RERA Property Intelligence Report · Preview

GM GLOBAL TECHIES TOWN TOWER- A

Gulam Mustafa Enterprises · Anekal · K-RERA PRM/KA/RERA/1251/308/PR/170928/001304

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
3
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

1,406
Registered units
₹413.8 Cr
Est. construction cost
Units profiled
28
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units1,406Total inventory registered with K-RERA.
Registered land area33,516 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings1Official tower/wing count in the K-RERA detail page.
Parking disclosed1,596 total (185 open) — 1.14 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date18-02-2017

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower A311,4061,596-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 1,406 official flat/unit rows, matching the 1,406 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK95558.5-74.8 sqm16.7-21.4 sqm955
3BHK45197.5-113.8 sqm27.9-32.5 sqm451

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower A1,40658.5-113.8 sqm16.7-32.5 sqm1,406
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A0101Tower A03BHK113.8 sqm32.5 sqm1
A0102Tower A02BHK74.8 sqm21.4 sqm1
A0103Tower A02BHK74.8 sqm21.4 sqm1
A0104Tower A02BHK74.8 sqm21.4 sqm1
A0105Tower A02BHK74.8 sqm21.4 sqm1
A0106Tower A03BHK97.5 sqm27.9 sqm1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~859 sqft — mid-format homes (2–3BHK territory), not compact stock. This is a mid-scale project — 1406 homes across 1 tower. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 1,596 parking spaces for 1,406 homes (~1.1 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~23 sqm per home; across all 1,406 homes that is ~96% of the plot — a healthy sign: buyers collectively hold close to all the land. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 23 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (54 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Devi Narayan Jaitly vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTDRefund of booking amount from builderAUTHORITY30/07/2025
Roja Kunala vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTDREFUND FULL AMOUNT of downpayment and home loan settlement needed due to delay in projectAUTHORITY29/07/2025
HARSH SRIVASTAVA vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTD.Return of full amount with interest and compensationAUTHORITY29/07/2025
Hariprasad T N vs M/S.GULAM MUSTAFA ENTERPRISESHelp to get the refund of paid amount with interestAUTHORITY29/06/2026
Aditya Poddar vs SUKESH JAIN, M/S GULAM MUSTAFA ENTERPRISES PVT LTDTo get my refund amount which is RS 1 Lac/AUTHORITY27/06/2023
NATARAJ C vs M/S.GULAM MUSTAFA ENTERPRISESSo request for interest on delay period as per the aggrement which is SBI MCLR +2% for the paid amount from 18 feb 2022 to till dateAUTHORITY24/06/2025
MS ANKITA BARANWAL AND ANOTHER vs M/S.GULAM MUSTAFA ENTERPRISESRefund with compensation of paid amount against the flatAUTHORITY21/05/2024
Prashant Kumar vs GM GLOBAL TECHIES TOWN TOWER- ADelayed interest and possession.AUTHORITY18/06/2024
Partha Pratim Buragohain vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTD.Please help to process the refund of 1Lakh rupeesAUTHORITY17/06/2025
Esshan Gupta vs M/S.GULAM ,MUSTAFANeed help from RERA to take appropriate action against the builder for the delay and misconduct along with assurance for compensationAUTHORITY17/02/2026
Mohammad Jarrar vs ALLAM INFINITE INDIA PVT LTDTimely delivery or refund of amount at current rates at the site.AUTHORITY17/02/2026
Niraj Mantri vs M/S.GULAM MUSTAFAinterest on delay period'AUTHORITY17/02/2026
Ajay Anand vs GM GLOBAL TECHIES TOWN TOWER AInterest amount of Rs. 25 Lakhs incurred for the delay period of 3 years and 4 months at 10.5% per annumAUTHORITY16/08/2025
Aniloy Kishore vs GULAM MUSTAFA ENTERPRISES PVT LTDrefund of amount with interestAUTHORITY16/06/2025
MS UMA DEENDAYAL PATHAK AND ANOTHER vs M/S.GULAM MUSTAFA ENTERPRISESRERA to intervene on 2 aspects, 1. Fast Track the Tower developement & completion as soon as possible 2.Monthly delay compensation from the date of completion expiry dateAUTHORITY16/05/2024
ABHINAV SINGH MUKUND vs GM GLOBAL TECHIES TOWN TOWERSir Madam its my hard earned money please help me in getting my amount refdund. I paid it through credit card which now i will have to pay back. only Rera can help me in getting my refund.AUTHORITY14/06/2024
kailash nailwal vs gulam mustafa enterprisesCompensation due to extended delay in project handoverAUTHORITY12/08/2025
Alankar Ghatak vs GM GLOBAL TECHIES TOWN TOWER ARERA ORDER TO THE DEVELOPER TO PAY COMPENSATION TILL THE HANDOVER IS MADEAUTHORITY12/05/2025
Neha Rathor vs GM GLOBAL TECHIES TOWN TOWER AI want my 10,000 INR of booking amount refunded back to me. Reason is that I want to cancel the booking due to non-disclosure of facts from builder. Their facts about the project are not true.AUTHORITY12/05/2025
Satyaprakash Dixit vs M/s.Gulam Mustafa Enterprises Pvt LtdCompensate House Rent for the delay periodAUTHORITY11/08/2025
