Bangalore/Project record

K-RERA · the public record

BHOO AABHARANA

Bengaluru East · BHOO DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

100%construction reportedQ1 2026 filing
0units not bookedof 116 · Q1 2026 filing
30 Apr 2025declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

30 Apr 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

2BHK
60
3BHK
56

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.3registered acres

86.7registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/140923/006261

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 April 2025
Land area5,416 sq m (1.3 acres)
Homes registered116
Tower/wing entries4
Unit mix60 × 2BHK, 56 × 3BHK

In context

Density86.7 homes per acre
Density in context68th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units116Total inventory registered with K-RERA.
Official carpet area10,667 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area17,892 sqmUseful scale context when comparing density and project cost.
Registered land area5,416 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.37Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries4Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)116Separate filed counts; these categories may overlap and are not added together.
Covered-parking field131Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBBMP/Ad.Com./MDP/0262/22-23Use this to match the sanctioned drawing set shown by the builder.
Plan approval date09-03-2023
Project start date23-12-2022

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2BHK6052%5,300 sqm
3BHK5648%6,530 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A3282813 m
B3282813 m
C3242413 m
D3363613 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 116 official flat/unit rows, matching the 116 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK6079.5-95.5 sqm36.8-43.8 sqm60
3 BHK56101.5-130.3 sqm46.7-59.4 sqm56

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
D3680.8-130.3 sqm37.3-59.4 sqm36
A2886.6-118.1 sqm39.8-54.2 sqm28
B2881.2-119.7 sqm37.4-54.7 sqm28
C2479.5-124.4 sqm36.8-56.9 sqm24
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A001A03 BHK117.1 sqm53.6 sqm1
A002A02 BHK93.8 sqm43.3 sqm1
A003A03 BHK118.1 sqm54.2 sqm1
A004A03 BHK116.6 sqm53.5 sqm1
A005A02 BHK86.6 sqm39.8 sqm1
A006A02 BHK86.6 sqm39.8 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

20 of 44 compliance document slots are filed as Not Applicable; the remaining 24 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Apr 2025, extended (Section 6 Extension) to 30 Apr 2026 — both dates have passed with no OC on file. The extension on file was granted on 11 Jun 2025 (K-RERA extension no. EX/PRM/KA/RERA/1251/446/PR/250611/006261) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note Fire NOC and environmental clearance are not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows them as "not found in catalog", that is why; ask the builder directly whether they apply here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

7 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved04-08-2023BWSSB NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved24-07-2023KSPCB CFE.pdf
KPTCL- BESCOMApproved03-06-2023BESCOM NOC.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantNirmala Sreenivasulu2179072006Bengaluru Urban, Karnataka - 560037
EngineerKumar C GBCC/BL-3.6/SE-0349/19-202020Bengaluru Urban, Karnataka - 560090
ArchitectRam Prasad MandalapuCA/2014/658752022Vizianagaram, Andhra Pradesh - 520004
ContractorAkshay Soumya Vishnu P S-2019Bengaluru Urban, Karnataka - 560043

Builder track record

RERA filing

Bhoo Developers has 2 other K-RERA-registered projects in our records. 2 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a higher delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹9.84 Cr collected from buyers, ₹4.44 Cr withdrawn from the project's escrow account.

Construction progress100% → 100% (+0 pts)
Units sold/booked as registered116/116 (100%)
Buyer collections in available QPRs₹29.53 Cr
Escrow withdrawals in available QPRs₹13.32 Cr (0.45x collections)
  • 100% of registered units are shown as sold/booked, but no completion certificate is on file yet.
  • The builder has drawn 0.45x of buyer collections from escrow (about 45% of the ₹30 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹44.6 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: STATE BANK OF INDIA Banaswadi IFSC Code : SBIN0007986 Pin Code : 560043. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata5 km
MG Road / city centre12 km
Whitefield IT hub14 km
Bellandur–Marathahalli belt14 km
Kempegowda Int'l Airport16 km
Electronic City24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Bhoo Developers.
Bhoo Developers has 3 projects registered in Bangalore, 1 completed.

Other projects by this builder in Bangalore

Other RERA-registered projects in Kothanur

Major developers building in Kothanur

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Bhoo Aabharana?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026