K-RERA · the public record
GM GLOBAL TECHIES TOWN TOWER C
Anekal · Gulam Mustafa Enterprises
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
18 Aug 2021
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
K-RERA registration · read 20 Sep 2026
Inventory & scale
What this registration contains.
Filed categories, unchanged · K-RERA registration · read 20 Sep 2026
The whole registration
8.3registered acres
171.5registered units per acre
The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.
From another project · Prestige Park Grove
A larger advertised area. Almost the same carpet area.
In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.
This illustrates the report format. These findings concern the named sample, not this project.
Read the sample report ↗
The source record
The details behind the headline.
K-RERA · PRM/KA/RERA/1251/308/PR/170928/001289
This project, on the record
The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.
On the register
In context
Values as crawled from the official K-RERA record; context percentiles name their comparison population.
Official Registry Facts
Official project scale
RERA filingRegistration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Registered units | 1,416 | Total inventory registered with K-RERA. |
| Registered land area | 33,404 sqm | The land area attached to this K-RERA registration. |
| Sanctioned FAR/FSI | 3.25 | Higher FAR generally means a denser vertical build, subject to site layout and open-space design. |
| Registered tower/wing entries | 1 | Official tower/wing count in the K-RERA detail page. |
| Parking total (reconciled) | 1,596 | Separate filed counts; these categories may overlap and are not added together. |
| Open-parking field | 187 | Separate filed counts; these categories may overlap and are not added together. |
| Garage field | 1,606 | Separate filed counts; these categories may overlap and are not added together. |
| Project start date | 18-02-2017 |
Official inventory & towers
RERA filingK-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.
Registered tower / wing summary
| Tower/wing | Floors | Units | Parking | Height |
|---|---|---|---|---|
| C | 31 | 1,416 | 1,596 | - |
Official unit register
RERA filingK-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 1,416 official flat/unit rows, matching the 1,416 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.
By unit type
| Unit type | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| 2BHK | 955 | 58.5-74.8 sqm | 16.7-21.4 sqm | 955 |
| 3BHK | 461 | 97.5-113.8 sqm | 27.9-32.5 sqm | 461 |
By tower / wing
| Tower/wing | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| C | 1,416 | 58.5-113.8 sqm | 16.7-32.5 sqm | 1,416 |
Show sample official unit rows
| Unit | Tower | Floor | Type | Carpet | UDS | Parking |
|---|---|---|---|---|---|---|
| C0101 | C | 0 | 3BHK | 97.5 sqm | 27.9 sqm | 1 |
| C0102 | C | 0 | 2BHK | 74.8 sqm | 21.4 sqm | 1 |
| C0103 | C | 0 | 2BHK | 74.8 sqm | 21.4 sqm | 1 |
| C0104 | C | 0 | 2BHK | 74.8 sqm | 21.4 sqm | 1 |
| C0105 | C | 0 | 2BHK | 74.8 sqm | 21.4 sqm | 1 |
| C0106 | C | 0 | 3BHK | 97.5 sqm | 27.9 sqm | 1 |
Legal, Approvals & Project Team
Litigation & compliance
RERA filingNo litigation declared on this project's K-RERA filing.
All 25 standard compliance document slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
⚠ Registration validity has lapsed: originally due 18 Aug 2021, extended (Section 6 Extension) to 18 May 2023 — both dates have passed with no OC on file. The extension on file was granted on 07 Mar 2023 (K-RERA extension no. EX/PRM/KA/RERA/1251/308/PR/230307/001289) — it has been used, its deadline has also passed, and no further extension is recorded.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
K-RERA enforcement record (the regulator's own defaulter list & penalty orders)
⚠ Listed on K-RERA's official DEFAULTER list.
