Bangalore/Project record

K-RERA · the public record

SAI GOPAL APARTMENT

· VANISHREE BUILDERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

70%construction reportedQ1 2026 filing
6units not bookedof 16 · Q1 2026 filing
16registered unitsK-RERA registration · read 16 Jul 2026

The record · free to read

Registration read 16 Jul 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

Not recorded

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 16 Jul 2026

Inventory & scale

What this registration contains.

2 BHK
4
3 BHK
12

Filed categories, unchanged · K-RERA registration · read 16 Jul 2026

The whole registration

0.2registered acres

74.0registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1259/410/PR/030525/007707

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Land area875 sq m (0.2 acres)
Homes registered16
Tower/wing entries1
Unit mix4 × 2 BHK, 12 × 3 BHK

In context

Density74 homes per acre
Density in context40th percentile of 4882 projects in this register (median 82.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units16Total inventory registered with K-RERA.
Official carpet area1,708 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area1,762 sqmUseful scale context when comparing density and project cost.
Registered land area875 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.01Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)16Separate filed counts; these categories may overlap and are not added together.
Covered-parking field16Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberHDW-LBPAS-45587/24-25/BPUse this to match the sanctioned drawing set shown by the builder.
Plan approval date26-12-2024
Project start date01-05-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2 BHK425%339 sqm
3 BHK1275%1,370 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
SAI GOPAL4161614.975 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 16 official flat/unit rows, matching the 16 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK12103.3-123.9 sqm52.9-63.5 sqm12
2 BHK484.7 sqm43.4 sqm4

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
SAI GOPAL1684.7-123.9 sqm43.4-63.5 sqm16
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
101SAI GOPAL13 BHK103.3 sqm52.9 sqm1
102SAI GOPAL13 BHK123.9 sqm63.5 sqm1
103SAI GOPAL13 BHK115.3 sqm59.0 sqm1
104SAI GOPAL12 BHK84.7 sqm43.4 sqm1
201SAI GOPAL23 BHK103.3 sqm52.9 sqm1
202SAI GOPAL23 BHK123.9 sqm63.5 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

3 of 20 compliance document slots are filed as Not Applicable; the remaining 17 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantPooja Katigar2581512021Dharwad, Karnataka - 580020
EngineerNikhil KatweHDW/BL/12310/2023 242024Dharwad, Karnataka - 580028
ArchitectARUN PATTARCA/2012/574382018Dharwad, Karnataka - 580031
ContractorBHAGAVAN PANDITH-1999Nashik, Maharashtra - 422006

Builder track record

RERA filing

Vanishree Builders has 19 other K-RERA-registered projects in our records (average reported construction progress 77%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.51 Cr collected from buyers, ₹0.69 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹0.69 Cr) exceeded buyer collections (₹0.51 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress55% → 70% (+15 pts)
Units sold/booked as registered10/16 (62%)
Buyer collections in available QPRs₹2.39 Cr
Escrow withdrawals in available QPRs₹1.25 Cr (0.52x collections)
  • Construction progress moved from 55% to 70% across the filed QPR window.
  • The builder has drawn 0.52x of buyer collections from escrow (about 52% of the ₹2 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹41.9 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: STATE BANK OF INDIA HOSAYALLAPUR - DHARWAD IFSC Code : SBIN0007964 Pin Code : 580001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~389 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kempegowda Int'l Airport384 km
Outer Ring Road / Manyata389 km
MG Road / city centre393 km
Bellandur–Marathahalli belt402 km
Whitefield IT hub404 km
Electronic City407 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Vanishree Builders. View Vanishree Builders's full track record →
Vanishree Builders has 19 projects registered in Bangalore, 4 completed.
1 complaints on the K-RERA register against Vanishree Builders in Bangalore.

Other projects by this builder in Bangalore

SAI RAJ Apartment
Filing overdue · 100% built · 56% sold
SAI Sharan Apartment
Filing overdue · 100% built · 56% sold
SAI Sudha Apartment
Filing overdue · 100% built · 62% sold
SAI Chandrama Apartment
No filings

Other RERA-registered projects in Jayanagar

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in SAI Gopal Apartment?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 16 Jul 2026