Purva Westend

Bengaluru South · Purva Star Properties

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2018declared completionK-RERA registration · read 20 Sep 2026
795registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

7.9registered acres

101.0registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/170915/000236

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2018
Land area31,849 sq m (7.9 acres)
Homes registered795
Tower/wing entries5

In context

Density101 homes per acre
Density in context82nd percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units795Total inventory registered with K-RERA.
Official carpet area10 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area31,849 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries5Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)795Separate filed counts; these categories may overlap and are not added together.
Open-parking field90Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date23-04-2015

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Block 1 Wing A19159159-
Block 1 Wing B19159159-
Block 1 Wing C19159159-
Block 2 Wing D19159159-
Block 2 Wing E19159159-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 815 official flat/unit rows vs 795 registered units disclosed above; ask why the row count differs. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK49674.0-114.7 sqm0.0 sqm496
2BHK23974.0-95.0 sqm0.0 sqm239
1BHK8010.3 sqm0.0 sqm80

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Block 2 Wing E17910.3-109.6 sqm0.0 sqm179
Block 1 Wing A15974.8-107.7 sqm0.0 sqm159
Block 1 Wing B15974.8-107.7 sqm0.0 sqm159
Block 1 Wing C15974.8-107.7 sqm0.0 sqm159
Block 2 Wing D15974.0-114.7 sqm0.0 sqm159
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
PWE-001Block 1 Wing A03BHK107.7 sqm0.0 sqm1
PWE-002Block 1 Wing A03BHK95.0 sqm0.0 sqm1
PWE-003Block 1 Wing A03BHK95.0 sqm0.0 sqm1
PWE-004Block 1 Wing A02BHK74.8 sqm0.0 sqm1
PWE-006Block 1 Wing A03BHK95.0 sqm0.0 sqm1
PWE-007Block 1 Wing A02BHK82.9 sqm0.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 20 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2018 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (20 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Supratik Gon vs M/S.PURVA STAR PROPERTIES LTD.Compensation as per RERA actAUTHORITY29/07/2025
VINAY SAGAR UDAGI vs PURVA WESTEND?1,519,150.81 in Delay Compensation and Compensation for giving 50 Sq.Ft. lessAUTHORITY09/09/2024
NIRANJAN GOYAL vs PURVA STAR PROPERTIES LTD,Respondent to pay delay compensation of approx. 14 months from 01.01.19 to 17.02.20; litigation expenses, interest and penaltyAUTHORITY08/01/2024
PRADEEP KUMAR KOTHA vs PURVA STAR PROPERTIES PVT. LTD.Compensation as per RERA ActAUTHORITY07/11/2022
MANISH RAJ KUMAR vs PURVA WESTEND?1,428,567.44 in Delay Compensation and Compensation for giving 50 Sq.Ft. less.AUTHORITY04/12/2023
V LAKSHMINARAYAN vs PURVA STAR PROPERTIES LTD?887,730.39 in Delay Compensation and Compensation for giving 50 Sq.Ft. lessAUTHORITY04/12/2023
MADHAN ANNAMALAI vs PURVA STAR PROPERTIES LTD?1,499,784.25 in Delay Compensation and Compensation for giving 50 Sq.Ft. lessAUTHORITY04/12/2023
MAHESH PARSRI vs PURVA STAR PROPERTIES LTD?1,928,261.70 in Delay Compensation and Compensation for giving 50 Sq.Ft. lessAUTHORITY04/12/2023
PERUMALLA VENKATA RAGHAVENDRA RAO vs PURVA WESTED?1,873,185.51 in Delay Compensation and Compensation for giving 50 Sq.Ft. lessAUTHORITY04/12/2023
SAIRAM PATRO vs PURVA STAR PROPERTIES LTD?134,944.96/ ?0.00 in Delay Compensation and Compensation for giving 50 Sq.Ft. lessAUTHORITY04/12/2023
SAIRAM PATRO vs PURVA WESTEND?1,632,131.11/ ?0.00 in Delay Compensation and Compensation for giving 50 Sq.Ft. lessAUTHORITY04/12/2023
SANDEEP PRABHU vs PURVA STAR PROPERTIES LTD?1,489,071.66 in Delay Compensation and Compensation for giving 50 Sq.Ft. lessAUTHORITY04/12/2023
SEELU CHACKO vs PURVA STAR PROPERTIES LTD?1,899,625.00 in Delay Compensation and Compensation for giving 50 Sq.Ft. lessAUTHORITY04/12/2023
ULLAS THARAKAN vs PURVA WESTEND?1,701,521.25 in Delay Compensation and Compensation for giving 50 Sq.Ft. lessAUTHORITY04/12/2023
VENU GOPALA KRISHNAN vs PURVA WESTEND?983,871.00/ ?0.00 in Delay Compensation and Compensation for giving 50 Sq.Ft. lessAUTHORITY04/12/2023
VENKATESH NADHAN vs PURVA WESTED?870,838.50 in Delay Compensation and Compensation for giving 50 Sq.Ft. lessAUTHORITY04/12/2023
ANANTH RAJENDRAN vs PURVA STAR PROPERTIES LTD?1,487,606.35 in Delay Compensation and Compensation for giving 50 Sq.Ft. lessAUTHORITY04/12/2023
VAGISH KALLIGUDD vs PURVA WESTENDPossession and delivery of flatsAUTHORITY04/11/2024
MANISH RAJ DUBEY vs PURVA WESTENDRegistration and Possession of flat along with due compensationAUTHORITY04/11/2024
Mahesh K R vs OZONE URBANA INFRA?1,499,784.25 in Delay Compensation and Compensation for giving 50 Sq.Ft. lessAUTHORITY03/04/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (47 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190209/0002082
09-02-2019
Delay in delivery of the apartmentPurva WestendDISPOSED AO
CMP/190307/0002386
07-03-2019
Delay in delivery of the apartmentPurva WestendDISPOSED AO
CMP/190309/0002399
09-03-2019
Non Adherence to Handover timeline as per AgreementPurva WestendDISPOSED AO
CMP/190309/0002402
09-03-2019
Non Adherence to Handover timeline as per AgreementPurva WestendDISPOSED AUTHORITY FULLBENCH
CMP/190311/0002401
11-03-2019
Non adherence to handover and not agreeing to pay the RERA penalty.Purva WestendDISPOSED AO
CMP/190312/0002377
12-03-2019
Delay in project delivery and not agreeing to pay RERA penalityPurva WestendDISPOSED AO
CMP/190407/0002575
07-04-2019
Delay for delivery of the project and compensation to be paid as per RERA GuidelinesPurva WestendDISPOSED AO
CMP/190411/0002614
11-04-2019
Delay in handover and compensation issuesPurva WestendDISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectThomas Associates-1999Kasturbha Road cross, Bangalore
ContractorStarworth Infrastructure & Construction Ltd-2008No 39, Ulsoor Road
Structural engineerWSP Consultants India Private Ltd---

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹38.8 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Richmond Road (IFSC HDFC0000052, a/c …9884). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Electronic City6 km
Bellandur–Marathahalli belt7 km
MG Road / city centre10 km
Whitefield IT hub15 km
Outer Ring Road / Manyata17 km
Kempegowda Int'l Airport35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Purva Star.
Purva Star has 2 projects registered in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Singasandra

Major developers building in Singasandra

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.