K-RERA complaint orders (91 complaints against a project of this name on K-RERA's orders register)
| Parties | Relief sought | Disposal | Order date |
|---|---|---|---|
| Syed Irfan Ahmed vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTD | i am burden by paying EMI and rent together from past 1 year. now developer saying possession in march 2023, making delay of 2 years, I need compensation from developer as per RERA regulation | AUTHORITY | 31/01/2024 |
| JINKA ANIL KUMAR vs M/s.Gulam Mustafa Enterprises Pvt Ltd | COMPENSATION FOR DELAYED PROJECT AND PAY THE INTREST WITH HIGH RATE | AUTHORITY | 31/01/2024 |
| PRANNAY SRIVASTAVA vs GM GLOBAL TECHIES TOWN TOWER C | Project is delayed and according to Construction Agreement or Government Norms seeking help from RERA for Compensation. | AUTHORITY | 30/08/2023 |
| Abhinay Prakash Pandey vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTD | I would like RERA to interfere here and direct the builder to provide full refund inclusive of the interest paid and cancel the flat for the complainant | AUTHORITY | 30/07/2025 |
| POULAMI BASU vs M/S.GULAM MUSTFA ENTERPRISES PVT LTD | Need Help from RERA in recovering the refund from the builder. | AUTHORITY | 30/07/2025 |
| Saurabh Sharma vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTD | REFUND OF AMOUNT PAID ALONGWIYTH INTEREST @ 24%, AND LITIGATION EXPENSES | AUTHORITY | 30/07/2025 |
| SATISH HONMUTE vs M/s gulam Mustafa Enterprised Pvt Ltd. | Refund of blocking amount | AUTHORITY | 30/05/2026 |
| L Ananth Narayan vs Gulam Mustafa Enterprises Pvt Ltd | Interest on delay period | AUTHORITY | 30/03/2026 |
| Mohan N V vs M/S.GULAM MUSTAFA ENTERPRISES | Quick delivery of flat, Interest on delay period of Rs.9,66,563 (Calculated until 14-03-2025), and legal fee refund of Rs.1,15,000 | AUTHORITY | 29/06/2026 |
| MR JAIKRISHNAN vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTD | Speedy completion of the project and Compensation for the delays as per the agreement | AUTHORITY | 28/02/2025 |
| manas sikdar vs gm global techies town tower c | RERA Order to Builder on the Delays and compensations | AUTHORITY | 27/02/2024 |
| birendra kumar sahu vs gulam mustafa enterprises | Builder should pay the delayed compensation immediately and start paying the compensation on a monthly basis.Builder should complete project within reasonable time with all promised amenities. | AUTHORITY | 27/02/2024 |
| SURYA KUMAR S vs GM GLOBAL TECHIES TOWN TOWER C | Compensation for the delay of flat; along with the rental amount we are paying. | AUTHORITY | 26/09/2023 |
| RAMAWATI DEVI vs GM GLOBAL TECHIES TOWN TOWER C | RERA ORDER BUILDER FOR DELAY COMPENSATION | AUTHORITY | 25/04/2024 |
| BHAGYASHREE SURYAVANSHI vs GM GLOBAL TECHIES TOWN TOWER C | RERA must ask builder for possesion date and compensation for delay. | AUTHORITY | 25/04/2024 |
| VARUN NIMBALAL vs G M GLOBAL TECHIES TOWN | I must get the respective compensation for the delayed period and make sure that Builder must be completing and giving possession as early as possible | AUTHORITY | 25/03/2025 |
| TUHIN BHOWMIC vs GM GLOBAL TCHIES TOWN TOWER C | RERA should order builder to pay compensation for delaying the project handover. | AUTHORITY | 23/08/2023 |
| INDRANIL SEN vs GULAM MUSTAFA ENTERPRISES | Compensation from builder | AUTHORITY | 23/08/2023 |
| RIJAS P K vs GULAM MUSTAFA ENTERPRISES PVT LTD | Project has been delayed from May 2022 and need help from RERA to get delay compensation as per agreement until delivery . | AUTHORITY | 23/08/2023 |
| SAI JAI GANESH GURUBARAN vs GM GLOBAL TECHIES TOWN TOWER C | RERA order to the builder to compensate for the delay as per the provisions outlined. | AUTHORITY | 23/05/2024 |
| DARSHAN GOPAL R vs GM GLOBAL TECHIES TOWN TOWER C | Compensation to be given until possession of apartment is given. | AUTHORITY | 23/04/2024 |
| UPAMANYA MODAK vs GM GLOBAL TECHIES TOWN TOWER C | Compensation full Amount | AUTHORITY | 23/04/2024 |
