RERA Property Intelligence Report · Preview
Relationship Properties · Bengaluru South · K-RERA PRM/KA/RERA/1251/310/PR/180222/002637
Report coverage
K-RERA registry & builder-record report
What this report covers
To confirm directly with the builder
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.
Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Registered units | 246 | Total inventory registered with K-RERA. |
| Official carpet area | 25,931 sqm | Regulator-disclosed project-level carpet area, not vision-derived room sums. |
| Registered land area | 12,436 sqm | The land area attached to this K-RERA registration. |
| Sanctioned FAR/FSI | 0.123 | Higher FAR generally means a denser vertical build, subject to site layout and open-space design. |
| Registered towers/wings | 1 | Official tower/wing count in the K-RERA detail page. |
| Parking disclosed | 340 total (26 open) — 1.38 spaces/unit | Confirm whether your quoted unit includes an allotted parking space and where it sits. |
| Project start date | 18-09-2015 |
K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.
Registered inventory mix
| Type | Units | Share | Official carpet area |
|---|---|---|---|
| Inventory details included in Project specification details | 246 | 100% | 25,931 sqm |
Registered tower / wing summary
| Tower/wing | Floors | Units | Parking | Height |
|---|---|---|---|---|
| Magnolia | 32 | 246 | 340 | - |
K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 246 official flat/unit rows, matching the 246 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.
By unit type
| Unit type | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| 3BHK | 182 | 104.9-117.5 sqm | 48.4-57.5 sqm | 254 |
| 2BHK | 58 | 82.7-83.8 sqm | 38.9 sqm | 80 |
| 4BHK | 6 | 188.0-217.3 sqm | 85.6-103.3 sqm | 6 |
By tower / wing
| Tower/wing | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| Magnolia | 246 | 82.7-217.3 sqm | 38.9-103.3 sqm | 340 |
| Unit | Tower | Floor | Type | Carpet | UDS | Parking |
|---|---|---|---|---|---|---|
| 1 | Magnolia | 0 | 3BHK | 104.9 sqm | 50.8 sqm | 2 |
| 2 | Magnolia | 0 | 3BHK | 117.1 sqm | 57.2 sqm | 2 |
| 3 | Magnolia | 0 | 3BHK | 104.9 sqm | 50.6 sqm | 2 |
| 4 | Magnolia | 0 | 3BHK | 117.1 sqm | 57.5 sqm | 2 |
| 5 | Magnolia | 0 | 3BHK | 105.5 sqm | 50.6 sqm | 2 |
| 6 | Magnolia | 0 | 2BHK | 82.7 sqm | 38.9 sqm | 2 |
What the numbers tell you
Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.
🔒 Unit-by-unit guidance · Unit Guidance report
Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.
🔒 Full records — land title, amenities paperwork & document catalog · Compliance report
The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.
No litigation declared on this project's K-RERA filing.
1 of 27 compliance document slots are filed as Not Applicable; the remaining 26 slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
⚠ Registration validity has lapsed: originally due 30 Apr 2022, extended (Extension) to 31 Jan 2025 — both dates have passed with no OC on file. The extension on file was granted on 12 Jan 2023 (K-RERA extension no. EX/PRM/KA/RERA/1251/310/PR/230112/002637) — it has been used, its deadline has also passed, and no further extension is recorded.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
K-RERA enforcement record (the regulator's own defaulter list & penalty orders)
⚠ Listed on K-RERA's official DEFAULTER list.
