Bangalore/Project record

K-RERA · the public record

Needs 3 Project276

Bengaluru South · Ds & Jaks Constructions

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2020declared completionK-RERA registration · read 20 Sep 2026
156registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Apartments
32

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

2.2registered acres

70.1registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/171026/000453

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2020
Land area9,004 sq m (2.2 acres)
Homes registered156
Tower/wing entries5
Unit mix32 × Apartments

In context

Density70.1 homes per acre
Density in context39th percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units156Total inventory registered with K-RERA.
Official carpet area2,655 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area9,004 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI~2.13Sanctioned floor-area ratio (≈19,142 sqm sanctioned FAR area ÷ 9,004 sqm land) — higher means a denser vertical build.
Registered tower/wing entries5Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)171Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date11-07-2014

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Apartments32100%2,655 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A83235-
B83235-
C83235-
D83235-
E82831-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 156 official flat/unit rows, matching the 156 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK78738.0-885.0 sqft275.8-332.6 sqft78
3BHK78938.0-1,134.0 sqft41.0-426.9 sqft78

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
A32738.0-970.0 sqft275.8-370.1 sqft32
B32842.0-1,081.0 sqft41.0-412.4 sqft32
C32864.0-1,081.0 sqft316.9-412.4 sqft32
D32741.0-1,028.0 sqft280.6-382.2 sqft32
E28845.0-1,134.0 sqft322.9-426.9 sqft28
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
101A13BHK960.0 sqft360.4 sqft1
102A13BHK970.0 sqft370.1 sqft1
103A12BHK750.0 sqft284.2 sqft1
104A12BHK738.0 sqft275.8 sqft1
201A23BHK960.0 sqft360.4 sqft1
202A23BHK970.0 sqft370.1 sqft1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 23 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2020, extended (Covid Extension) to 30 Sep 2021 — both dates have passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (2 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
sughandit vikas raina vs M/s Ds & Jaks ConstructionsCompensation for Delay in possession of the propertyAUTHORITY11/02/2025
NAZIA AHMAD vs M/S DS & JAKS CONSTRUCTIONSCompensation as 10% interest on amount paidAUTHORITY07/03/2023

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (2 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190709/0003506
09-07-2019
Return of amount according to RERA due to delay in possession(more than 18 months)Needs 3 Project276DISPOSED AO
CMP/191126/0004807
26-11-2019
Return of amount according to RERA due to delay in possession(more than 18 months)Needs 3 Project276DISPOSED AUTHORITY FULLBENCH

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectGnannavel Thirumaran-20042nd Block, R.T Nagar
Structural engineerD.Srinivas---

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹27.6 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: KOTAK MAHINDRA BANK J.P Nagar (IFSC KKBK0000433, a/c …2601). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Electronic City7 km
MG Road / city centre12 km
Bellandur–Marathahalli belt12 km
Outer Ring Road / Manyata19 km
Whitefield IT hub20 km
Kempegowda Int'l Airport38 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Ds Jaks.

Other RERA-registered projects in Hulimavu

Major developers building in Hulimavu

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Needs 3 Project276?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026