K-RERA · the public record
Parkwest - Sapphire- Tower 5
Bengaluru South · Relationship Properties
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2021
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
K-RERA registration · read 20 Sep 2026
Inventory & scale
What this registration contains.
Filed categories, unchanged · K-RERA registration · read 20 Sep 2026
The whole registration
4.2registered acres
59.5registered units per acre
The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.
From another project · Prestige Park Grove
A larger advertised area. Almost the same carpet area.
In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.
This illustrates the report format. These findings concern the named sample, not this project.
Read the sample report ↗
The source record
The details behind the headline.
K-RERA · PRM/KA/RERA/1251/310/PR/171015/000284
This project, on the record
The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.
On the register
In context
Values as crawled from the official K-RERA record; context percentiles name their comparison population.
Official Registry Facts
Official project scale
RERA filingRegistration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Registered units | 248 | Total inventory registered with K-RERA. |
| Registered land area | 16,867 sqm | The land area attached to this K-RERA registration. |
| Sanctioned FAR/FSI | 0.123 | Higher FAR generally means a denser vertical build, subject to site layout and open-space design. |
| Registered tower/wing entries | 1 | Official tower/wing count in the K-RERA detail page. |
| Parking total (reconciled) | 343 | Separate filed counts; these categories may overlap and are not added together. |
| Open-parking field | 25 | Separate filed counts; these categories may overlap and are not added together. |
| Garage field | 0 | Separate filed counts; these categories may overlap and are not added together. |
| Project start date | 29-07-2017 |
Official inventory & towers
RERA filingK-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.
Registered inventory mix
| Type | Units | Share | Official carpet area |
|---|---|---|---|
| Refer Annexure - SPECIFICATIONS | 0 | 0 sqm |
Registered tower / wing summary
| Tower/wing | Floors | Units | Parking | Height |
|---|---|---|---|---|
| SAPPHIRE | 32 | 248 | 343 | - |
Official unit register
RERA filingK-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 248 official flat/unit rows, matching the 248 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.
By unit type
| Unit type | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| 3BHK | 217 | 118.5-141.3 sqm | 54.9-69.1 sqm | 299 |
| 4BHK | 31 | 169.3-169.6 sqm | 76.9-82.5 sqm | 44 |
By tower / wing
| Tower/wing | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| SAPPHIRE | 248 | 118.5-169.6 sqm | 54.9-82.5 sqm | 343 |
Show sample official unit rows
| Unit | Tower | Floor | Type | Carpet | UDS | Parking |
|---|---|---|---|---|---|---|
| 1 | SAPPHIRE | 0 | 3BHK | 140.8 sqm | 69.1 sqm | 2 |
| 2 | SAPPHIRE | 0 | 3BHK | 140.8 sqm | 69.1 sqm | 2 |
| 3 | SAPPHIRE | 0 | 3BHK | 140.8 sqm | 69.1 sqm | 2 |
| 4 | SAPPHIRE | 0 | 3BHK | 140.8 sqm | 69.1 sqm | 2 |
| 5 | SAPPHIRE | 0 | 4BHK | 169.3 sqm | 82.5 sqm | 2 |
| 6 | SAPPHIRE | 0 | 3BHK | 121.3 sqm | 58.5 sqm | 2 |
Legal, Approvals & Project Team
Litigation & compliance
RERA filingNo litigation declared on this project's K-RERA filing.
12 of 38 compliance document slots are filed as Not Applicable; the remaining 26 slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
⚠ Registration validity has lapsed: originally due 31 Dec 2021, extended (Extension) to 31 Dec 2024 — both dates have passed with no OC on file. The extension on file was granted on 09 Nov 2022 (K-RERA extension no. EX/PRM/KA/RERA/1251/310/PR/221109/000284) — it has been used, its deadline has also passed, and no further extension is recorded.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
K-RERA enforcement record (the regulator's own defaulter list & penalty orders)
⚠ Listed on K-RERA's official DEFAULTER list.