1 K-RERA order on this project (PROJECT EXTENSION) — read the order copies on the K-RERA portal.
K-RERA complaint orders (77 complaints against a project of this name on K-RERA's orders register)
| Parties | Relief sought | Disposal | Order date |
|---|---|---|---|
| Sreenivas TR vs Park West Mangnaolia Tower-6 | Interest at 21% pa from Apr 22. | AUTHORITY | 23/02/2026 |
| M Suresh Jangid vs M/s Relationship Properties Private Limited & 3 others | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 22/02/2024 |
| Prakash Sethu vs Relationship Properties Private Limited | full refund + interest of the monies paid by my towards the apartment | AUTHORITY | 21/12/2022 |
| SULEKHA vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | No extension from RERA. Interest to be paid at 18% pa from May 2022. No new launches to be allowed to the Builder. | AUTHORITY | 16/03/2024 |
| AMIT KUMAR vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Intentionally not giving credit note on 26 th slab..full credit note should be given on 26 th slab and complete refund of amount with interest due to delay in project | AUTHORITY | 16/03/2024 |
| RAJENDRA KOTHARI vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 13/11/2023 |
| RAHUL BIHANI, KHUSHBU JHAWAR vs RELATIONSHIP PROPERTIES PRIVATE LIMITED & OTERS | No further extension from RERA. Interest to be paid at 18% pa from May 2022. No new launches to be allowed to Builder | AUTHORITY | 12/09/2023 |
| B.S. SRINIVAS ^ REKHA H.R. vs RELATIONSHIP PROPERTIES PRIVATE LIMITED & OTHERS | Projection to be completed at the earliest & compensation for the delay to be paid in time. | AUTHORITY | 12/09/2023 |
| SANGEETHA vs Parkwest Mongolia | 1.Request for revoking the termination of flat allotment 2.To make delayed interest payment.3. To Deliver the flat3006 MAGNOLIA . | AUTHORITY | 11/08/2025 |
| Supriya Suraj Shanbhag vs Relationship Properties Private Limited | Need interest on delay period at 21% pa from Mar 2023 | AUTHORITY | 09/12/2025 |
| G KRISHNA MURTHY vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Direct the Respondent to complete the project on or before 31.12.2023 and pay interest at 18% per annum against the amount paid as stated in the Facts of the Complaint. | AUTHORITY | 09/12/2023 |
| LEENA JAIN & SUSHEELA DEVI vs M/S RELATIONSHIP PROPERTIES PRIVATE LIMITED & OTHERS | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 09/11/2023 |
| VALARAM S PANCHAL vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Compensation for delayed flat no Mg 2703 | AUTHORITY | 09/09/2023 |
| BABULAL K JAIN vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | No extension from RERA. Interest to be paid at 18% pa from May 2022. No new launches to be allowed to the Builder. Allow exit without charges & interest relief of 18% pa post Jul 2023 | AUTHORITY | 08/07/2023 |
| CHETHAN H vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Monthly compensation with 12% per annum interest for the delayed period. Allow exit with complete refund & interest of 12% pa after Jul2023 or incr interest rates of 2% every quarter after Jul2023 | AUTHORITY | 08/07/2023 |
| JITESH HEMRAJ PUROHIT vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | No extension from RERA. Interest to be paid at 18% pa from May 2022. No new launches to be allowed to the Builder. Allow exit without charges & interest relief of 18% pa post Jul 2023 | AUTHORITY | 08/07/2023 |
| INDRABAI SONIGARA vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | No extension from RERA. Interest to be paid at 18% pa from May 2022. No new launches to be allowed to the Builder. | AUTHORITY | 08/07/2023 |
| KUPARAM PARMAR vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| K B SUNIL KUMAR vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | NO MORE EXTENSION FROM RERA. INTEREST OF UPTO 18% PLUS THE BENEFIT AS PER INCOME TAX HOSUING RELEIF. NO NEW PROJECT LAUNCHES. PRIORITY TO BE GIVEN TO MAGNOLIA PROJECT.INVOLVEMENT OF AKHIL GUPTA(MD) | AUTHORITY | 08/07/2023 |
| KUNAL M JAIN vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| NARENDRA KUMAR CHORADIA vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| NIKHIL JAIN vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| RAHUL MATMARI vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| ANUPSURYA vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| PRAVEEN KUMAR vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| PRAVEEN KUMAR vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| VIVEK P JAIN vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| PRATIK BENGANI vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| JABRA RAM POSARAM GEHLOL vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| RISHAB BENGANI vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. | AUTHORITY | 08/07/2023 |
| HEMANT BENGANI vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| VANDANA KUMARI M vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| USHA KUMARI M vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| GHEVARCHAND S GURLIA vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| ANAND G GURLIA vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| KRISHNA MOHAN vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| SANTOSH KUMAR vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| VIKAS CHOPRA vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| ANITHA DEVI vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| SHASHI KUMAR P V vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| SURESH KUMAR vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| BALAJI SATHYANARAYANAN vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| KAMALESH KUMAR B vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| SANTHOSH SRIKANT vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| RAHUL JAIN vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| PRASHANTHA GANIGA vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| PRIYA RAGHAVENDRA vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. | AUTHORITY | 08/07/2023 |
