Parkwest - Sequoia - Tower 11
Bengaluru South · Relationship Properties
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Promoter-reported construction
K-RERA quarterly filings · Q3 2025 to Q1 2026
declared completion
27 Feb 2029
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
K-RERA registration · read 20 Sep 2026
Inventory & scale
What this registration contains.
Filed categories, unchanged · K-RERA registration · read 20 Sep 2026
The whole registration
2.8registered acres
65.1registered units per acre
The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.
From another project · Prestige Park Grove
A larger advertised area. Almost the same carpet area.
In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.
This illustrates the report format. These findings concern the named sample, not this project.
Read the sample report ↗
The source record
The details behind the headline.
K-RERA · PRM/KA/RERA/1251/310/PR/220124/006569
This project, on the record
The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.
On the register
In context
Values as crawled from the official K-RERA record; context percentiles name their comparison population.
Official Registry Facts
Official project scale
RERA filingRegistration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Registered units | 182 | Total inventory registered with K-RERA. |
| Official carpet area | 23,286 sqm | Regulator-disclosed project-level carpet area, not vision-derived room sums. |
| Official built-up area | 42,086 sqm | Useful scale context when comparing density and project cost. |
| Registered land area | 11,320 sqm | The land area attached to this K-RERA registration. |
| Sanctioned FAR/FSI | ~3.12 | Sanctioned floor-area ratio (≈35,350 sqm sanctioned FAR area ÷ 11,320 sqm land) — higher means a denser vertical build. |
| Registered tower/wing entries | 1 | Official tower/wing count in the K-RERA detail page. |
| Parking total (reconciled) | 201 | Separate filed counts; these categories may overlap and are not added together. |
| Covered-parking field | 182 | Separate filed counts; these categories may overlap and are not added together. |
| Open-parking field | 19 | Separate filed counts; these categories may overlap and are not added together. |
| Garage field | 0 | Separate filed counts; these categories may overlap and are not added together. |
| Approved plan number | PRJ/0810/23-24 | Use this to match the sanctioned drawing set shown by the builder. |
| Plan approval date | 04-01-2024 | |
| Project start date | 01-04-2024 |
Official inventory & towers
RERA filingK-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.
Registered inventory mix
| Type | Units | Share | Official carpet area |
|---|---|---|---|
| 4 BHK | 54 | 30% | 8,268 sqm |
| 3 BHK | 128 | 70% | 15,018 sqm |
Registered tower / wing summary
| Tower/wing | Floors | Units | Parking | Height |
|---|---|---|---|---|
| Parkwest - Sequoia - Tower 11 | 30 | 182 | 201 | 101.2 m |
Official unit register
RERA filingK-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 182 official flat/unit rows, matching the 182 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.
By unit type
| Unit type | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| 3 BHK | 128 | 115.8-130.4 sqm | 55.5-63.1 sqm | 128 |
| 4 BHK | 54 | 152.8-153.4 sqm | 70.6-76.4 sqm | 54 |
By tower / wing
| Tower/wing | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| Parkwest - Sequoia - Tower 11 | 182 | 115.8-153.4 sqm | 55.5-76.4 sqm | 182 |
Show sample official unit rows
| Unit | Tower | Floor | Type | Carpet | UDS | Parking |
|---|---|---|---|---|---|---|
| 001 | Parkwest - Sequoia - Tower 11 | 0 | 3 BHK | 116.1 sqm | 55.5 sqm | 1 |
| 002 | Parkwest - Sequoia - Tower 11 | 0 | 3 BHK | 118.2 sqm | 57.4 sqm | 1 |
| 003 | Parkwest - Sequoia - Tower 11 | 0 | 3 BHK | 118.0 sqm | 56.5 sqm | 1 |
| 004 | Parkwest - Sequoia - Tower 11 | 0 | 3 BHK | 115.8 sqm | 55.6 sqm | 1 |
| 101 | Parkwest - Sequoia - Tower 11 | 1 | 3 BHK | 116.1 sqm | 55.5 sqm | 1 |
| 102 | Parkwest - Sequoia - Tower 11 | 1 | 3 BHK | 118.2 sqm | 57.4 sqm | 1 |
Legal, Approvals & Project Team
Litigation & compliance
RERA filingNo litigation declared on this project's K-RERA filing.
