K-RERA · the public record
Ishtaa
· Ikigai Estates
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 16 Jul 2026Progress & dates
The timeline on file.
Promoter-reported construction
K-RERA quarterly filings · Q3 2025 to Q4 2025
declared completion
Not recorded
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
K-RERA registration · read 16 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
K-RERA · PRM/KA/RERA/1254/460/PR/190925/008106
Official Registry Facts
Official project scale
RERA filingRegistration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Approved plan number | CUDA/04/2025-26 | Use this to match the sanctioned drawing set shown by the builder. |
| Plan approval date | 16-06-2025 | |
| Project start date | 01-08-2025 |
Legal, Approvals & Project Team
Litigation & compliance
RERA filingNo litigation declared on this project's K-RERA filing.
2 of 21 compliance document slots are filed as Not Applicable; the remaining 19 slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
Statutory approval status
RERA filing0 of 1 applicable approvals are on file; still outstanding: KPTCL- BESCOM. Confirm each has been granted, not merely applied for, before booking.
10 further authority slots are marked not applicable by the regulator.
| Authority / NOC | Status | Date | File |
|---|---|---|---|
| KPTCL- BESCOM | To Be Applied | - | View NOC |
Project team & certifications
RERA filingK-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.
| Role | Name | Registration / licence | Since | Locality |
|---|---|---|---|---|
| Chartered accountant | chiraag mutha | 265255 | 1990 | Bengaluru Urban, Karnataka - 560028 |
| Engineer | S Ravindra | F-29037 | 2021 | Bengaluru Urban, Karnataka - 560079 |
Financials & Construction Progress
Financial disclosures
RERA filingLatest quarterly filing (2025-Q4): ₹9.55 Cr collected from buyers, ₹6.25 Cr withdrawn from the project's escrow account.
| Construction progress | 63% → 72% (+9 pts) |
| Buyer collections in available QPRs | ₹13.37 Cr |
| Escrow withdrawals in available QPRs | ₹8.22 Cr (0.61x collections) |
- Construction progress moved from 63% to 72% across the filed QPR window.
- The builder has drawn 0.61x of buyer collections from escrow (about 61% of the ₹13 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.
QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.
The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.
RERA 70% project account is on file: IDFC FIRST BANK Sadashivnagar branch IFSC Code : IDFB0080178 Pin Code : 560080. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
Location & Connectivity
The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Outer Ring Road / Manyata | 5 km |
| MG Road / city centre | 7 km |
| Bellandur–Marathahalli belt | 10 km |
| Whitefield IT hub | 11 km |
| Electronic City | 19 km |
| Kempegowda Int'l Airport | 21 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.