Aqibur Rahman Jalal vs M/s.Gulam Mustafa Enterprises Pvt Ltd M/S Patel Reality India LimitedNeed Compensation from Builder for the delay in handover. Builder has to pay the Pre EMI till possession.AUTHORITY11/08/2025
DHIMMER HARDHIK ASHWIN KUMAR vs GM GLOBAL TECHIES TOWN TOWER-ACompensation on delay, Handover with OC.AUTHORITY11/07/2023
Prasanta Kumar Patra and Sanjukta Sahoo as Co-app vs GM GLOBAL TECHIES TOWN TOWER Ainterest on delay period to be paid by builderAUTHORITY11/06/2025
ashish ranjan vs GULAM MUSTAFA ENTERPRISES PVT LTDinterest on delay periodAUTHORITY10/06/2025
BHAWANA MOHANTY vs Gulam Mustafa Enterprises Private LimitedInterest on delay periodAUTHORITY10/04/2026
Baskar vs Gulam Mustafa Enterprises Pvt Ltdi have paid the entire cost of the apartment upfront, i request the interest money as outlined in the agreement for the entire duration of delay.AUTHORITY10/04/2026
CAPACITE INFRAPROJECTS LIMITED vs M/s.Gulam Mustafa Enterprises Pvt LtdDirections from Hon'ble authority for registration deeds of conveyance in relation to the 24 Units/Apartments listed in Table . Deliver possession of the 24 Units/Apartments listed in TableAUTHORITY09/01/2026
Mohit Saxena vs M/s.Gulam Mustafa EnterprisesComplete Refund of paid amount with appreciation cost.I need the refund on per square foot price of the current selling cost or what they received along with Interest I paid to bank, whatever is more.AUTHORITY08/10/2025
Charu Singh vs M/S.GULAM MUSTAFA ENTERPRISESComplete Refund of paid amount with appreciation cost.I need the refund on per square foot price of the current selling cost or what they received along with Interest I paid to bank, whatever is more.AUTHORITY08/10/2025
Dipti Prakash Chinara vs GULAM MUSTAFA ENTERPRISESThe delivery date should be declared and prorated compensation must be extendedAUTHORITY07/04/2025
Amarchand chandran vs GULAM MUSTAFA ENTERPIRSESTo complete the flat at the earliest and also to give the delay compensation as paying the rent and EMI has become coatlyAUTHORITY06/10/2025
Vinay Kumar Pulabaigari vs M/s.Gulam Mustafa Enterprises Pvt LtdInterest on delay period and completion of the projectAUTHORITY06/08/2025
Jathin Kumar P V vs M/s.Gulam Mustafa Enterprises Pvt Ltdinterest on delay periodAUTHORITY06/08/2025
MUHAMMED HASHIM P vs GM GLOBAL TECHIES TOWN TOWER CHelp in getting the refundAUTHORITY06/08/2024
SUBHADA MEKAP vs GM GLOBAL TECHIES TOWN TOWER ARefund of Booking amount Rs 25,000 with interestAUTHORITY06/08/2024
LAVANYA vs GM GLOBAL TECHIES TOWNdirect the promoter to take the full payment and deliver the flat with delay interest for the same under section 18 and 19 of the Act.AUTHORITY05/08/2024
ESHA SHREE vs GM GLOBAL TECHIES TOWN TOWER ARefund our paid moneyAUTHORITY05/08/2024
AMIR KHAN SHERWANI vs GM GLOBAL TECHIES TOWN TOWER APlease help me get back advance money deposited(Rs-50,000)AUTHORITY05/08/2024
MR.SHIVANKAR SINGH vs M/S.GULAM MUSTAFA ENTERPRISES, BANGALORECompensation to be paid out by the builder each month as per the agreement and expedite the construction of the projectAUTHORITY05/06/2024
MR AMAL VINAYAK AND ANOTHER vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTD.Compensation as per RERA agreement from builder for all the loss that we are bearing during the delay in delivery.AUTHORITY05/01/2024
MR MUKTHAR AHMAD PARREY & ANOTHER vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTD & OTHERSCompensation and actions against the BuilderAUTHORITY05/01/2024
Krishna Kunal vs GULAM MUSTAFA ENTERPRISESExact delivery date and interest on delay periodAUTHORITY04/08/2025
Santanu kumar vs GULAM MUSTAFA ENTERPRISESExact Delivery date and interest on delay periodAUTHORITY04/08/2025
GANESH MANJANATH NAYAK vs GULAM MUSTAFA ENTERPRISESWE REQUEST YOU TO TAKE UP THE MATTER WITH BUILDER AND RETURN OUR REFUNDABLE DEPOSITAUTHORITY03/09/2025
Rumeela Bhat vs M/s.GULAM MUSTFA ENTERPRISES PVT LTD.Interest for delay and monthly payment till project handoverAUTHORITY03/06/2025
Wartika Vashishtha vs M/s.GULAM MUSTFA ENTERPRISES PVT LTD.Refund compensation and Closing of Bank LoanAUTHORITY03/06/2025
Josephine Anto Roopa vs M/s.GULAM MUSTFA ENTERPRISES PVT LTD.Advance refund from GM InfinityAUTHORITY03/06/2025
SAMIKSHYA MOHANTY vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTDInterest on delay periodAUTHORITY02/08/2025
Akshay Rajendra Lunawat vs M/S.GULAM MUSTFA ENTERPRISESCompensation from builder against the delay till possessionAUTHORITY02/05/2025
MOLLETI VAMSI BHASKAR vs ALLAM INFINITE INDIA PVT LTDRefund of Advance amount paid of Rupees Two Lacs plus Interest till dateAUTHORITY02/04/2026
Raja Perumal vs M/S.GULAM MUSTA ENTERPRISES PVT LTDNeed delayed compensation till possession and builder to fasten the construction with good quality.AUTHORITY01/07/2025
Supriya Mohanty vs m/s.GULAM MUSTAFA ENTERPRISES PVT LTD.Please help in returning the total advance amount taken by builder(Rs 6 Lacs)AUTHORITY01/07/2025
Anuj Kumar Agrawal vs M/S.GULAM MUSTAFA ENTEERPRISES PVT LTDPlease ask builder to refund booking amountAUTHORITY01/07/2025
Hariprasad T N vs Gulam Mustafa Enterprises Pvt LtdRefund of amount paid with interest as per RERA ActAUTHORITY01/04/2026