| ARCHANA S MALLYA vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| JAYCHAND K JAIN vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| VIKRAM MEHTA vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| KANCHAN DEVI CHAJER vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| CHANDRAKALA SARDA vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| GOUTAM K JAIN vs PARKWEST - MAGNOLIA - TOWER 6 | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| GOUTAM K JAIN vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| KAILASH KUMAR CHOUDHARY vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| VIJAY RAJ vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| JEETENDER CHHAJED vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| JEETENDER CHHAJED vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| CHETAN KUMAR vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| KANTILAL CHHAJER vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| PRAKASH KUMAR vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| MITESH KUMAR vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | No extension from RERA. Interest to be paid at 18% PA from May 2022. No new launches to be allowed to the builder. | AUTHORITY | 08/07/2023 |
| NISHANT K JAIN vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| NILESH KUMAR vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| MANOJ KUMAR vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| VIKRAM KUMAR vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| PRATIK JAIN vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| KRISHNA KUMAR PUROHIT vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Compensation for delay of Our Flat MANGOLIA MG2402 | AUTHORITY | 08/07/2023 |
| AMIT KUMAR JAIN vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| DHANANJAY P KADAM vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| NARESH JAIN vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| RAVI KUMAR GHANCHI vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | Interest at 18% pa from May 22. No new tower launch allowed without completing the current project. | AUTHORITY | 08/07/2023 |
| PRAKASH SETHU, SAHANA P. vs RELATIONSHIP PROPERTIES PVT LTD., | Request RERA to immediately review the project status please. I fear if the situation is unchecked, this will result in a massive default in project delivery causing hardships to hundreds of families. | AUTHORITY | 06/09/2023 |
| SAHANA P, & PRAKASH SETHU vs RELATIONSHIP PROPERTIES PRIVATE LIMITED | We as home buyers are not part of any agreement to exit ETA group and given an NOC was not sought by developer from us, we seek complete refund of our payments along with interest accrued | AUTHORITY | 06/09/2023 |
| Yogita Yogesh Thakur vs Relationship Properties Private Limited | Compensation, interest for delay and payment of my Rent | AUTHORITY | 04/06/2026 |
| GAURAV BHANSALI vs PARKWEST MAGNOLIA TOWER-6 | Monthly compensation with 18% per annum interest for the delayed period. Allow exit with complete refund & interest of 18% pa after Jul2023 or incr interest rates of 2% every quarter after Jul2023. | AUTHORITY | 02/11/2023 |
| GAURAV BHANSALI vs PARK WEST MAGNOLIA TOWER-6 | Interest at 18% pa from May 22. Rent at market rates from May 22. Exit from May 22 with int at 18% pa from date of payments made. No new tower launch allowed without completing the current project. | AUTHORITY | 02/11/2023 |
⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.
Complaints on this project's K-RERA page (312 complaints listed against this promoter)
| Complaint | Subject (as filed) | Project | Status |
|---|---|---|---|
| CMP/220309/0009098 09-03-2022 | Return of amount andcompensation in full | Parkwest - Maple - Tower 4 (another project by this promoter) | DISPOSED AO |
| CMP/220310/0009104 10-03-2022 | Unreasonable delay in the delivery of the project | Parkwest - Maple - Tower 4 (another project by this promoter) | DISPOSED AO |
| CMP/221107/0010187 07-11-2022 | Delay in handing over of property and seeking compensation for delay in handover of Property | Parkwest - Maple - Tower 4 (another project by this promoter) | DISPOSED AO |
| CMP/221125/0010401 25-11-2022 | monthly rental | Parkwest - Maple - Tower 4 (another project by this promoter) | DISPOSED AO |
| CMP/190311/0002417 11-03-2019 | Refund of Booking amount with GST along with interest and compensation, For revokation of RERA registration granted to the promoter | Parkwest - Sapphire- Tower 5 (another project by this promoter) | DISPOSED AUTHORITY |
| CMP/190311/0002422 11-03-2019 | Refund of booking amount and GST amount paid, along with interest and compensation, to revoke the registration granted by RERA | Parkwest - Sapphire- Tower 5 (another project by this promoter) | DISPOSED AUTHORITY |
| CMP/201009/0006794 09-10-2020 | Delay in Project Delivery as promised in Advertisement and Agrement | Parkwest - Maple - Tower 4 (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/201010/0006804 10-10-2020 | Delay in apartment unit and amenities handover as committed in the Agreemetn | Parkwest - Maple - Tower 4 (another project by this promoter) | DISPOSED AUTHORITY BENCH4 |
Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.
K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.
| Role | Name | Registration / licence | Since | Locality |
|---|---|---|---|---|
| Architect | Lalit Narula | - | 1978 | Ashok Nagar, Bengaluru |
| Contractor | Shapoorji Pallonji And Company Private Limited | - | 1943 | Kaveri Nagar, Murgesh Pallya |
| Structural engineer | Designtree Service Consultants Private Limited | - | - | - |
Relationship Properties has 10 other K-RERA-registered projects in our records (average reported construction progress 64%). 8 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.
Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.
⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.
Declared construction cost ÷ registered units averages to ₹69.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.
RERA 70% project account is on file: HDFC Fort Branch (IFSC HDFC0000060, a/c …7188). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
K-RERA has 1 project-photo upload.
These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit.
The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| MG Road / city centre | 5 km |
| Outer Ring Road / Manyata | 11 km |
| Bellandur–Marathahalli belt | 14 km |
| Electronic City | 17 km |
| Whitefield IT hub | 21 km |
| Kempegowda Int'l Airport | 30 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
Should you buy in Parkwest - Magnolia - Tower 6?
This page is the free K-RERA filing summary. The full RERA Property Intelligence Report gives you buyer-complaint history, regulatory flags, builder track record, the official unit register, land title, NOCs, and (where the sanctioned plans support it) room-by-room unit data and an annotated site plan. See a real one first:
Sample: Sobha Silicon Oasis → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Built by Relationship Properties.
Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.