| PRIYANKA KUMARI & SHAILENDRA KUMAR vs GULAM MUSTAFA ENTERPRISES | RERA ORDER TO THE BUILDER FOR DELAY COMPESATION | AUTHORITY | 23/04/2024 |
| SUMITH SINGH vs GM GLOBAL TECHIES TOWN TOWER C | I am seeking compensation from builder as they failed to deliver by the date they promised and also failed to deliver by the extension RERA provided. | AUTHORITY | 23/04/2024 |
| K PRADEEP KUMAR REDDY & MEGHA V S vs GM GLOBAL TECHIES TOWN TOWER-C | RERA ODER TO THE BUILD FOR DELAY COMPENSATION TILL I GET POSSESSION OF THE FLAT | AUTHORITY | 22/08/2023 |
| Arindam Dhar vs GULAM MUSTAFA ENTERPIRSES PVT LTD | Refund of entire sale consideration of Rs.67,16,985/- with interest @ 18 % P.A, & Grant such other relief if any, as this authority deems fit in the interest of justice and equity | AUTHORITY | 22/07/2025 |
| Soumendra Kumar Dash vs GM GLOBAL TECHIES TOWN TOWER C | I want the interest amount from the builder on delay period till possession of my Flat. | AUTHORITY | 21/07/2025 |
| Mahesh M Pai vs GM GLOBAL TECHIES TOWN TOWER C | 1. Compensation and handover of GTT Tower C with committed quality along with agreed amenities 2. Compensation for delay (Paid in monthly until builder provides the possession) | AUTHORITY | 20/09/2023 |
| ARINDAM DHAR AND NEHA PUROHIT vs GM GLOBAL TECHIES TOWN TOWER-C | Return of amount and compensation | AUTHORITY | 20/02/2024 |
| RISHABH TAKA vs GM GLOBAL TECHIES TOWN TOWER C | 1. Monthly compensation to me @9.5% on the amount paid by me to the builder for delay beyond 18-05-2022. 2. In case the penalty is not paid monthly, the interest should start compounding monthly. | AUTHORITY | 20/02/2024 |
| RITIKA MAHESHWARI vs GM GLOBAL TECXHIES TOWN TOWER C | Compensation & possession of flat at the earliest. | AUTHORITY | 20/02/2024 |
| SUDIPTA MAJUMDAR vs GM GLOBAL TECHIES TOWN TOWER A | Handover of the flats along with compensation mentioned in the sale and construction agreement. | AUTHORITY | 18/06/2024 |
| SIBANI ROUT vs GM GLOBAL TECHIES TOWN TOWER C | Compensation for the delay in handover + Handover of Apt C2017 | AUTHORITY | 18/06/2024 |
| Neeraj Lohia vs M/S.GULAM MUSTAFA | Kindly help me getting the refund of the advances paid | AUTHORITY | 17/02/2026 |
| Sravya Bommakanti vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTD | I urge RERA to direct the developer to complete my flat registration immediately and pay the interest on delay period and keep me updated of my complaint's status | AUTHORITY | 16/08/2025 |
| B Varadaraj vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTD | Refund of booking amount with interest | AUTHORITY | 16/06/2025 |
| SHASHI KANT VERMA vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTD | Kindly order the builder for delay compensation. | AUTHORITY | 16/01/2024 |
| BHASKAR BHARDWAJ vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTD | Please instruct to builder for timely deliver of project and also ask them to compensate their customers | AUTHORITY | 16/01/2024 |
| RAVISH TAK vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTD | RERA should take a concern of completion of the project with Full COMPENSATION on the delay | AUTHORITY | 16/01/2024 |
| NIRANJAN ANIRUDHA VILADKAR vs GM GLOBAL TECHIES TOWN TOWER C | Kindly order the builder to pay delay compensation as per the agreement beginning May 2022 | AUTHORITY | 14/06/2024 |
| ABHISHEK S vs GM GLOBAL TECHIES TOWN TOWER C | Need compensation from the builder for my losses | AUTHORITY | 14/06/2024 |
| NIHAR RANJAN vs COLUMBIA INFRA HOLDINGS | RERA ORDER BUILDER FOR DELAY COMPENSATION | AUTHORITY | 14/02/2024 |
| DEEPIKA JAIN vs GULAM MUSTAFA ENTERPRISES PRIVATE LIMITED PATEL ENGINEERING LIMITED | Get the possession date from builder with proper compensation from builder | AUTHORITY | 13/11/2023 |
| RAKESH RANJAN vs GM GLOBAL TECHIES TOWN TOWER C | Requesting you to kindly help us get possession with delay compensation to incur the rent paid as per the provision of K-RERA | AUTHORITY | 13/01/2025 |
