31 Aug 2018declared completionK-RERA registration · read 20 Sep 2026
567registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Aug 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

APARTMENT
567

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

7.2registered acres

78.9registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/171014/000248

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 August 2018
Land area29,085 sq m (7.2 acres)
Homes registered567
Tower/wing entries5
Unit mix567 × APARTMENT

In context

Density78.9 homes per acre
Density in context53rd percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units567Total inventory registered with K-RERA.
Official carpet area61,114 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area29,085 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3.164Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries5Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)735Separate filed counts; these categories may overlap and are not added together.
Open-parking field30Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date10-12-2014

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
APARTMENT567100%61,114 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower 12781157-
Tower 221118141-
Tower 321122150-
Tower 421124144-
Tower 521122143-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 567 official flat/unit rows, matching the 567 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK19782.0-117.0 sqm35.4-49.5 sqm197
2BHK16581.0-82.0 sqm34.8-35.4 sqm165
2.5BHK12088.0-90.0 sqm37.8-38.4 sqm120
4BHK81160.0-174.0 sqm71.4-76.2 sqm81
Pent House4232.0-241.0 sqm100.5-111.0 sqm8

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower 412481.0-117.0 sqm34.8-49.5 sqm124
Tower 312282.0-117.0 sqm35.1-49.5 sqm122
Tower 512282.0-232.0 sqm35.1-100.5 sqm124
Tower 211881.0-241.0 sqm34.8-111.0 sqm120
Tower 181160.0-174.0 sqm71.4-76.2 sqm81
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1011Tower 104BHK174.0 sqm76.2 sqm1
1012Tower 104BHK169.0 sqm71.7 sqm1
1021Tower 114BHK174.0 sqm76.2 sqm1
1022Tower 114BHK169.0 sqm71.7 sqm1
1031Tower 124BHK174.0 sqm76.2 sqm1
1032Tower 124BHK169.0 sqm71.7 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 23 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Aug 2018 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (6 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
MS LEELAVATHI & ANOTHER vs M/S.PRESTIGE ESTATES PROJECTS LTDCompensation for delay in project handover and as they mentioned in construction agreement to pay 9% per annum for the amounts paidAUTHORITY29/11/2024
KRISHNADAS SRINIVASA vs PRESTIGE ESTATES PROJECTS LIMITEDPlease help to get compensation of Rs 4.97 lakhs prestige promised me to pay as compensationAUTHORITY13/09/2022
MS Apex E Learning Technologies Ltd vs PRESTIGE ESTATES PROJECTS LIMITEDi) To duly register the booked apartments in complainant favour and hand over the vacant possession of the apartments to the complainant. OR ii) To return entire amount of 31,59,968/- (Rupees ThirtyAUTHORITY12/02/2024
Shanker Kopparam Govindraj vs M/s Prestige Estates Projects LimitedCompensation of interest for delayed project delivery and distress caused for poor engineering construction qualityAUTHORITY10/07/2023
ARUNA JAIN vs M/S PRESTIGE ESTATES PROJECTS LIMITEDI WANT THEM TO PAY INTEREST ON THE AMOUNT PAID BY ME ON THE DELAYED TIME.AUTHORITY10/07/2023
G Chandra Shekhar vs M/s Prestige Estates Projects LimitedHelp with fixing irregularities with master bathroom , bedroom , living room and entrance of home and to ensure builder adheres to promised deliveryAUTHORITY01/08/2023

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (61 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190225/0002242
25-02-2019
Builder not paying compensation as per agreement and no handover of apartment after deadlinePRESTIGE WESTWOODSDISPOSED AO
CMP/190325/0002508
25-03-2019
Delayed Interest for delayed handoverPrestige Royale Gardens Phase-I (another project by this promoter)DISPOSED AO
CMP/190330/0002539
30-03-2019
Delay in delivery of ProjectPrestige Royale Gardens Phase-I (another project by this promoter)DISPOSED AO
CMP/190419/0002630
19-04-2019
This is to request to adjust against balance or reimburse the amount as per delay clause @ 9% till date on the amount paid. Also to adhere to agreement for handover of flat no 14011 in tower 14Prestige Royale Gardens Phase-I (another project by this promoter)DISPOSED AO
CMP/190519/0003075
19-05-2019
Prestiege Royale Gardens T2147 Apartmen Dealy in possession, compensation not being pais as per agreementPrestige Royale Gardens Phase-I (another project by this promoter)DISPOSED AO
CMP/190519/0003091
19-05-2019
Undue delay of project completion and Monetary compensation towards that per Construction agreementPrestige Royale Gardens Phase-I (another project by this promoter)DISPOSED AO
CMP/190520/0003069
20-05-2019
There is no OC 2 yrs after promised data of delivery. There is misrepresentation of the tower number scheduled apartment comparing brochure and sanctioned plan.PRESTIGE ROYALE GARDENS PHASE 2 (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/190614/0003288
14-06-2019
Delay in delivery and compensation not paidPRESTIGE ROYALE GARDENS PHASE 2 (another project by this promoter)DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectABHAY ITTY ZACHARIAH-2016OFF BRUNTON ROAD, BANGALORE
ContractorALFARA INFRA PROJECTS PRIVATE LIMITED-2011EJIPURA, BANGALORE
Structural engineerG.H.BASAVARAJ---

Builder track record

RERA filing

Prestige has 81 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Prestige Estates”) (average reported construction progress 64%). 52 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹53.9 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: KOTAK MAHINDRA BANK LAVELLE ROAD, BANGALORE (IFSC KKBK0000422, a/c …6314). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
MG Road / city centre5 km
Outer Ring Road / Manyata10 km
Bellandur–Marathahalli belt14 km
Electronic City18 km
Whitefield IT hub20 km
Kempegowda Int'l Airport29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Prestige Estates. View Prestige Estates's full track record →
Prestige Estates has 46 projects registered in Bangalore, 2 completed, 1 past RERA deadline.

Other projects by this builder in Bangalore

Prestige Elm Park
Past deadline · 88% built · 72% sold
Prestige Gardenia Estate
Filing overdue · 59% built
Prestige Green Gables
Filing overdue · 100% built · 100% sold
Evergreen @ Prestige Raintree Park
On track · 24% built · 59% sold
Prestige Bagamane Temple Bells
No filings

Other RERA-registered projects in Binnipete

Major developers building in Binnipete

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Prestige Westwoods?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026