Bangalore/Project record

K-RERA · the public record

AQUA VISTA

Bengaluru South · POPPY REALTORS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

100%construction reportedQ3 2025 filing
8units not bookedof 181 · Q3 2025 filing
31 Dec 2024declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q3 2025

declared completion

31 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

PENT HOUSE
1
TYPE-3b(3BHK + 3T)
4
TYPE-3c (3BHK + 3T)
9
PENT HOUSE
1
TYPE-5 (3BHK + 3T)
14
PENT HOUSE
1
TYPE-2 (3BHK + 3T)
13
PENT HOUSE
1
PENT HOUSE
1
TYPE-1 (3BHK +SERVANT)
16
PENT HOUSE
1
PENT HOUSE
1
TYPE-5 (3BHK + 3T)
14
TYPE-4 (3BHK +SERVANT)
28
PENT HOUSE
1
PENT HOUSE
1
TYPE-2 (3BHK + 3T)
14
TYPE- 2a (3BHK + 3T)
2
TYPE-1 (3BHK +SERVANT)
14
PENT HOUSE
1
TYPE-6 (3BHK + 3T)
28
TYPE-3a (3BHK + 3T)
9
TYPE-3d (3BHK + 3T)
4
TYPE-6A (3BHK + 3T)
1
PENT HOUSE
1

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

2.9registered acres

62.6registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/120522/004879

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2024
Land area11,707 sq m (2.9 acres)
Homes registered181
Tower/wing entries3
Unit mix11 × PENT HOUSE, 4 × TYPE-3b(3BHK + 3T), 9 × TYPE-3c (3BHK + 3T), 28 × TYPE-5 (3BHK + 3T), 27 × TYPE-2 (3BHK + 3T), 30 × TYPE-1 (3BHK +SERVANT), 28 × TYPE-4 (3B

In context

Density62.6 homes per acre
Density in context30th percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units181Total inventory registered with K-RERA.
Official carpet area5,832 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area58,257 sqmUseful scale context when comparing density and project cost.
Registered land area11,707 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3.21Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)194Separate filed counts; these categories may overlap and are not added together.
Covered-parking field194Separate filed counts; these categories may overlap and are not added together.
Open-parking field26Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan number256/2011-12Use this to match the sanctioned drawing set shown by the builder.
Plan approval date19-02-2020
Project start date01-08-2021

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
PENT HOUSE11%256 sqm
TYPE-3b(3BHK + 3T)42%120 sqm
TYPE-3c (3BHK + 3T)95%122 sqm
PENT HOUSE11%245 sqm
TYPE-5 (3BHK + 3T)148%137 sqm
PENT HOUSE11%239 sqm
TYPE-2 (3BHK + 3T)137%121 sqm
PENT HOUSE11%237 sqm
PENT HOUSE11%499 sqm
TYPE-1 (3BHK +SERVANT)169%140 sqm
PENT HOUSE11%255 sqm
PENT HOUSE11%236 sqm
TYPE-5 (3BHK + 3T)148%137 sqm
TYPE-4 (3BHK +SERVANT)2815%140 sqm
PENT HOUSE11%255 sqm
PENT HOUSE11%247 sqm
TYPE-2 (3BHK + 3T)148%121 sqm
TYPE- 2a (3BHK + 3T)21%149 sqm
TYPE-1 (3BHK +SERVANT)148%140 sqm
PENT HOUSE11%247 sqm
TYPE-6 (3BHK + 3T)2815%124 sqm
TYPE-3a (3BHK + 3T)95%120 sqm
TYPE-3d (3BHK + 3T)42%122 sqm
TYPE-6A (3BHK + 3T)11%118 sqm
PENT HOUSE11%239 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A18576159.5 m
B18636859.5 m
C19616562.5 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 181 official flat/unit rows, matching the 181 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK170117.8-149.4 sqm49.7-62.5 sqm170
pent house11236.6-498.5 sqm103.0-212.5 sqm24

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
B63121.3-255.8 sqm50.6-109.8 sqm68
C61117.8-247.9 sqm51.5-106.0 sqm65
A57119.6-498.5 sqm49.7-212.5 sqm61
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A-303A33 BHK139.8 sqm58.4 sqm1
A-304A33 BHK140.0 sqm58.6 sqm1
A-401A43 BHK121.4 sqm51.5 sqm1
A-402A43 BHK119.6 sqm52.0 sqm1
A-403A43 BHK139.8 sqm58.4 sqm1
A-404A43 BHK140.0 sqm58.6 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

17 of 48 compliance document slots are filed as Not Applicable; the remaining 31 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2024, extended (an extension) to 31 Dec 2025 — both dates have passed with no OC on file. An extension application filed on 31 Dec 2024 is pending with K-RERA — until it is approved, the registration stands lapsed.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Yojana Moghe vs Aqua Vistainterest on delay period and fixing of design issuesAUTHORITY03/11/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

2 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved04-06-2019Aqua VistaBWSSB NOCmodified 1 1 3 1 1 1.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved22-11-2019Aqua VistaCFE Expansion 1 1 1 2 1 1.pdf
KSPCB- MOEF (Above 50 Acres)Approved14-03-2018Aqua VistaEC 1 2 3 1.pdf
KPTCL- BESCOMApproved02-09-2006Aqua vistaBescom NOC 1 2 1 1.pdf
Fire and SafetyApproved16-12-2024Aqua VistaFire CC 1.pdf
Labour and Education DepartmentApproved18-01-2020Aqua VistaLabour Cess 1 1 2 1.pdf
Airport Authority of IndiaApproved02-03-2020Aqua VistaAirport Noc 1 1 2 1.pdf
BSNL/Telecommunication DepartmentApproved05-08-2011Aqua VistaBSNL NOC 1 1 1 1.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantDhirendra Kumar Dhal2216912008Bengaluru Urban, Karnataka - 560093
EngineerDesign Tree Service Consultant Pvt LtdBCCL/BL-3.6/SE- 0061/21-222008Bengaluru Urban, Karnataka - 560078
ArchitectRathi AssociatesBCCL/BL-3.6/A-0294/2021-221976Bengaluru Urban, Karnataka - 560008
ContractorConsolidated Construction Consortium Limited-1996Chennai, Tamil Nadu - 600086

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q3): ₹3.64 Cr collected from buyers, ₹2.72 Cr withdrawn from the project's escrow account.

Construction progress100% → 100% (+0 pts)
Units sold/booked as registered173/181 (96%)
Buyer collections in available QPRs₹3.64 Cr
Escrow withdrawals in available QPRs₹2.72 Cr (0.75x collections)
  • 96% of registered units are shown as sold/booked, but no completion certificate is on file yet.
  • The filed unit sales count did not move across the available QPR window because the project was already effectively sold out.
  • The builder has drawn 0.75x of buyer collections from escrow (about 75% of the ₹4 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹77.0 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: FEDERAL BANK OF INDIA Koramangala, Bangalore IFSC Code : FDRL0001437 Pin Code : 560095. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Electronic City8 km
MG Road / city centre12 km
Bellandur–Marathahalli belt13 km
Outer Ring Road / Manyata20 km
Whitefield IT hub21 km
Kempegowda Int'l Airport39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Poppy Realtors.
2 complaints on the K-RERA register against Poppy Realtors in Bangalore.

Other RERA-registered projects in Hulimavu

Major developers building in Hulimavu

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Aqua Vista?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026