| bibash saha vs gm global technies town tower c | RERA Order to the Builder for delay Compensation and hand over the flat as soon as possible | AUTHORITY | 12/12/2023 |
| arun kumar ps vs gm global techies town towe C | Need delay compensation from the RERA completion date to till the time handover as per Rera rules | AUTHORITY | 12/12/2023 |
| Akshita Monga vs GULAM MUSTAFA ENTERPRISES PVT LTD | Please help in getting our refund on priority. | AUTHORITY | 12/05/2025 |
| Sangram Keshari Satapathy vs gm global techies town tower c | interest on delay period | AUTHORITY | 11/07/2025 |
| manab mitra and rupsa mitra vs gulam mustafa | Handover of the flats along with compensation mentioned in the sale and construction agreement. | AUTHORITY | 11/07/2024 |
| ROHITH G vs GM GLOBAL TECHIES TOWN TOWER A | CANCELLATION OF SALE AGREEMENT, COMPENSATION & REFUND. | AUTHORITY | 11/06/2025 |
| manish kumar singh vs gm global techies town tower c | RERA to order for delay compensation( interest part of the amount disbursed i am paying to bank) or full refund with interest if project is not completed. | AUTHORITY | 10/09/2024 |
| KAUSTAV BISWAS vs GM GLOBAL TECHIES TOWN TOWER C | Rera order to the builder for compensation and immediate possession | AUTHORITY | 09/05/2024 |
| Satendra Kumar Musla vs GULAM MUSTAFA | Refund of full amount paid including Sale Amount, registration & Legal & TDS charges, Interest & penalties, Legal action and removal of any unauthorised case on us for this wrong property registration | AUTHORITY | 09/03/2026 |
| CAPACITE INFRAPROJECTS LIMITED vs M/s.Gulam Mustafa Enterprises Pvt Ltd | Directions from Hon'ble authority for registration deeds of conveyance in relation to the 24 Units/Apartments listed in Table .Deliver possession of the 24 Units/Apartments listed in Table | AUTHORITY | 09/01/2026 |
| ABHRAJYOTHI SEN vs GM GLOBAL TECHNIES TOWN TOWER C | Refund of Rs - 6,15,000 in case they dont provide me the legal documents for verification and if they found not in line with govt. approvals and exit from the project | AUTHORITY | 09/01/2024 |
| Kurinji Meenakshi D vs gulam mustafa enterprises pvt ltd | 1. Request Hon KA RERA to direct the respondent cancel the allotment and immediately refund the entire amount with interest (MCLR+2%) . | AUTHORITY | 07/07/2025 |
| MR.TULU BAIDYA vs M/S.GULAM MUSTAFA ENTERPRISES AND ANOTHER | Refund of Booking amount on cancelation | AUTHORITY | 07/03/2025 |
| MR NILESH PAWATE vs M/S.GULAM MUSTAFA ENTERPRISES | I request a full refund of the booking amount with compensation and interest | AUTHORITY | 07/03/2025 |
| ARINDAM DHAR vs GM GLOBAL TECHIES TOWN TOWER-C | Project completion , delivery of flat and compensation for bank interest and delay | AUTHORITY | 07/03/2024 |
| MR.JESWIN VARGHESE vs M/S.Gulm Mustafa Enterprises, Bangalore | Request RERA to intervene and return our booking amount of 2 lakhs as this project is blacklisted by all the major banks in Sep 2022 | AUTHORITY | 05/06/2024 |
| Ajesh Janardhan Nambiar vs gm global techies town tower c | It is very difficult to bear burden of Rent & EMI hence seeking your assistance to get following 2 items completed 1) To complete project at earliest with committed quality 2) Compensation for delay. | AUTHORITY | 05/03/2025 |
| Aditya Singh vs M/s.Gulam Mustafa Enterprses | I need delay compensation from builder for delayed period of time between date promised on rera and when they will handover | AUTHORITY | 05/02/2026 |
| MR RAJAT SAXENA vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTD. | Order the builder to pay me compensation at the rate of 2% more than the bank interest rates, at monthly frequency, as soon as possible. This is to be continued until possession is not provided. | AUTHORITY | 05/01/2024 |
| MR SHIVAKUMAR KOLAGAD vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTD | Looking for big compensation and immediate possession of my flat C1607 Tower C. RERA should monitor these projects regularly. | AUTHORITY | 05/01/2024 |
