Bangalore/Project record

K-RERA · the public record

alpine vistula

Bengaluru East · Alpine Housing Development Corporation

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Oct 2020declared completionK-RERA registration · read 20 Sep 2026
142registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Oct 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

1 BHK 2BHK 3 BHK
125

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

5.4registered acres

26.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/171014/000211

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 October 2020
Land area21,839 sq m (5.4 acres)
Homes registered142
Tower/wing entries3
Unit mix125 × 1 BHK 2BHK 3 BHK

In context

Density26.3 homes per acre
Density in context9th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units142Total inventory registered with K-RERA.
Official carpet area11,431 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area21,839 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.99Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)157Separate filed counts; these categories may overlap and are not added together.
Open-parking field64Separate filed counts; these categories may overlap and are not added together.
Garage field45Separate filed counts; these categories may overlap and are not added together.
Project start date01-07-2016

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
1 BHK 2BHK 3 BHK125100%11,431 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A163742-
B104651-
C105964-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 142 official flat/unit rows, matching the 142 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK7674.6-78.8 sqm28.1-34.0 sqm76
3BHK4696.8-110.2 sqm37.0-43.4 sqm46
1BHK2034.7-54.6 sqm12.5-20.2 sqm20

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
C5937.3-110.2 sqm12.5-43.4 sqm59
B4634.7-78.0 sqm13.5-30.8 sqm46
A3737.0-97.3 sqm13.3-39.6 sqm37
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
GF-A001A01BHK37.0 sqm13.3 sqm1
GF-A002A01BHK48.0 sqm18.1 sqm1
GF-A003A01BHK52.4 sqm20.2 sqm1
GF-A004A01BHK40.7 sqm16.3 sqm1
GF-A005A01BHK52.6 sqm19.8 sqm1
1F-A101A12BHK78.8 sqm29.4 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 16 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Oct 2020, extended (Covid Extension) to 30 Jul 2021 — both dates have passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
SATYARTHA SRIVASTAVA vs ALPINE HOUSING DEVELOPMENT CORPORATION LIMITEDNeed to ensure that the buyers are compensated as per rera act and the agreement between buyer and sellerAUTHORITY18/01/2023

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (5 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/210328/0007845
28-03-2021
Complaint against the promotors for lack of complianceALPINE PYRAMID EFGH (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/210331/0007854
31-03-2021
illegal encroachment of Car Exit Ramp and car parking spot not allocatedALPINE FIESTA ABDF (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/211028/0008478
28-10-2021
Dampness on wallsALPINE FIESTA C E (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/211111/0008541
11-11-2021
Rera date is over still I have not received the compensation for the housealpine vistulaDISPOSED AUTHORITY BENCH4
CMP/211111/0008543
11-11-2021
Poor build quality, delay in handover & not responding to fix the issuesALPINE FIESTA C E (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectManoj Ladhad-1996Architecture Paradigm 26 4th B Cross, 5th Block Koramangala
ContractorSaukcon Infra Private Limited-2013Alpine Arch, 10 Langford Road
Structural engineerGunasheel Karanth---

Builder track record

RERA filing

Alpine Housing has 4 other K-RERA-registered projects in our records (average reported construction progress 35%). 3 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹0.0 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: BANK OF INDIA JC Road (IFSC BKID0008407, a/c …0390). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub5 km
Bellandur–Marathahalli belt12 km
Outer Ring Road / Manyata15 km
MG Road / city centre17 km
Kempegowda Int'l Airport21 km
Electronic City22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Alpine Housing. View Alpine Housing's full track record →
Alpine Housing has 5 projects registered in Bangalore.

Other projects by this builder in Bangalore

Alpine Pyramid - Iris
On track · 35% built · 42% sold

Other RERA-registered projects in Kannamangala

Major developers building in Kannamangala

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Alpine Vistula?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026