1 K-RERA order on this project (PROJECT EXTENSION) — read the order copies on the K-RERA portal.
K-RERA complaint orders (22 complaints against a project of this name on K-RERA's orders register)
| Parties | Relief sought | Disposal | Order date |
|---|---|---|---|
| Harish B vs RELATIONSHIP PROPERTIES PVT LTD & 4 OTHERS | The delivery of the flat is overdue and construction work is stalled, I pray for the refund of money with interest (SBI mclr + 2% ) on the amount rs 1,22,01,479 paid till the settlement date. | AUTHORITY | 30/11/2024 |
| RAJESH KUMAR vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Refund of booking amount with compensation | AUTHORITY | 25/06/2022 |
| MS. RAJ RANI vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Refund of amount with GST and compensation | AUTHORITY | 25/06/2022 |
| AKBAR BAIG vs M/S RELATIONSHIP PROPERTIES PVT LTD & 3 OTHERS | FULL REFUND WITH INTEREST | AUTHORITY | 23/08/2023 |
| HITESH B VYAS vs Parkwest - Sapphire Tower- 5 | INTEREST ON DELAY PERIOD | AUTHORITY | 19/09/2025 |
| suresh kumar dave vs Parkwest - Sapphiree - Tower -5 | INTEREST ON DELAY PERIOD | AUTHORITY | 19/08/2025 |
| nivedith gajapathy vs Parkwest Sapphire-5 | Full refund with compensation | AUTHORITY | 16/06/2025 |
| KAJUDEVI M PAREKH vs Relationship Properties Private Limited | REQUIRE FULL REFUND OF THE MONEY PAID AND COMPENSATION TO INTEREST PAIDS AND OTHER COMPENSATIONS. | AUTHORITY | 16/03/2024 |
| sumit jain vs Parkwest Sappiere -Tower 5 | Interest on delay period | AUTHORITY | 15/07/2025 |
| AANAND VASU vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Commitment or full refund (refund preferred) | AUTHORITY | 12/11/2022 |
| AANAND VASU vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Refund of full amount paid and cancellation of allotment due to breach of agreement and trust. If cancelled before 31 Dec 2021, I do not need to be compensated for interest. | AUTHORITY | 12/11/2022 |
| AANAND VASU vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Refund or compensation as explained above | AUTHORITY | 12/11/2022 |
| SWETA vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | We demand full refund from builder with interest as per RERA act for various violations of RERA Act. | AUTHORITY | 12/11/2022 |
| AANAND VASU vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Refund of amount paid till date with interest accrued till date | AUTHORITY | 12/11/2022 |
| AANAND VASU vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Cancellation of allotment and refund of entire amount paid so far with interest | AUTHORITY | 12/11/2022 |
| HANNULAL TIWARI vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Compensation on the ground of delayed hand over as per the RERA policy. | AUTHORITY | 12/09/2023 |
| Nikisha Jain vs Park west- Sopphire -Tower-5 | Refund total amount with interest | AUTHORITY | 08/10/2025 |
| D MAHENDRA KUMAR vs RELATIONSHIP PROPERTIES PRIVATE LIMITED, ETA KARNATAKA ESTATES LIMITED, ETA CONSTRUCTIONS (INDIA) LIMITED , ETA STAR INFOPARK | cancel the booking and agreement. request them to refund the booking amount with gst and interest | AUTHORITY | 08/02/2024 |
| ANNAMALAI CHOCRALINGAM & REVATHY CHIDAMBARAM vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Refund of Money paid with Interest | AUTHORITY | 06/09/2023 |
| LATHA MANOJ JAIN vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | REFUND THE ADVANCE PAID RS. 3984526/- WITH INTEREST @18% P/A AND COMPENSATION WITH DAMAGES & GST PAID RS. 482972/- | AUTHORITY | 06/08/2024 |
| Vipul Kumar Jain & Sowan Devi vs Relationship Properties Private Limited & 4 others | Penalty for delay in posession and return of our Amounts paid with interest @ 24% p.a | AUTHORITY | 06/06/2024 |
| Jaya Jain & Pushpa Devi vs Relationship Properties Private Limited | Penalty for my family's lost years for a dream home, and refund of my payment with Interest of 24% p.a along with interest and charges levied on me from my bank. | AUTHORITY | 06/06/2024 |
⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.
Complaints on this project's K-RERA page (312 complaints listed against this promoter)
| Complaint | Subject (as filed) | Project | Status |
|---|---|---|---|
| CMP/190311/0002417 11-03-2019 | Refund of Booking amount with GST along with interest and compensation, For revokation of RERA registration granted to the promoter | Parkwest - Sapphire- Tower 5 | DISPOSED AUTHORITY |
| CMP/190311/0002422 11-03-2019 | Refund of booking amount and GST amount paid, along with interest and compensation, to revoke the registration granted by RERA | Parkwest - Sapphire- Tower 5 | DISPOSED AUTHORITY |
| CMP/201009/0006794 09-10-2020 | Delay in Project Delivery as promised in Advertisement and Agrement | Parkwest - Maple - Tower 4 (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/201010/0006804 10-10-2020 | Delay in apartment unit and amenities handover as committed in the Agreemetn | Parkwest - Maple - Tower 4 (another project by this promoter) | DISPOSED AUTHORITY BENCH4 |
| CMP/201010/0006812 10-10-2020 | Delay in Project Delivery as promised in Advertisement and Agrement | Parkwest - Maple - Tower 4 (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/201011/0006814 11-10-2020 | POSSESSION PENDING | Parkwest - Maple - Tower 4 (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/201107/0007032 07-11-2020 | No construction activity/No concrete response from Builder | Parkwest - Sapphire- Tower 5 | DISPOSED AUTHORITY BENCH5 |
| CMP/201127/0007136 27-11-2020 | Breach of Agreement and non response to previous complaint | Parkwest - Sapphire- Tower 5 | DISPOSED AUTHORITY BENCH5 |
Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.
Project team & certifications
RERA filingK-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.
| Role | Name | Registration / licence | Since | Locality |
|---|---|---|---|---|
| Architect | LALIT NARULA | - | 1978 | Ashok Nagar, Bengaluru |
| Contractor | Simplex Infrastructures Limited | - | 1924 | Majestic, Bengaluru |
| Structural engineer | Designtree Service Consultants Private Limited | - | - | - |
Builder track record
RERA filingRelationship Properties has 10 other K-RERA-registered projects in our records (average reported construction progress 65%). 8 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.
Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.
Financials & Construction Progress
Financial disclosures
RERA filing⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.
Declared construction cost ÷ registered units averages to ₹92.3 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.
RERA 70% project account is on file: HDFC FORT BRANCH (IFSC HDFC0000006, a/c …7327). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
Construction photo filings
RERA filingK-RERA has 1 project-photo upload.
These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.
Location & Connectivity
The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| MG Road / city centre | 5 km |
| Outer Ring Road / Manyata | 11 km |
| Bellandur–Marathahalli belt | 14 km |
| Electronic City | 17 km |
| Whitefield IT hub | 21 km |
| Kempegowda Int'l Airport | 30 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.