wing 1 To 6
Filing overdue · 5% built · 0% sold
Sobha Crystal Meadows Phase 2 Wing 7 And 8
Filing overdue · 2% built · 0% sold
Sobha Crystal Meadows Phase 3 Wing 9 To 15
Filing overdue · 2% built · 0% sold
Sobha Crystal Meadows Phase 4 Wing 23 To 28
Filing overdue · 2% built · 0% sold
Sobha Crystal Meadows Phase 5 Wing 16 To 22
Filing overdue · 2% built · 0% sold
Sobha Dream Acres - Tropical Greens Phase 21 Wing 21 And 22
Filing overdue · 100% built · 100% sold

Other RERA-registered projects in Kothanur

Major developers building in Kothanur

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Sobha Neopolis Phase 3 - W 1, 2, 10 & 11?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026