Bangalore/Project record

K-RERA · the public record

JEYA GREEN HORIZON

Bengaluru East · JEYA DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

35%construction reportedQ1 2026 filing
105units not bookedof 120 · Q1 2026 filing
31 Dec 2029declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q4 2025 to Q1 2026

declared completion

31 Dec 2029

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3 BHK
56
2 BHK
64

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.8registered acres

68.6registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/210126/008417

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2029
Land area7,082 sq m (1.8 acres)
Homes registered120
Tower/wing entries2
Unit mix56 × 3 BHK, 64 × 2 BHK

In context

Density68.6 homes per acre
Density in context39th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units120Total inventory registered with K-RERA.
Official carpet area9,777 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area17,450 sqmUseful scale context when comparing density and project cost.
Registered land area7,082 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.75Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)120Separate filed counts; these categories may overlap and are not added together.
Covered-parking field121Separate filed counts; these categories may overlap and are not added together.
Open-parking field12Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBBMP/Ad.Com./MDP/0861/24-25Use this to match the sanctioned drawing set shown by the builder.
Plan approval date13-11-2025
Project start date01-12-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK5647%5,392 sqm
2 BHK6453%4,385 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower A3808014.95 m
Tower B3404014.95 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 120 official flat/unit rows, matching the 120 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK6465.4-71.7 sqm49.0-50.5 sqm64
3 BHK5689.7-99.4 sqm64.1-74.6 sqm56

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower A8065.8-99.4 sqm49.0-71.1 sqm80
Tower B4065.4-99.4 sqm49.2-74.6 sqm40
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
G01Tower A03 BHK99.4 sqm71.1 sqm1
G02Tower A02 BHK69.0 sqm49.2 sqm1
G03Tower A02 BHK69.0 sqm49.2 sqm1
G04Tower A02 BHK68.9 sqm49.1 sqm1
G05Tower A02 BHK68.9 sqm49.1 sqm1
G06Tower A02 BHK68.9 sqm49.1 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

2 of 21 compliance document slots are filed as Not Applicable; the remaining 19 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

2 of 3 applicable approvals are on file; still outstanding: Water supply and sewage board. Confirm each has been granted, not merely applied for, before booking.

7 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApplied12-02-2025View NOC
KSPCB- PCB (10 Acres to 125 Acres)Approved20-12-2025KSPCB Noc.pdf
KPTCL- BESCOMApproved14-01-2026BESCOM NOC with Fees paid.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantPoornashekar Reddy B2372582017Bengaluru Urban, Karnataka - 560102
EngineerBALAJI K NBCCL/BL3.6/E0345/21 222021Bengaluru Urban, Karnataka - 560043
ArchitectRangarao InugantiCA/2011/541872011Bengaluru Urban, Karnataka - 560076
ContractorJEYA DEVELOPERS-2022Bengaluru Urban, Karnataka - 560075

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹7.88 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress20% → 35% (+15 pts)
Units sold/booked as registered15/120 (12%)
Buyer collections in available QPRs₹7.88 Cr
  • Construction progress moved from 20% to 35% across the filed QPR window.
  • The builder has drawn 0.00x of buyer collections from escrow (about 0% of the ₹8 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹60.5 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: KOTAK MAHINDRA BANK. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bellandur–Marathahalli belt4 km
MG Road / city centre6 km
Electronic City11 km
Whitefield IT hub11 km
Outer Ring Road / Manyata11 km
Kempegowda Int'l Airport29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Jeya Developers.

Other RERA-registered projects in Marathahalli

Major developers building in Marathahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Jeya Green Horizon?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026