| MR AMIT SEN vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTD & OTHERS | Request for Refund of total amount paid with interest | AUTHORITY | 05/01/2024 |
| MR MANAS RANJAN MOHAPATRA & ANOTHER vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTD | I want my amount should be refunded and settlement of home loan asap | AUTHORITY | 05/01/2024 |
| SOORAJ K V vs GULAM MUSTAFA ENTERPRISES PVT LTD | Need your kind intervention on delay compensation and to make sure project completion at the earliest | AUTHORITY | 04/09/2023 |
| PRAMIT SEN vs GM GLOBAL TECHIES TOWN TOWER C | Need Compensation for the delay construction | AUTHORITY | 04/09/2023 |
| Kiran M Vijay & Padmavathi H S vs Gulam Mustafa Enterprises Pvt.Ltd., | It is a RERA registered project. So, I request the concerned authorities to take strict action against the builder and force GM builder to provide interest on delay period. | AUTHORITY | 04/08/2025 |
| Ranganayakulu Neppalli vs GM GLOBAL TECHIES TOWN TOWER C | Requesting RERA to help us get our money back (Rs.11,25,000) and compensation as soon as possible. | AUTHORITY | 04/08/2025 |
| Rajat Saxena vs M/s.Gulam Mustafa Enterprises Pvt Ltd | Execution of Sale Deed, Completion of Unit, Transfer of Ownership (Khata) | AUTHORITY | 03/06/2026 |
| SIDDHARTH DAS vs M/s.GULAM MUSTFA ENTERPRISES PVT LTD. | BUILDER TO PROVIDE MONETARY COMPENSATION | AUTHORITY | 03/06/2025 |
| NIDHIN KRISHNAN B vs M/s.GULAM MUSTFA ENTERPRISES PVT LTD. | 1)Completion & handover of GTT Tower C with committed quality along with amenities. 2) Compensation for the delay. | AUTHORITY | 03/06/2025 |
| Prabin vs M/s.GULAM MUSTFA ENTERPRISES PVT LTD. | compensation for the delay | AUTHORITY | 03/06/2025 |
| Azhar Ajaz vs M/s.GULAM MUSTFA ENTERPRISES PVT LTD. | I want to transfer my agreement to the third party. as soon as possible. | AUTHORITY | 03/06/2025 |
| Mrs Chitra Rajendra Ghatnatti vs M/s.GULAM MUSTFA ENTERPRISES PVT LTD. | Want RERA to instruct GM to provide delay compensation till property registration date. | AUTHORITY | 03/06/2025 |
| Sri Harsha Ravi vs M/s.GULAM MUSTFA ENTERPRISES PVT LTD. | Please help us in getting the delayed compensation amount from the builder | AUTHORITY | 03/06/2025 |
| Anupam Das vs M/s.GULAM MUSTFA ENTERPRISES PVT LTD. CMP NO.870 | RERA order to Builder for Delay compensation and Delivery of Flat | AUTHORITY | 03/06/2025 |
| SUBRAT BORDOLOI vs M/S.GULAM MUSTAFA ENTERPRISES PVT LTD | RERA Order to builder to start paying compensation to customer for delayed project and complete the project in next 4-5 months | AUTHORITY | 03/06/2025 |
| Satya Narayan Mohapatra vs M/s.GULAM MUSTFA ENTERPRISES PVT LTD. | Help me get the proper compensation here since the project is delayed or help me cancel the flat and get full refund | AUTHORITY | 03/06/2025 |
| Amit Gupta vs M/s.GULAM MUSTFA ENTERPRISES PVT LTD. | RERA SHOULD ORDER TO THE BUILDER TO PROVIDE COMPENSATION TILL I GET POSSESSION OF MY FLAT. ALSO THEY SHOULD STRICTLY ORDER TO COMPLETE THE PROJECT ASAP AS PER RERA GUIDELINES | AUTHORITY | 03/06/2025 |
| Cibin Varghese vs M/s.GULAM MUSTFA ENTERPRISES PVT LTD. | RERA to intervene here, to order the builder for delay compensation. | AUTHORITY | 03/06/2025 |
| Ravi Prakash vs M/s.GULAM MUSTFA ENTERPRISES PVT LTD. | We are looking for the refund of token money, which they had taken by giving the false promise of national bank loan of 90% | AUTHORITY | 03/06/2025 |
| Aman Kumar Chaudhary vs M/s.GULAM MUSTFA ENTERPRISES PVT LTD. | I WANT THE INTEREST AMOUNT FROM THE BUILDER ON DELAY PERIOD TILL POSSESSION OF MY FLAT. | AUTHORITY | 03/06/2025 |
| Sumeet Kumar Chaudhary & Tanisha Tomar vs M/s.GULAM MUSTFA ENTERPRISES PVT LTD. | Please get our booking amount refunded. We will be highly grateful | AUTHORITY | 03/06/2025 |
| Nirbhan Singh vs M/s.GULAM MUSTFA ENTERPRISES PVT LTD. | I need my booking amount refund with interest and penalty to the builder. | AUTHORITY | 03/06/2025 |
