Mahendra Solterra Aarya Phase-2

Bengaluru South · Mahendra Homes

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

9%construction reportedQ1 2026 filing
522units not bookedof 522 · Q1 2026 filing
31 Dec 2030declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Dec 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Apartment (3 BHK)
522

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

8.3registered acres

62.5registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/281125/008282

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2030
Land area33,791 sq m (8.3 acres)
Homes registered522
Tower/wing entries3
Unit mix522 × Apartment (3 BHK)

In context

Density62.5 homes per acre
Density in context30th percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units522Total inventory registered with K-RERA.
Official carpet area51,743 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area96,355 sqmUseful scale context when comparing density and project cost.
Registered land area33,791 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.249Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)522Separate filed counts; these categories may overlap and are not added together.
Covered-parking field578Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan number182/2025-26Use this to match the sanctioned drawing set shown by the builder.
Plan approval date16-08-2025
Project start date15-01-2026

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Apartment (3 BHK)522100%51,743 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
E1420220244.85 m
F14868644.85 m
G1423423444.85 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 522 official flat/unit rows, matching the 522 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK52280.5-119.7 sqm48.9-77.6 sqm522

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
G23480.5-119.7 sqm48.9-77.6 sqm234
E20280.5-119.7 sqm48.9-77.6 sqm202
F8696.9-119.7 sqm60.2-77.6 sqm86
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
E-0001E03 BHK116.9 sqm74.9 sqm1
E-0002E03 BHK117.9 sqm76.6 sqm1
E-0005E03 BHK80.5 sqm48.9 sqm1
E-0006E03 BHK81.5 sqm49.0 sqm1
E-0007E03 BHK98.5 sqm60.3 sqm1
E-0008E03 BHK96.9 sqm60.2 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

7 of 34 compliance document slots are filed as Not Applicable; the remaining 27 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Complaints on this project's K-RERA page (5 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/191208/0004926
08-12-2019
Company kept my money 38 lakhs for 10 months without agreement - returned 34 lakhs only - asking for compensationMahendra AARNA (another project by this promoter)DISPOSED AO
CMP/200322/0005792
22-03-2020
Refusal of token amount refundMahendra AARNA 5 (another project by this promoter)DISPOSED AO
CMP/210903/0008296
03-09-2021
formation of association, completion of amenities , reasonable maintenance charges and handover of the projectMahendra AARNA (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/220408/0009334
08-04-2022
CLAIM FOR COMPENSATION UNDER SECTION 31 READ WITH SECTION 71 OF REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016Mahendra AARNA (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/220708/0009735
08-07-2022
Builder has denied complete refund against cancellationMahendra AARNA (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

3 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved12-12-2023TMC Chandapura water_NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved24-07-2025KSPCB NOC.pdf
KSPCB- MOEF (Above 50 Acres)Approved22-08-2025MOEF_compressed.pdf
KPTCL- BESCOMApproved08-10-2025Bescom_NOC.pdf
Fire and SafetyApproved07-05-2025Fire_NOC.pdf
Airport Authority of IndiaApproved20-03-2025Airport_Authority_Of_india.pdf
BSNL/Telecommunication DepartmentApproved26-03-2025BSNL NOC.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantCA Vinaykumar Munolimath1179272004Bengaluru Urban, Karnataka - 560059
EngineerRajesh ShirakolM-137173-22018Bengaluru Urban, Karnataka - 560008
ArchitectGirish SCA/2013/599632013Bengaluru Urban, Karnataka - 560070
ContractorSri Elite Plus Construction Pvt Ltd-2022Bengaluru Urban, Karnataka - 560067

Builder track record

RERA filing

Mahendra Homes has 4 other K-RERA-registered projects in our records (average reported construction progress 100%). 2 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.00 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress7% → 9% (+2 pts)
Units sold/booked as registered0/522 (0%)
  • Construction progress moved from 7% to 9% across the filed QPR window.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹44.9 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Karnataka Bank Ltd.. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Electronic City5 km
Bellandur–Marathahalli belt12 km
Whitefield IT hub17 km
MG Road / city centre20 km
Outer Ring Road / Manyata26 km
Kempegowda Int'l Airport41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Mahendra Homes. View Mahendra Homes's full track record →
Mahendra Homes has 5 projects registered in Bangalore, 1 completed.
9 complaints on the K-RERA register against Mahendra Homes in Bangalore.

Other projects by this builder in Bangalore

Mahendra Aarya
Filing overdue · 100% built · 84% sold

Other RERA-registered projects in Chandapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Mahendra Solterra Aarya Phase-2?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026