Bangalore/Project record

K-RERA · the public record

Parkwest - Oak - Tower 10

Bengaluru South · Relationship Properties

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

74%construction reportedQ1 2026 filing
0units not bookedof 222 · Q1 2026 filing
30 Jun 2025declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

30 Jun 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3 BHK (S) Typ 03a
1

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

2.6registered acres

86.6registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/210216/003900

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 June 2025
Land area10,376 sq m (2.6 acres)
Homes registered222
Tower/wing entries1
Unit mix1 × 3 BHK (S) Typ 03a

In context

Density86.6 homes per acre
Density in context66th percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units222Total inventory registered with K-RERA.
Official carpet area110 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area10,376 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI~3.02Sanctioned floor-area ratio (≈31,307 sqm sanctioned FAR area ÷ 10,376 sqm land) — higher means a denser vertical build.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)285Separate filed counts; these categories may overlap and are not added together.
Open-parking field21Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date01-02-2021

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK (S) Typ 03a1100%110 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Oak - Tower 1032222285-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 222 official flat/unit rows, matching the 222 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK123108.2-110.1 sqm54.4-58.8 sqm186
1BHK3343.2-69.9 sqm21.4-36.8 sqm33
2.5 BHK3388.6 sqm44.9-47.1 sqm33
2BHK3369.9-108.5 sqm36.8-54.4 sqm33

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Oak - Tower 1022243.2-110.1 sqm21.4-58.8 sqm285
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
001Oak - Tower 1002.5 BHK88.6 sqm44.9 sqm1
002Oak - Tower 1001BHK43.2 sqm21.4 sqm1
003Oak - Tower 1002BHK69.9 sqm36.8 sqm1
101Oak - Tower 1012.5 BHK88.6 sqm44.9 sqm1
102Oak - Tower 1011BHK43.2 sqm21.4 sqm1
103Oak - Tower 1012BHK69.9 sqm36.8 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

12 of 41 compliance document slots are filed as Not Applicable; the remaining 29 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Jun 2025, extended (Section 6 Extension) to 30 Jun 2026 — both dates have passed with no OC on file. The extension on file was granted on 04 Jul 2025 (K-RERA extension no. EX/PRM/KA/RERA/1251/310/PR/250704/003900) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Sudipta Dey vs Park West OakWe respectfully pray for a direction to the Respondents to pay interest for the delay in possession and to provide a firm timeline for completion and handover of the flat, along with any other reliefsAUTHORITY17/12/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (312 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190311/0002417
11-03-2019
Refund of Booking amount with GST along with interest and compensation, For revokation of RERA registration granted to the promoterParkwest - Sapphire- Tower 5 (another project by this promoter)DISPOSED AUTHORITY
CMP/190311/0002422
11-03-2019
Refund of booking amount and GST amount paid, along with interest and compensation, to revoke the registration granted by RERAParkwest - Sapphire- Tower 5 (another project by this promoter)DISPOSED AUTHORITY
CMP/201009/0006794
09-10-2020
Delay in Project Delivery as promised in Advertisement and AgrementParkwest - Maple - Tower 4 (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/201010/0006804
10-10-2020
Delay in apartment unit and amenities handover as committed in the AgreemetnParkwest - Maple - Tower 4 (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/201010/0006812
10-10-2020
Delay in Project Delivery as promised in Advertisement and AgrementParkwest - Maple - Tower 4 (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/201011/0006814
11-10-2020
POSSESSION PENDINGParkwest - Maple - Tower 4 (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/201107/0007032
07-11-2020
No construction activity/No concrete response from BuilderParkwest - Sapphire- Tower 5 (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/201127/0007136
27-11-2020
Breach of Agreement and non response to previous complaintParkwest - Sapphire- Tower 5 (another project by this promoter)DISPOSED AUTHORITY BENCH5

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectRSP Design Consultants India Private Limited-1978Ashok Nagar, Bengaluru
ContractorShapoorji Pallonji And Company Private Limited-1943Kaveri Nagar, Murgesh Pallya
Structural engineerDesigntree Service Consultants Private Limited---

Builder track record

RERA filing

Relationship Properties has 10 other K-RERA-registered projects in our records (average reported construction progress 62%). 8 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹3.41 Cr collected from buyers, ₹3.60 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹3.60 Cr) exceeded buyer collections (₹3.41 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress66% → 74% (+8 pts)
Units sold/booked as registered222/222 (100%)
Buyer collections in available QPRs₹10.53 Cr
Escrow withdrawals in available QPRs₹72.95 Cr (6.93x collections)
  • 100% of registered units are shown as sold/booked, but no completion certificate is on file yet.
  • Construction progress moved from 66% to 74% across the filed QPR window.
  • The filed unit sales count did not move across the available QPR window because the project was already effectively sold out.
  • Across available QPR rows, escrow withdrawals are 6.93x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹70.0 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Rajajinagar, Dr. Rajkumar road (IFSC HDFC0004000, a/c …9375). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
MG Road / city centre5 km
Outer Ring Road / Manyata11 km
Bellandur–Marathahalli belt14 km
Electronic City17 km
Whitefield IT hub21 km
Kempegowda Int'l Airport30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Relationship Properties.
Relationship Properties has 11 projects registered in Bangalore, 2 past RERA deadline.
1 complaints on the K-RERA register against Relationship Properties in Bangalore.

Other projects by this builder in Bangalore

Parkwest - Pine - Tower 9
Past deadline · 86% built · 100% sold
Parkwest - Cedar - Tower 8
Due soon · 75% built · 100% sold
Parkwest - Emerald - Tower 2
No filings
Parkwest - Magnolia - Tower 6
No filings
Parkwest - Mahogany - Tower 7
No filings
Parkwest - Maple - Tower 4
No filings

Other RERA-registered projects in Binnipete

Major developers building in Binnipete

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Parkwest - Oak - Tower 10?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026