Leaves & Lives Phase 1

Bengaluru East · APG Intelli Homes

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2021declared completionK-RERA registration · read 20 Sep 2026
47registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Row House
47

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

4.1registered acres

11.6registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/180808/001979

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 July 2021
Land area16,400 sq m (4.1 acres)
Homes registered47
Tower/wing entries6
Unit mix47 × Row House

In context

Density11.6 homes per acre
Density in context4th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units47Total inventory registered with K-RERA.
Official carpet area9,597 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area16,400 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI0.11Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries6Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)94Separate filed counts; these categories may overlap and are not added together.
Open-parking field5Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date05-07-2018

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Row House47100%9,597 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
BUILDING 131020-
BUILDING 2324-
BUILDING 331224-
BUILDING 43612-
BUILDING 53714-
BUILDING 631020-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 47 official flat/unit rows, matching the 47 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK26185.9-216.7 sqm95.6-104.6 sqm52
4BHK21216.7-229.7 sqm103.3-108.9 sqm42

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
BUILDING 312185.9-229.7 sqm95.6-108.9 sqm24
BUILDING 110227.4 sqm107.0-108.5 sqm20
BUILDING 610191.0-216.7 sqm97.0-104.7 sqm20
BUILDING 57191.0-216.7 sqm97.0-104.7 sqm14
BUILDING 46185.9-216.7 sqm95.6-104.7 sqm12
BUILDING 22216.7 sqm104.6-104.7 sqm4
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
3BUILDING 104BHK227.4 sqm108.5 sqm2
4BUILDING 104BHK227.4 sqm107.0 sqm2
5BUILDING 104BHK227.4 sqm107.0 sqm2
6BUILDING 104BHK227.4 sqm107.0 sqm2
7BUILDING 104BHK227.4 sqm107.0 sqm2
8BUILDING 104BHK227.4 sqm107.0 sqm2

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

4 of 21 compliance document slots are filed as Not Applicable; the remaining 17 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Jul 2021, extended (Section 6 Extension) to 29 Apr 2023 — both dates have passed with no OC on file. The extension on file was granted on 04 Nov 2022 (K-RERA extension no. EX/PRM/KA/RERA/1251/446/PR/221104/001979) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Jacob Varghese and Amritha Jacob vs APG INTELLI HOMES PRIVATE LIMITEDquashing of the fine and cost re adjustment of tax amount from the time i bought the villa in 2018 and subsequent reduction of tax in 2019 ,AUTHORITY27/02/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (1 complaint listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190607/0003254
07-06-2019
Breach of Agreement in offering compensation for delay in handover63 Degree East - Tower C & D (another project by this promoter)DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectManoj Ladhad, Architecture paradigm-1997koramangala industrial layout, koramangala
Structural engineerRajesh Shirakol, Cratis Designers Pvt Ltd---

Builder track record

RERA filing

Apg Intelli has 6 other K-RERA-registered projects in our records (average reported construction progress 88%). 5 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹126.1 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Richmond Road (IFSC HDFC0000523, a/c …9715). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bellandur–Marathahalli belt6 km
Electronic City7 km
Whitefield IT hub10 km
MG Road / city centre14 km
Outer Ring Road / Manyata20 km
Kempegowda Int'l Airport35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Apg Intelli.
Apg Intelli has 7 projects registered in Bangalore.

Other projects by this builder in Bangalore

63 Degree East - Tower A
No filings
63 Degree East - Tower C & D
No filings
63 Degree East - Tower E
On track · 88% built · 100% sold
63 Degree East - Tower F
No filings
63 Degree East - Tower B
No filings
Leaves & Lives Phase 2
No filings

Other RERA-registered projects in Chikkakannalli

Major developers building in Chikkakannalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Leaves & Lives Phase 1?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026