⚠ 3 of 35 compliance document slots are filed as under process / not yet usable: Urban Land Ceiling, District Magistrate, Proforma For Sale Deed.
2 additional compliance slots are filed as Not Applicable.
No completion certificate (OC) on file yet — project has not been declared complete.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
Complaints on this project's K-RERA page (312 complaints listed against this promoter)
| Complaint | Subject (as filed) | Project | Status |
|---|---|---|---|
| CMP/190311/0002417 11-03-2019 | Refund of Booking amount with GST along with interest and compensation, For revokation of RERA registration granted to the promoter | Parkwest - Sapphire- Tower 5 (another project by this promoter) | DISPOSED AUTHORITY |
| CMP/190311/0002422 11-03-2019 | Refund of booking amount and GST amount paid, along with interest and compensation, to revoke the registration granted by RERA | Parkwest - Sapphire- Tower 5 (another project by this promoter) | DISPOSED AUTHORITY |
| CMP/201009/0006794 09-10-2020 | Delay in Project Delivery as promised in Advertisement and Agrement | Parkwest - Maple - Tower 4 (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/201010/0006804 10-10-2020 | Delay in apartment unit and amenities handover as committed in the Agreemetn | Parkwest - Maple - Tower 4 (another project by this promoter) | DISPOSED AUTHORITY BENCH4 |
| CMP/201010/0006812 10-10-2020 | Delay in Project Delivery as promised in Advertisement and Agrement | Parkwest - Maple - Tower 4 (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/201011/0006814 11-10-2020 | POSSESSION PENDING | Parkwest - Maple - Tower 4 (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/201107/0007032 07-11-2020 | No construction activity/No concrete response from Builder | Parkwest - Sapphire- Tower 5 (another project by this promoter) | DISPOSED AUTHORITY BENCH5 |
| CMP/201127/0007136 27-11-2020 | Breach of Agreement and non response to previous complaint | Parkwest - Sapphire- Tower 5 (another project by this promoter) | DISPOSED AUTHORITY BENCH5 |
Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.
Statutory approval status
RERA filing10 further authority slots are marked not applicable by the regulator.
| Authority / NOC | Status | Date | File |
|---|
Project team & certifications
RERA filingK-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.
| Role | Name | Registration / licence | Since | Locality |
|---|---|---|---|---|
| Chartered accountant | Bhavesh R Nagda | 127270 | 0000 | Mumbai City, Maharashtra - 400080 |
| Engineer | SANJIV VASUDEO AUNDHE | BCCL/BL-3.6/A- 0020/21-22 | 2019 | Bengaluru Urban, Karnataka - 560038 |
| Architect | PAUL RAVI JOHN | CA/97 /21547 | 1997 | Bengaluru Urban, Karnataka - 560020 |
| Contractor | Shapoorji Pallonji And Company Private Limited | - | 1943 | Bengaluru Urban, Karnataka - 560017 |
Builder track record
RERA filingRelationship Properties has 10 other K-RERA-registered projects in our records (average reported construction progress 78%). 9 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a higher delayed rate than the K-RERA average across Bengaluru on the same measure.
Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.
Financials & Construction Progress
Financial disclosures
RERA filingLatest quarterly filing (2026-Q1): ₹27.82 Cr collected from buyers, ₹17.46 Cr withdrawn from the project's escrow account.
| Construction progress | 16% → 26% (+10 pts) |
| Units sold/booked as registered | 175/182 (96%) |
| Buyer collections in available QPRs | ₹68.75 Cr |
| Escrow withdrawals in available QPRs | ₹73.83 Cr (1.07x collections) |
- 96% of registered units are shown as sold/booked, but no completion certificate is on file yet.
- Construction progress moved from 16% to 26% across the filed QPR window.
- Across available QPR rows, escrow withdrawals are 1.07x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.
QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.
Declared construction cost ÷ registered units averages to ₹87.3 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.
RERA 70% project account is on file: HDFC World Trade Centre, Bengaluru IFSC Code : HDFC0002710 Pin Code : 560055. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
Location & Connectivity
The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| MG Road / city centre | 5 km |
| Outer Ring Road / Manyata | 11 km |
| Bellandur–Marathahalli belt | 14 km |
| Electronic City | 17 km |
| Whitefield IT hub | 21 km |
| Kempegowda Int'l Airport | 31 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.