| SANDO STELLANCE vs M/s.Gulam Mustafa Enterprises Pvt Ltd | completion of the project & interest on delay in possesion of apartment (ie period from 2019 till possesion | AUTHORITY | 03/06/2025 |
| Sri Ratna Manoj Pullipudi vs GM GLOBAL TECHIES TOWN TOWER C | Handover of the project and compensation for delay to the buyers | AUTHORITY | 03/04/2024 |
| PRINCE vs GM GLOBAL TECHIES TOWN TOWER C | RERA ORDER BUILDER FOR COMPENSATION | AUTHORITY | 03/04/2024 |
| DOLLY SUSAMMA KOSHY vs GM GLOBAL TEHIES TOWN TOWER C | All of us need a project timeline for completion or need to be paid compensation for delay. | AUTHORITY | 02/06/2025 |
| ANSHUMAN PRAKASH vs M/S.GULAM MUSTAFA ENTERPRISES | 1) Intervention needed to ensure that the project is completed as soon as possible and handover is given 2) Need the delayed compensation as per the agreement and RERA guidelines | AUTHORITY | 02/05/2025 |
⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.
Complaints on this project's K-RERA page (74 complaints listed against this promoter)
| Complaint | Subject (as filed) | Project | Status |
|---|---|---|---|
| CMP/190218/0002184 18-02-2019 | Amount to be refunded due to non compliance of words | GM GLOBAL TECHIES TOWN TOWER C | DISPOSED AO |
| CMP/191020/0004270 20-10-2019 | Cheat / Fraud by GM Infinite - Bangalore | GM GLOBAL TECHIES TOWN TOWER- A (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/191221/0003014 21-12-2019 | Flat given to different customer without notice and taking booking installment with fake promises | GM GLOBAL TECHIES TOWN TOWER- A (another project by this promoter) | DISPOSED AO |
| CMP/210826/0008274 26-08-2021 | Request for Refund of Amount paid with Interest | GM ELEGANCE TOWER-1 (E-12) (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/211113/0008552 13-11-2021 | Refund not done for blocking amount after cancellation | GM GLOBAL TECHIES TOWN TOWER C | DISPOSED AUTHORITY BENCH4 |
| CMP/220111/0008775 11-01-2022 | Project is stalled, looking for immediate possession of Flat | GM ELEGANCE TOWER-1 (E-12) (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/220111/0008776 11-01-2022 | Project is stalled, looking for immediate possession of Flat or compensation | GM ELEGANCE TOWER-1 (E-12) (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/220209/0008999 09-02-2022 | Booking Amount Refund of Rs. 1 Lakh. | GM GLOBAL TECHIES TOWN TOWER- A (another project by this promoter) | DISPOSED AUTHORITY BENCH5 |
Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.
Project team & certifications
RERA filingK-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.
| Role | Name | Registration / licence | Since | Locality |
|---|---|---|---|---|
| Architect | Mr.Jayaprakash Narayan | - | 2002 | 2nd Cross, koramangala |
| Structural engineer | Mr. B.E. Pruthviraja | - | - | - |
Builder track record
RERA filingGulam Mustafa has 3 other K-RERA-registered projects in our records. 2 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.
Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.
Financials & Construction Progress
Financial disclosures
RERA filing⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.
Declared construction cost ÷ registered units averages to ₹33.5 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.
RERA 70% project account is on file: HDFC BTM Layout (IFSC HDFC0000885, a/c …1174). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
Construction photo filings
RERA filingK-RERA has 1 project-photo upload.
These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.
Location & Connectivity
The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Electronic City | 3 km |
| Bellandur–Marathahalli belt | 13 km |
| MG Road / city centre | 18 km |
| Whitefield IT hub | 19 km |
| Outer Ring Road / Manyata | 25 km |
| Kempegowda Int'l Airport | 42 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.