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (74 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190218/0002184
18-02-2019
Amount to be refunded due to non compliance of wordsGM GLOBAL TECHIES TOWN TOWER C (another project by this promoter)DISPOSED AO
CMP/191221/0003014
21-12-2019
Flat given to different customer without notice and taking booking installment with fake promisesGM GLOBAL TECHIES TOWN TOWER- ADISPOSED AO
CMP/220811/0009877
11-08-2022
Delay in HandoverGM GLOBAL TECHIES TOWN TOWER C (another project by this promoter)DISPOSED AO
CMP/191020/0004270
20-10-2019
Cheat / Fraud by GM Infinite - BangaloreGM GLOBAL TECHIES TOWN TOWER- ADISPOSED AUTHORITY BENCH6
CMP/220111/0008775
11-01-2022
Project is stalled, looking for immediate possession of FlatGM ELEGANCE TOWER-1 (E-12) (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/210826/0008274
26-08-2021
Request for Refund of Amount paid with InterestGM ELEGANCE TOWER-1 (E-12) (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/211113/0008552
13-11-2021
Refund not done for blocking amount after cancellationGM GLOBAL TECHIES TOWN TOWER C (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/220307/0009082
07-03-2022
Builder is not refunding down payment or Bank loan partial disbursement amountGM ELEGANCE TOWER-1 (E-12) (another project by this promoter)DISPOSED AUTHORITY BENCH5

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectMr.Jayaprakash Narayan-20025th A Block, Koramangala
Structural engineerMr. B.E. Pruthviraja---

Builder track record

RERA filing

Gulam Mustafa has 3 other K-RERA-registered projects in our records. 2 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹29.4 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC BTM Layout (IFSC HDFC0000885, a/c …1151). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Electronic City3 km
Bellandur–Marathahalli belt13 km
MG Road / city centre18 km
Whitefield IT hub19 km
Outer Ring Road / Manyata25 km
Kempegowda Int'l Airport42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Gulam Mustafa.
Gulam Mustafa has 4 projects registered in Bangalore.
3 complaints on the K-RERA register against Gulam Mustafa in Bangalore.

Other projects by this builder in Bangalore

GM Global Techies Town Tower C
No filings
GM Global Techies Town Tower-B
No filings

Other RERA-registered projects in Electronic City

Major developers building in Electronic City

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.