Bangalore/Project record

K-RERA · the public record

Legacy Madelia

Bengaluru North · Legacy Global Projects

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Aug 2018declared completionK-RERA registration · read 20 Sep 2026
9registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Aug 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3 BHK
3

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

0.2registered acres

37.9registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/309/PR/171024/000882

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 August 2018
Land area962 sq m (0.2 acres)
Homes registered9
Tower/wing entries1
Unit mix3 × 3 BHK

In context

Density37.9 homes per acre
Density in context17th percentile of 525 Bengaluru North projects (median 75.4)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units9Total inventory registered with K-RERA.
Official carpet area793 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area962 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3.23Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)23Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date28-05-2015

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK3100%793 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
LEGACY MADELIA4923-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 9 official flat/unit rows, matching the 9 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK92,721.0-4,986.0 sqft963.0-1,837.0 sqft23

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
LEGACY MADELIA92,721.0-4,986.0 sqft963.0-1,837.0 sqft23
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A-01LEGACY MADELIA03BHK2,910.0 sqft1,036.0 sqft2
A-11LEGACY MADELIA13BHK2,910.0 sqft1,036.0 sqft2
A-12LEGACY MADELIA13BHK2,721.0 sqft963.0 sqft2
A-21LEGACY MADELIA23BHK2,910.0 sqft1,036.0 sqft2
A-22LEGACY MADELIA23BHK2,721.0 sqft963.0 sqft2
A-31LEGACY MADELIA33BHK2,910.0 sqft1,036.0 sqft2

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

9 of 27 compliance document slots are filed as Not Applicable; the remaining 18 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Aug 2018, extended (Section 6 Extension) to 31 Aug 2019 — both dates have passed with no OC on file. The extension on file was granted on 13 Jun 2022 (K-RERA extension no. EX/PRM/KA/RERA/1251/309/PR/220613/000882) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Complaints on this project's K-RERA page (13 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/200529/0005940
29-05-2020
Refusal to Honour Terms of Sale AgreementLegacy Vivienda (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/201124/0007120
24-11-2020
Refund of Sale Consideration with Interest and CompensationLegacy Vivienda (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/210309/0007771
09-03-2021
As per the complaint uploaded.Legacy Vivienda (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/210309/0007772
09-03-2021
As per the complaint uploaded.Legacy Vivienda (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/210309/0007773
09-03-2021
As mentioned in the complaint uploadedLegacy Vivienda (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/210420/0007910
20-04-2021
As per mentioned in the Complaint in the previous page.Legacy Vivienda (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/210420/0007912
20-04-2021
My Booking of Apartement-G-01 of M/S Legacy Salvador (Legacy Global Projects Pvt Ltd)Legacy Salvador (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/210531/0007969
31-05-2021
As per the Complaint uploaded.Legacy Vivienda (another project by this promoter)DISPOSED AUTHORITY BENCH5

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectFHD CONSULTANTS PVT LTD-2001LIC colony, Srinagar colony Hyderabad
Structural engineerANGHA ENGINEERING CONSULTANTS---

Builder track record

RERA filing

Legacy Global has 12 other K-RERA-registered projects in our records (average reported construction progress 59%). 8 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹132.7 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC MILLERS ROAD (IFSC HDFC0001208, a/c …7826). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
MG Road / city centre3 km
Outer Ring Road / Manyata7 km
Bellandur–Marathahalli belt12 km
Whitefield IT hub18 km
Electronic City18 km
Kempegowda Int'l Airport26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Legacy Global. View Legacy Global's full track record →
Legacy Global has 13 projects registered in Bangalore, 1 completed, 2 past RERA deadline.

Other projects by this builder in Bangalore

Legacy Cataleya
Past deadline · 92% built · 25% sold
Legacy Vivienda
Past deadline · 46% built · 7% sold
Legacy Maximus
On track · 48% built · 46% sold

Other RERA-registered projects in Ashok Nagar

Sobha Crystal Meadows Phase 1 Wing 1 To 6

Major developers building in Ashok Nagar

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Legacy Madelia?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026