Reliaable Prime City PHASE 1

Anekal · RD Buildtech and Developers (Karnataka)

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2023declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

8.9registered acres

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/191220/003094

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2023
Land area36,068 sq m (8.9 acres)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered land area36,068 sqmThe land area attached to this K-RERA registration.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date15-12-2019

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 33 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2023, extended (Covid Extension) to 30 Sep 2024 — both dates have passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (4 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
PUSHPARAJ KUMAR K.A. & HARINI K.S. vs M/S RD BUILDTECH AND DEVELOPERS(KARNATAKA_ PRIVATE LIMITEDRefundAUTHORITY30/09/2023
NAVEEN KUMAR & ASHWINI KUKEHALLI SRINIVAS vs RD BUILDTECH AND DEVELOPERS (KARNATAKA) PRIVATE LIMITEDWe request RERA to direct RD Buildtech and Developers (Karnataka) Private Limited to refund our money as promised along with the interest charges for delay in payment.AUTHORITY20/03/2023
HEMASUNDAR VENIGALLA vs M/S.RD BUILDTECH & DEVELOPERSRequest RERA team look into this issue and arrange refund of 1Lac plus interest from Reliaable builderAUTHORITY14/03/2023
H. RAJKUMAR REDDY & ANOTHER vs M/S RD BUILDTECH AND DEVELOPERS (KARNATAKA) PRIVATE LIMITEDIf they failed to provide legal docs they suppose to refund full amount even they did not return single penny atlea reducing 10%. Please urging you people to get my money back with interest for2.year.AUTHORITY08/01/2024

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (10 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190518/0003078
18-05-2019
Reliaable Developers cheated usRELIAABLE DOLLAR COLLONY Phase 2B (another project by this promoter)DISPOSED AO
CMP/191025/0004564
25-10-2019
Original Suit Pending (o.s no 477/2016) in anekal Court. Writ Petition (wp 15040/2019) in the High CourtRELIAABLE DOLLAR COLLONY Phase 2B (another project by this promoter)DISPOSED AUTHORITY
CMP/201118/0007087
18-11-2020
Advance amount not refunded when I went to office behaving rudely and not ready to refund, they are not not at all professionalRELIAABLE DOLLAR COLLONY (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/210308/0007758
08-03-2021
cancellation of plot and refundReliaable Prime City PHASE 1DISPOSED AUTHORITY BENCH4
CMP/210415/0007897
15-04-2021
REFUND OF THE ENTIRE BOOKING AMOUNTReliaable Residenza Phase 1 (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/210917/0008345
17-09-2021
Denied in refunding the booking amount.Reliaable Prime City Phase 1A (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/211020/0008451
20-10-2021
Did not receive refund for Reliaable plot 196 cancellationReliaable Prime City PHASE 1DISPOSED AUTHORITY BENCH5
CMP/220302/0009060
02-03-2022
Long delay in Refund of plot booking amountReliaable Residenza Phase 1 (another project by this promoter)DISPOSED AUTHORITY BENCH5

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectMr.Vinayakaram M S-2011Museum Road, Bengaluru
ContractorM/s. PUSHPAGIRI INFRASTRUCTURE COMPANY-2008Nagarabhavi II Stage, BANGALORE - 560 072.
Structural engineerRAJESH CONSULTANTS---

Builder track record

RERA filing

Rd Buildtech has 12 other K-RERA-registered projects in our records. 12 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a higher delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: HDFC Richmond Road (IFSC HDFC0000523, a/c …0296). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Electronic City4 km
Bellandur–Marathahalli belt8 km
Whitefield IT hub14 km
MG Road / city centre16 km
Outer Ring Road / Manyata22 km
Kempegowda Int'l Airport38 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Rd Buildtech. View Rd Buildtech's full track record →
Rd Buildtech has 13 projects registered in Bangalore.
1 complaints on the K-RERA register against Rd Buildtech in Bangalore.

Other projects by this builder in Bangalore

Reliaable Dollar Collony Phase 2B
No filings
Reliaable Dollar Collony Phase 2E
No filings
Reliaable Dollar Collony Phase 2F
No filings
Reliaable Dollar Collony Phase 2C
No filings
Reliaable Dollar Collony Phase 2D
No filings
Reliaable Dollar Collony Phase 1C
No filings

Other RERA-registered projects in Gattahalli

Major developers building in Gattahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.